¶ 1. This appeal involves an employment contract dispute. Employee James Kernz negotiated a three-year contract with J. L. French Corporation that required the company to pay Kernz's salary and benefits for the remainder of the contract term if the company terminated Kernz without "just cause." Nine months into the contract, French Corporation terminated Kernz and Kernz sued for breach of contract, alleging he was terminated without "just cause." Kernz sought more than $260,000 under the contract damages clause. French Corporation countered that Kernz was terminated for "just cause" and argued in the alternative that, even if it terminated Kernz without just cause, the damages clause was an unenforceable "penalty clause." Following a jury trial in which French Corporation was found liable for termination without just cause, the trial court concluded that the damages clause was enforceable and entered judgment in favor of Kernz. French Corporation appeals from that judgment. Post-trial, the trial court entered an order denying Kernz's motion for pre-verdict interest, which forms the basis of Kernz's cross-appeal.
Background
¶ 2. On April 27, 2000, Kernz and French Corporation entered into a three-year employment contract. French Corporation offered language which permitted *131 the company to terminate Kernz if he "shall be neglectful of the interest of the employer, or manage the business under his supervision badly or in a manner unsatisfactory to employer, or shall be guilty of misconduct." During negotiations, Kernz requested, and the French Corporation negotiator agreed, to replace the above provision with "just cause" language. The following shows the agreed change with the stricken language and the added language in italics:
If the Employee is terminated for''just cause," or by mutual agreement, shall be neglectful of the interest of the-employer, or manage the busmess-nnder his supervision badly or in a manner unsatisfactory-to-employer, or-shall be guilty of-misconduct, the Employer may at their option terminate this agreement and such services and compensation on thirty (30) days notice to the Employee.
¶ 3. In early 2001, Kernz was accused of committing "two safety violations of. .. plant employee safety rules." In one incident, Kernz was observed entering a secured area containing a 3,500-ton press without following the proper "lock-out" procedures. In the other incident, Kernz was observed on foot in an area where pedestrian traffic was prohibited. French Corporation terminated Kernz's employment.
¶ 4. Kernz sued, alleging that French Corporation breached the contract by terminating him without "just cause." Kernz sought a pretrial ruling declaring the phrase "just cause" ambiguous and permitting the introduction of extrinsic evidence of the phrase's meaning. The trial court concluded that the phrase "just cause" was ambiguous and ruled that extrinsic evidence would be permitted. French Corporation moved to prevent testimony of any witness's subjective uncom- *132 municated belief regarding the meaning of "just cause." The trial court denied that motion.
¶ 5. The trial was held in two phases: the first phase was tried before a jury to determine liability, and the second phase was tried to the court to determine damages. During the liability phase, Kernz testified that, during contract negotiations, he sought inclusion of the phrase "just cause" because "I needed something where . . . [French Corporation] didn't have the option to terminate in the contract unless it was for some intentional wrongdoing." The deposition testimony of Don Porritt, the negotiator for French Corporation, was read to the jury. The French Corporation negotiator testified that "just cause to me would be if you intentionally do something." The negotiator also provided examples of intentional misbehavior that he believed constituted "just cause" for termination at French Corporation, including "fighting on company property, reporting under the influence of drugs or . . . theft,. .. those sorts of things that had already been outlined in the [employee] handbook." The French Corporation negotiator gave no further testimony about the employee handbook and there was no evidence that French Corporation employees generally understood that "just cause" has a particular meaning. Notably, neither Kernz nor the French Corporation negotiator testified that he communicated his belief about the meaning of "just cause" to the other. There was no special verdict asking the jury to make a finding on the meaning of "just cause." The jury was simply asked if French Corporation terminated Kernz for "just cause" as set forth in the contract, and the jury answered that question "No."
¶ 6. During the damages phase, the trial court considered whether the contract damages clause ("If *133 employment is terminated for other than 'just cause' or mutual agreement, the Employer shall pay salary and benefits for [the] remainder of the contract.") was an illegal penalty clause or an enforceable stipulated damages provision. The trial court concluded that the damages clause was an enforceable stipulated damages provision and determined that Kernz was due $263,993.02 under the contract.
¶ 7. Kernz sought pre-verdict interest on the damages under the theory that the damages were liquidated. French Corporation objected to the taxation of prejudgment interest. The trial court agreed with French Corporation and denied Kernz's post-trial motion for pre-verdict interest.
