80 Mo. 573 | Mo. | 1883
This is the third time this case has been here on defendant’s appeal. It is an action to recover damages for property of plaintiff destroyed by fire, which, plaintiff' alleges, was set ont by defendant’s negligence. The pleadings are substantially the same as when the cause was here before, and the facts are not materially different. See 70 Mo. 253.
It appears from the transcript now before us, that at the June term, 1880, of the Caldwell circuit court, an order was made requiring defendant to supply the pleadings in the cause within thirty days of the close of that term, and continuing the case to the next term. It does not appear why the defendant was required to supply the pleadings, but it may be infei’red that it was through its fault that they were missing. On the first day of the succeeding term, defendant having failed to supply the pleadings, plaintiff had leave to file his petition as a substitute for the original, and on the same day a judgment by default was rendered against defendant, which, on the fifth day of the term, on defendant’s motion, was set aside, whereupon plaintiff withdrew the petition he had filed as a substitute, and defendant filed substitutes for the original pleadings, together with an amended answer, which differed from the original only in that it contained an allegation that by virtue of its charter it had the right to use locomotive engines, moved and worked by steam as a motive power to draw cars and trains, upon which, however, no issue was made by the replication. Defendant, thereupon, applied for a postponement of the trial for two days, which was refused, and then applied for a continuance of the cause to the next term, on account of the absence of material witnesses, and of what occurred in relation to the substitution of the pleadings, etc. . This application was refused, and the propriety of that action of the court is the principal matter for consideration, if we adhere to our rulings in the cause when last here.
It was the duty of the defendant to supply the missing
The following are instructions asked by defendant, the first of which was refused and the second given:
1. It appearing from the uncontradicted evidence offered by the defendant that the engine which it is alleged communicated the fire to plaintiff’s property was provided with the latest, best, and most approved machinery, appliances and contrivances, to prevent the escape of fire, and that a careful and competent engineer was operating said engine at the time, and that he used reasonable care in operating the same to prevent the escape of fire, therefore, the frima facie case relied upon by the plaintiff, is rebutted and the finding of the court must be for the defendant.
2. If the court, sitting as a jury, finds from the evidence, that the engine which it is alleged communicated the fire to plaintiff’s property, was provided with the latest, best, and most approved machinery, appliances and contrivances to prevent the escape of fire, and that a careful and competent engineer was operating the engine at the time and that he used reasonable care in operating the same to’ prevent the escape of fire therefrom, then the court mus^ find for the defendant.
Defendant’s counsel states in his brief that “ on the evidence as it now stands there is no pretense that the fire was not there before the engine passed.” Eolsom, at the former trial, testified that “immediately after the passage of the train going east he saw fire spring up after it and on the right of way adjoining plaintiff’s premises.” His
The plaintiff asked no instructions; none were given except that at defendant’s instance. The cause was tried by tbe court without a jury and tbe judgment which was for plaintiff is affirmed.