OPINION OF THE COURT
Joseph Kenny (hereinafter plaintiff), an employee of the Harris Structural Steel Co. (hereinafter Harris), was injured when he fell approximately 35 feet while working on the construction of a new building at Hunter College owned by the Dormitory Authority of the State of New York (hereinafter the Authority). The Authority had contracted with the George A. Fuller Co. (hereinafter Fuller) to be the construction manager on the project, and had also entered into separate agreements with Harris, for the erection of the structural steel, and with the Thomas Crimmins Contracting Co., Inc. (hereinafter Crimmins), for the excavation and construction of the foundation walls. Crimmins had, in turn, subcontracted with the Brisk Waterproofing Co., Inc. (hereinafter Brisk) to waterproof the foundation walls. Under the Authority’s agreements with Harris and Crimmins, Fuller was designated as the owner’s “representative” in the performance of the work. In addition, these agreements included a “save harmless” clause running to the benefit of the owner and its agents. It is undisputed that the plaintiff was not provided with any scaffolding, safety belts, netting, or other safety equipment in the performance of his work.
Plaintiff and his wife subsequently commenced this suit for personal injuries and loss of services against Fuller, the construction manager, for alleged violations of sections
After all of the evidence was submitted on the issue of liability, the court directed a verdict in favor of the plaintiffs and against Fuller on the ground of the latter’s violation of sections 240 (subd 1) and 241 (subd 6) of the Labor Law. The remaining questions were then submitted to the jury for determination, and while Harris was found to have acted negligently, codefendants Crimmins and Brisk were both exonerated. The court thereupon granted third-party plaintiff Fuller’s motion for a directed verdict against Harris on the theory of contractual indemnification and this appeal followed.
The principal issue raised on appeal is whether Fuller was entitled to contractual indemnification from Harris. The plain and simple language used in the contract between Harris and the Authority, as well as the surrounding facts and circumstances, lead this court to conclude that the indemnification provision required Harris to indemnify Fuller, as agent of the owner, for all damages incurred as a result of Harris’ work, regardless of how the claim arose (see Vey v Port Auth. of N. Y. & N. J.,
In order to determine whether Harris, the claimed indemnitor, may be held liable to Fuller on the theory of contractual indemnification, it must first be determined whether Fuller, the claimed indemnitee, was properly held liable to the plaintiffs under sections 240 (subd 1) and 241 (subd 6) of the Labor Law (see Greenberg v City of New York,
The primary distinction between sections 240 (subd 1) and 241 (subd 6) is that the latter requires a determination of whether the safety measures actually employed on a job site were “reasonable and adequate” (see Long v Forest-Fehlhaber,
Wfyen, in 1969, the Legislature amended section 240 of the Labor Law and repealed the then existing section 241 and enacted the present provision, it was noted, inter alia, that the Labor Law was enacted for the sole purpose of protecting workmen, and that, under the state of the law as it then existed (i.e., prior to the proposed ámendment), a subcontractor, because he was named in sections 240 and 241, could effectively relieve an owner or general contractor of his liability for safe work practices by the routine
“Under the * * * sections [proposed to be amended] an owner and/or contractor would be inclined to choose a subcontractor predicated on price, disregarding the subcontractor’s safety measures. This, of course, is dangerous to the welfare and health of the men working on the project and would defeat the original intent of the Labor Law * * *
“The [proposed] bill restores to the owner and general contractor the responsibility, where it properly belongs, in their selection of subcontractors and in the progress of the work in regard to the safety of all men on the job. Under * * * Sections 240 and 241 [as they now read] * * * the non-delegable duty has shifted from the general contractor and owner to the subcontractor, making him responsible for many things that he has no control of, such as coordination and overall supervision of the work * * *
“In order to accomplish liability upon the owner and contractor and to specifically provide a greater measure of safety for workers, [former] Section 241, which was eliminated in 1962, is reinstated by this bill” (sponsoring memorandum of Senator Calandra and Assemblyman Amann, NY Legis Ann, 1969, p 408; emphasis supplied).