Appeal
I. Whether Evidence of the Parties' Uncommunicated Subjective Interpretations of "Just Cause" Was Properly Admitted
¶ 8. French Corporation argues that "just cause" is unambiguous and, therefore, the trial court improperly admitted extrinsic evidence, including uncommu-nicated subjective interpretations of "just cause." Whether a contract is ambiguous is a question of law, which we review
de novo. State v. Windom,
¶ 9. "The ultimate aim of all contract interpretation is to ascertain the intent of the parties."
Eden Stone Co. v. Oakfield Stone Co.,
¶ 10. We first determine whether a disputed contract provision is ambiguous. "Contract language is considered ambiguous if it is susceptible to more than one reasonable interpretation."
Danbeck v. American Family Mut. Ins. Co.,
¶ 11. The question here is whether the contract phrase "just cause" is ambiguous and, if so, whether the parties' uncommunicated subjective beliefs regarding that phrase are admissible extrinsic evidence where the negotiating parties had substantially the same bargaining power, actually negotiated the contract term, and had substantially the same understanding of the phrase.
A. Whether the Phrase "Just Cause" is Ambiguous
¶ 12. The employment contract does not define "just cause." French Corporation argues that the phrase is unambiguous because "just cause" has a plain and ordinary meaning defined in case law. That definition, the company contends, is contained in
Millar v. Joint School District,
¶ 13. Apart from its reliance on the definition of "good and sufficient cause" found in
Millar,
French Corporation has not attempted to define "just cause." Our own research reveals case law defining "just cause" for purposes of terminating a tenured municipal employee.
See Safransky v. Personnel
Bd.,
¶ 14. These definitions provide no assistance here. First, the definitions are different from each other, thereby giving lie to the notion that "just cause” has a single "plain and ordinary" meaning. Second, the definitions are geared toward public sector employment. While they may provide a meaning for the term "just cause" contained in some public employment con *137 tracts, nothing before ns suggests that either definition is generally understood to define "just cause" for purposes of private employers or employees.
¶ 15. In
Yauger v. Skiing Enterprises, Inc.,
¶ 16. At the same time, we agree with French Corporation that a phrase is not ambiguous simply because it is general or broad.
See id.
at 499. A phrase need not have a single dictionary definition to avoid ambiguity.
See Ruff v. Graziano,
B. Whether Evidence of the Parties' Uncommunicdted Subjective Interpretations of an Ambiguous Contract Provision is Admissible When the Negotiators for Each Party Share a Substantially Similar Subjective Interpretation
¶ 17. The facts in this case are unusual. Neither the parties nor this court has uncovered a case with similar facts. Kernz alleges that both he and the French Corporation negotiator testified, in substance, that he believed at the time of the negotiations that the phrase "just cause" meant intentional wrongdoing. At trial, and now on appeal, French Corporation disclaims the subjective belief of its own negotiator. Accordingly, we are faced with the question whether a party may present evidence that the negotiators for two parties to a contract had substantially the same belief regarding the meaning of an ambiguous contract phrase when there is no evidence that those beliefs were communicated.
¶ 18. We stress that this issue arises in the context of a phrase that was actually the subject of negotiation and where the parties had substantially equal bargaining power. Kernz successfully requested that the phrase "just cause" be substituted for other language. This is not a situation in which the contract was unilaterally drafted by an employer with substantially *139 greater bargaining power and we do not comment on whether our analysis would be different under such facts.
¶ 19. French Corporation argues that the uncom-municated subjective beliefs of parties to a negotiation are not admissible to show the meaning of an ambiguous contract phrase. In its motion in limine seeking to exclude testimony of its own negotiator and Kernz, French Corporation quoted from 17A Am. Jur 2d Contracts § 352, at 368 (1991):
It is not necessarily the real intent, but the expressed or apparent intent, which is sought. Indeed, a party's subjective, undisclosed intent is immaterial to the interpretation of a contract. The court will not attempt to ascertain the actual mental processes of the parties in entering into the particular contract; rather the law presumes that the parties understood the import of their contract and that they had the intention which its terms manifest.
¶ 20. French Corporation's general proposition, that a party's uncommunicated subjective intent is inadmissible, has support in the case law. In
Hart v. Hart,
"It must be borne in mind that the office of judicial construction is not to make contracts or to reform them, but to determine what the parties contracted to do; not necessarily what they intended to agree to, but what, in a legal sense, they did agree to, as evidenced by the language they saw fit to use."
Marion v. Orson's Camera Ctrs., Inc.,
¶ 21. Thus, the creation of an enforceable agreement is usually predicated on the language used in the contract and the
expressed
intentions of the parties.
