OPINION OF THE COURT
The plaintiff Key International Manufacturing, Inc. (hereinafter Key), a New York corporation, commenced the present action in order to recover compensation for the economic losses it suffered in connection with a construction project on Staten Island. In its complaint, Key alleged that it was forced to remedy, "at substantial cost”, various design and construction defects caused by the negligence and breach of contract committed by several defendants, including the respondents Albert Melniker, an architect, and Toder/ Schwartz, a professional engineering firm. The Supreme Court, finding that the respondents were not in privity of contract with Key, and holding that the absence of privity bars Key from recovering for its economic losses against the respondents, awarded summary judgment to them. On this appeal by Key, we find that issues of fact as to whether privity exists and as to whether Key may have standing to sue on a contract theory based on its status as a third-party beneficiary preclude the awarding of summary judgment.
I
The Supreme Court properly held, in light of controlling precedent, that the owner of a construction project may not recover compensation for economic damages caused by the negligence of an architect or engineer with whom it is not in privity of contract. This rule is analogous to the well-settled rule that the manufacturer of a product may not be held liable to a party with whom it is not in privity for economic losses suffered as a result of a defect in the product.
In the area of products liability, the majority rule, as reflected in the seminal case of Seely v White Motor Co. (63 Cal 2d 9,
The New York Court of Appeals has adhered to the majority view outlined above (see, Schiavone Constr. Co. v Elgood Mayo Corp.,
The rule which eliminates tort liability for economic losses in the context of defective products has been applied in New
In Alvord & Swift v Muller Constr. Co. (NYLJ, Sept. 15, 1976, at 7, col 4, affd
Consistent with the Alvord & Swift case (supra), this court held, in Ossining Union Free School Dist. v Anderson LaRocca Anderson (
Also, in Lake Placid Club Attached Lodges v Elizabethtown Bldrs. (
Thus, the rule which bars recovery for economic losses in the absence of privity as applied to actions against architects or engineers is also settled as a matter of New York law. We note that analogous rules apply in actions against other professionals as well (see, Viscardi v Lerner,
II
Key was not a named party to any written contract with the respondents. However, the respondents did enter into written contracts with a wholly owned subsidiary of Key, i.e., Key Land Development Corporation (hereinafter Key Land). Christopher Jeffries, an officer of both Key and Key Land, stated that the latter corporation’s activities in connection with the project were "at the direction of, and under the control of, Key, the property’s owner”. Jeffries also averred that he had informed the respondents that in executing contracts with them, he was "acting on behalf of the owner, which was Key”. These assertions by Jeffries, contained in his affidavit in opposition to the respondents’ motions for summary judgment, indicate the existence of an issue of fact as to whether Key Land acted as an agent for Key and, if so, whether that agency relationship was disclosed.
The respondents do not dispute the general rule that "a principal [e.g., Key] is liable on contracts entered into on its behalf by an authorized agent [e.g., Key Land]” (Plymouth Rock Fuel Corp. v Leucadia, Inc.,
Essentially, the respondents take the position that if they had a grievance against Key, they would be precluded from obtaining redress because the "corporate veil” would shield Key from any liability, unless they offered evidence sufficient to "pierce” that "veil”. The respondents then proceed to argue that where the tables are turned, and where it is Key which seeks to impose liability against them, the burden falls upon Key to offer sufficient proof to establish, as a matter of law, that Key Land was merely a "dummy” or "shell” corporation. The respondents argue that this burden was not met.
The respondents may, in fact, be correct in arguing that if Key is to ultimately succeed in this action on an agency theory, it will have to prove that Key Land was the agent of Key, so that the former corporation acted under the direction of the latter. Several factors may ultimately be considered by the trier of fact in making this determination (see, e.g., Worldwide Carriers v Aris S. S. Co.,
Ill
The awarding of summary judgment to the respondents
"[I]t is the intention of the promisee which is of primary importance in ascertaining whether a party is to be considered an intended beneficiary” (Goodman-Marks Assocs. v Westbury Post Assocs., 70 AD2d 145, 148, citing Fosmire v National Sur. Co.,
"Where performance is to be made directly to a third party, that party is generally deemed an intended beneficiary of the contract and is entitled to enforce it or there is, at least, a presumption that the contract was for the benefit of the third party” (Nepco Forged Prods. v Consolidated Edison Co.,
The respondents argue, in essence, that the holding of Port Chester Elec. Constr. Corp. v Atlas (
The facts of the case of Fourth Ocean Putnam Corp. v Interstate Wrecking Co. (
The case of Lake Placid Club Attached Lodges v Elizabethtown Bldrs. (
Although there is dicta in Port Chester Elec. Constr. Corp. v Atlas (supra, at 656) to the effect that "[generally * * * the
For the foregoing reasons, summary judgment was improperly granted to the respondents.
IV
Key also applied for leave to serve an amended complaint in order to name Key Land as an additional party plaintiff. There is no dispute that Key Land may properly be joined pursuant to the permissive joinder provisions of CPLR 1002 (a). The respondents argue, however, that any claim to be asserted by Key Land based on allegations of negligence would be time barred pursuant to the applicable Statute of Limitations (CPLR 214 [4]); Key responds by arguing that any claim to be asserted by Key Land based on allegations of negligence should be deemed to have been interposed at the time that Key’s original claims were interposed, pursuant to CPLR 203 (e), so that no valid Statute of Limitations defense exists.
Pursuant to CPLR 203 (e), a "claim asserted in an amended pleading is deemed to have been interposed at the time the claims in the original pleading were interposed, unless the original pleading does not give notice of the transactions, occurrences, or series of transactions or occurrences, to be proved pursuant to the amended pleading”. Since it cannot be realistically argued by the respondents that Key’s original complaint did not give notice to them of the transactions upon which Key Land’s claims will be based, they argue, in essence,
The persuasiveness of this argument is vitiated by the holdings of the Court of Appeals in Duffy v Horton Mem. Hosp. (
The Appellate Division, First Department, has squarely held that when a new party plaintiff is joined in order to allow it to assert a claim on its behalf, its claim will be deemed to have been interposed as of the time of the interposition by the preexisting plaintiff of its similar or identical claim (Schleidt v Stamler,
We emphasize, however, that the rule permitting the claim of a newly joined plaintiff to relate back to the earlier claim of
V
In conclusion, the order under review is reversed insofar as appealed from. The motions of Toder/Schwartz and Melniker for summary judgment dismissing the complaint insofar as it is asserted against them are denied. Key’s cross motion for leave to serve an amended complaint adding Key Land as an additional party plaintiff is granted in its entirety, without prejudice to the assertion by the respondents of defenses based on the Statute of Limitations as against the newly joined plaintiff Key Land.
Kunzeman, Rubin and Spatt, JJ., concur.
Ordered that the order is reversed insofar as appealed from, with costs, the motions of the respondents are denied, and the plaintiff’s motion for leave to serve an amended complaint is granted in its entirety, without prejudice to the assertion by the respondents of defenses based upon the Statute of Limitations as against the newly joined plaintiff Key Land.