The Legislature, however, in addressing the problem, merely chose to employ the generic term “contractor”, and in the absence of any statutory definition, varying interpretations have been placed upon that term in attempting to determine which “contractors” ought to be encumbered with nondelegable responsibilities under the relevant Labor Law provisions (compare Rosenbaum v Lefrak Corp.,
In 1981, the Court of Appeals addressed the issue by holding, inter alia, that “prime contractors” lacking privity with the general contractor are not to be held liable under sections 240 and 241 unless they have been delegated “the authority to supervise and control” that portion of the
“Although sections 240 and 241 now make nondelegable the duty of an owner or general contractor to conform to the requirement of those sections (Haimes v New York Tel. Co.,
“Our interpretation of the statutory ‘agent’ language appropriately limits the liability of a contractor as agent for a general contractor or owner for job site injuries to those areas and activities within the scope of the work delegated or, in other words, to the particular agency created.”
The Russin case, however, is a limited holding, and is directly applicable to the case at bar only insofar as it relates the status of a statutory “agent” to the legislative concept of “coordination and overall supervision of the work” (NY Legis Ann, 1969, p 408).
The specific question of whether a construction manager can be held to be a “contractor” within the meaning of sections 240 and 241 of the Labor Law was answered in the affirmative in Carollo v Tishman Constr. & Research Co. (
In the instant case, Fuller, under its agreement with the owner was required, inter alia, to analyze design programs and costs; co-ordinate implementation of the design; prepare all cost analyses for the owner; continuously review and make recommendations concerning construction detailing; review the contract documents; recommend the establishment and implementation of a comprehensive safety program for the project; and, during the construction stage, establish procedures for and maintain co-ordination among the owner, architect, the various contractors and itself concerning all aspects of the project and regularly observe the work being performed by the contractors by inspecting the site for the purposes of controlling quality, co-ordinating, expediting and reporting construction progress. Absent a more specific legislative directive, one would be hard-pressed to envision a “contractor” better fitting the stated statutory purpose.
In addition, this court is of the further view that Fuller was an “agent” of the owner within the meaning of sections 240 and 241 and, thus, was independently chargeable with the duties imposed by the foregoing sections. Here, the agreement between the Authority and Harris specifically provided that “in the performance of [this] work the Owner shall be represented by [the] George A. Fuller Company”. Having been designated by the owner as its contractual agent in the performance of the structural steel contract, Fuller had the undoubted authority to “supervise and control” this aspect of the work (see Russin v Picciano & Sons,
In light of the foregoing and in view of the evidence adduced at the trial, it is our belief that the trial court acted properly in granting judgment in favor of the plaintiffs against Fuller under subdivision 1 of section 240 of the Labor Law (see Pereira v Herman Constr. Co.,
In this arm’s length transaction between sophisticated business concerns, the designation of Fuller as the owner’s representative in the Harris contract is susceptible of little misinterpretation. The words “representative” and “agent” have been deemed synonymous and interchangeable (see Sunset Milling & Grain Co. v Anderson, 39 Cal 2d 773, 778; Texas Power & Light Co. v Adamson,
Harris, under its contract with the Authority, agreed to assume the “entire responsibility and liability for any and all damage * * * to all persons * * * arising out of, or occurring in connection with * * * the work provided for in this contract” and to “indemnify and save harmless the owner, its agents, servants and employees, from and against any and all loss * * * that the owner, its agents; servants and employees, may sustain as the result of any such claim” (emphasis supplied). This strong, unequivocal hold-harmless provision leaves little doubt that Harris was to be held responsible for any and all claims made against Fuller as the owner’s representative in the performance of
Finally, we consider Fuller’s contention that the jury improperly exonerated cothird-party defendants Brisk and Crimmins. The evidence reveals that the jury may well have concluded that the waterproofers did not contribute to the plaintiff’s injury in any way. Though there may be differing conclusions to be drawn from the testimony, we do not find the jury’s verdict to be contrary to the weight of the evidence (see Goehle v Town of Smithtown,
The judgment must, accordingly, be affirmed.
Mollen, P. J., Weinstein and Thompson, JJ., concur.
Judgment of the Supreme Court, Kings County, dated October 23, 1981, affirmed, without costs or disbursements.
Notes
The Authority was not named as a party defendant.