See Shetney v. Shetney,
¶ 22. Interpreting Wisconsin law, the Seventh Circuit Court of Appeals has stated:
Yet "intent" does not invite a tour through [a party's] cranium, with [that party] as the guide. Like most other states, Wisconsin takes an objective view of "intent." "The intent of the parties [to be bound] must necessarily be derived from a consideration of their words, written and oral, and their actions." Household Utilities, Inc. v. Andrews Co.,71 Wis. 2d 17 , 28-29, 236 N.W2d 663, 669 (1976). Secret hopes and wishes count for nothing. The status of a document as a contract depends on what the parties express to each other and to the world, not on what they keep to themselves.
Skycom Corp. v. Telstar Corp.,
¶ 23. For example, in
Gerruth Realty Co. v. Pire,
*142 ¶ 24. While the above cases can be read as providing support for French Corporation's argument that evidence of uncommunicated subjective belief of one party is generally not admissible to supply meaning to an ambiguous contract term, we need not fully explore that topic because we have a different situation. Here, there is evidence that negotiators on both sides held substantially the same uncommunicated belief regarding the ineaning of an ambiguous contract phrase. To repeat, we have not found, and the parties have not produced, a case addressing this scenario. However, for the reasons set forth below, we conclude that when a contract term is ambiguous, a circuit court may admit evidence which, if believed, shows that the two negotiating parties agreed to the ambiguous term while independently possessing substantially the same understanding of the term, even though this understanding was not communicated.
¶ 25. We are guided here by the overarching principle that guides all contract interpretation: "The ultimate aim of all contract interpretation is to ascertain the intent of the parties."
Eden Stone Co.,
¶ 26. Accordingly, the admissibility question for trial courts is whether the proffered evidence is sufficient to support a factual finding that the negotiating parties held substantially similar subjective beliefs regarding the ambiguous term.
¶ 27. At trial, Kernz testified that he included the phrase "just cause" in the contract because "I needed something where . . . [French Corporation] didn't have the option to terminate in the contract unless it was for some intentional wrongdoing." The French Corporation negotiator testified that "just cause to me would be if you intentionally do something." When the French Corporation negotiator was asked about his intent in agreeing to a "just cause" provision, he explained that he "was just basically following the outline of things that made just cause at [French Corporation] at that time, which would be fighting on company property, reporting under the influence of drugs or . . . theft, . . . those sorts of things that had already been outlined in the [employee] handbook." While Kernz and the French Corporation negotiator do not use identical phrasing, we conclude that a jury could find their interpretations of "just cause" to be substantially the same. Accordingly, we affirm admission of this extrinsic evidence of the meaning of "just cause."
II. Whether the Stipulated Damages Clause Was an Enforceable Liquidated Damages Clause or an Unenforceable Penalty Provision
¶ 28. The parties dispute whether the stipulated damages provision in the termination clause of the
*144
employment contract is reasonable and, thus, an enforceable liquidated damages provision, or unreasonable and, thus, an unenforceable penalty provision. Following the terminology used in the seminal case on this topic,
Wassenaar v.
Panos,
¶ 29. The review of a stipulated damages provision is a mixed question of law and fact.
Id.
at 525. Where, as here, the facts as found by the trial court are undisputed, only legal issues remain and our review is
de novo.
2
See Westhaven Assocs., Ltd. v. C.C. of Madison, Inc.,
¶ 30. "A stipulated damages provision will be enforced if it is reasonable under the totality of the circumstances."
Westhaven,
¶ 31. Courts generally assume that "bargains are enforceable and that the party asking the court to intervene to invalidate a bargain should demonstrate the justice of his or her position."
Wassenaar,
[W]here neither party complains of inequity in bargaining power, the party seeking to avoid a stipulated damages provision bears both the "burden of proving facts which would justify the trial court's concluding that the clause should not be enforced" and the burden of persuading the court that the provision should not be enforced.
Westhaven,
*146 A. Intent of the Parties
¶ 32. The first factor we examine when determining the reasonableness of a stipulated damages provision is whether the parties intended the provision to provide liquidated damages or, instead, to provide a penalty. As explained in
Koenings v. Joseph Schlitz Brewing Co.,
¶ 33. On the issue of intent, the trial court made a number of findings:
Several factors forge the Court's decision in this regard. Among them are one, clearly, [Kernz] was looking for job security and advanced standing in his profession. Secondly, the parties were aware that the diecasting operation is tied to the automotive industry, an industry which business waxes and wanes and ebbs and flows. Thirdly, the parties certainly were aware that should downturns in business occur that it would be extremely difficult for [Kernz] to secure employment in the future let alone comparable employment without a formal education. Fourth, [Kernz] had recently been terminated by French about three months earlier after French acquired Nelson Metals. Fifth, [Kernz] obviously did not want to relocate.
¶ 34. Accordingly, to the extent we have factual findings regarding intent, those findings support the view that the parties intended to compensate Kernz for his reasonably anticipated but undeterminable damages rather than penalize French Corporation for breaching the agreement. However, for the reasons expressed in Koenings, we do not give this factor great weight in our consideration.
*147 B. Whether the Damages Were Ascertainable at the Time of Contracting, and Whether the Stipulated Damages Reasonably Forecast the Actual Damages
¶ 35. In
Westhaven,
this court examined the second and third
Wassenaar
factors (whether the damages can be estimated at the time of contracting and whether the stipulated damages provisions are a reasonable forecast of the harm caused by the breach) and concluded that although both factors use a prospective-retrospective approach, "the fact remains that [these factors] require two distinct inquiries: the reasonableness of the stipulated damages provision at the time of contracting and the reasonableness of the provision when compared with actual damages after a breach."
Westhaven,
¶ 36. Before addressing the merits of the parties' arguments, however, we detail the trial court's relevant factual findings on the second and third Wassenaar factors.
• Kernz suffered a loss of prestige in the industry.
• Kernz incurred relocation costs, including the costs of securing a new residence in Wisconsin.
• Kernz was not interested in relocating and had been "reasonably settled" in Florida.
• Kernz lost business opportunities as a result of the breach.
• "[A]t the time of the contract it's relatively easy to determine what the salary and the benefits were going to be under the agreement."
• "[A]t the time of trial looking back, it's very *148 difficult to ascertain the damages incurred by [Kernz] where he was forced to leave his home in Florida, where he was forced to relocate and purchase a new residence."
• "[T]he Court believes that the parties did include consequential damages at the time that the contract was reached."
• "The parties contemplated more than just insured salary for 3 years."
• "[T]he parties contemplated that [Kernz] would become a member of the Corporate Business Development Team," which "objectively is viewed as an elevation in rank."
• Kernz was required to seek new employment because of the breach.
1. Reasonableness of the Clause at the Time of Contracting
¶ 37. French Corporation argues that the clause is unreasonable because it was simple to calculate the compensation due Kernz under the contract. Therefore, according to French Corporation, Kernz's potential damages were readily ascertainable at the time of contracting. French Corporation also contends that calculations of Kernz's potential damages at the time of contracting should not include consequential damages because there is no evidence that the parties ever negotiated to compensate Kernz for consequential damages. As French Corporation states:
[T]here is simply no evidence that [Kernz] and French [Corporation] contracted to provide for the protection of Kernz against any other damage besides those al *149 lowed under the black letter rule. In other words, Kernz has not shown that he and French [Corporation] agreed that the stipulated damages clause was intended to protect him against so-called consequential damages.
¶ 38. First, French Corporation misperceives its burden. It is French Corporation that seeks to avoid imposition of the stipulated damages clause and, therefore, French Corporation has the burden to persuade this court that we should not enforce the stipulated damages provision. Kernz did not have to prove that the contract was intended to compensate him for consequential damages.
¶ 39. Second, to the extent French Corporation discusses the parties' intent in relation to the second Wassenaar factor, its argument is misplaced because evidence of the parties' intent is considered under the first Wassenaar factor.
¶ 40. Third, it is obvious that the parties contemplated Kernz's potential damages, including consequential damages, at the time of contracting, otherwise the contract would have followed "black letter law" and required Kernz to mitigate his damages and compensate him only for his out-of-pocket expenses. As in
Wassenaar,
the parties foresaw that Kernz might incur consequential damages, and contracted to compensate Kernz accordingly.
See Wassenaar,
¶ 41. Assessing the reasonableness of this particular contract clause at the time of contracting is difficult. At the time of contracting, it was not known if or when French Corporation might terminate Kernz *150 without just cause, whether Kernz might secure new employment at a higher or lower salary, or what other damages Kernz might incur. Thus, the reasonableness of the clause seemingly depends on an unknown: the circumstances under which it would be invoked. To the extent the contract contemplates that if Kernz is terminated three weeks into the contract and promptly secures comparable new employment at a higher salary, the damages clause seems to be an unreasonable penalty clause. In contrast, termination after a longer time period, combined with a failure to find comparable employment, makes application of the clause much more reasonable. We conclude it makes little sense to void a damages clause because there are some possible scenarios that would produce punitive results while, at the same time, many other scenarios producing fair results. Accordingly, we give little weight to the reasonableness of this particular damages clause at the time of contracting.
2. Reasonableness of the Clause After the Breach
¶ 42. Next we address the reasonableness of the stipulated damages provision when compared with actual damages after the breach.
See Westhaven,
¶ 43. French Corporation argues that Kernz will receive a "windfall" as a result of the stipulated damages provision. French Corporation alleges that Kernz "suffered [compensatory] damages of approximately $30,000.00 while the stipulated damage clause rewards Kernz $263,993.02," or "10 times [Kernz's] actual damage [s]," an amount that is "grossly disproportionate to [the compensatory] damage sustained." We disagree.
¶ 44. First, French Corporation's calculations are imprecise. Kernz was terminated on January 19, 2001. *151 He was unemployed for two months before he obtained a job that paid him $89,000 for eight months and then switched to another job that paid him $90,000. Under the French Corporation contract, Kernz was entitled to a $110,000 salary. According to French Corporation's brief, Kernz lost $30,000 in lost wages and benefits during the two months he did not work. However, over the next twenty-five months until the end of the contract, Kernz will likely suffer approximately $42,333.33 in lost wages, producing a total of approximately $72,333.33 in compensatory damages, rather than the $30,000 figure quoted by French Corporation. 3 $263,993.02 is 3.65 times greater than $72,333.33; a significant disparity, but far short of the "10 times" disparity alleged by French Corporation.
¶ 45. Second, the $72,333.33 figure does not include consequential damages suffered by Kernz. These damages are difficult to ascertain,
see Wassenaar,
¶ 46. In this case, French Corporation has the burden to demonstrate that the stipulated damages clause is unreasonable. Based upon the totality of the circumstances, we conclude that French Corporation has not met its burden.
Cross-Appeal
¶ 47. Kernz argues that the trial court erroneously denied his request for pre-verdict interest because the amount awarded was determinable as of the date of the breach. "Whether preverdict interest may be awarded is a question of law. Preverdict interest is available when damages are fixed and determinable or may be measured according to a reasonably certain standard."
Loehrke v. Wanta Builders, Inc.,
¶ 48. French Corporation argues that the damages in this case were undeterminable because it did not know whether it would succeed on its legal argument that the stipulated damages provision was an unenforceable penalty provision and, therefore, it could not calculate Kernz's potential damages. A similar argument was addressed and rejected in Wenzel Brothers, 88 *153 Wis. 2d at 697. In Wenzel Brothers, the defendants disputed whether a statutorily mandated liquidated damages provision applied. Id. at 694. After concluding that the statute did apply, the court awarded prejudgment interest over the defendants' objection because the defendants disputed only their liability under the statutory liquidated damages provision; there was no dispute over the computation of damages. Id. at 698. As in Wenzel Brothers, French Corporation merely disputes its liability under the stipulated damages clause. The amount the company owed under the contract was easily calculable: salary and benefits for the remainder of the contract term.
¶ 49. French Corporation attempts to distinguish Wenzel Brothers from the instant case by arguing that Wenzel Brothers involved the applicability of a statutory liquidated damages provision rather than a dispute over the reasonableness of a stipulated damages clause. We think this is a distinction without a difference, and French Corporation does not persuade us otherwise.
Conclusion
¶ 50. We affirm the judgment entered against French Corporation. We reverse the trial court's order denying Kernz's request for pre-verdict interest. Kernz contends that he is owed pre-verdict interest from January 19, 2001, the day French Corporation breached the contract, to November 19, 2001, the day he was tendered a settlement offer under Wis. Stat. § 807.01(4). French Corporation does not dispute this assessment and, therefore, we remand the cause to the trial court to enter an order consistent with this decision.
*154 By the Court. — Judgment affirmed; order reversed and cause remanded with directions.
Notes
All references to the Wisconsin Statutes are to the 2001-02 version unless otherwise noted.
French Corporation points to testimony which seemingly conflicts with some of the circuit court's findings, but the company does not argue that the circuit court's findings are clearly erroneous. We decline to develop this argument for French and then resolve the issue.
See State v. Pettit,
For purposes of this decision, we will assume Kernz will maintain the job paying $90,000 for the duration of the three-year term.
