KENNEDY TANK & MFG. CO., INC., Appellant-Defendant/Third-Party Plaintiff, and Hemlock Semiconductor Corp., and Hemlock Semiconductor, LLC, Appellant-Third-Party Defendants, v. EMMERT INDUSTRIAL CORPORATION, d/b/a Emmert International, Appellee-Plaintiff.
No. 49A02-1507-CT-934
Court of Appeals of Indiana
April 22, 2016
67 N.E.3d 505
John R. Maley, T. Joseph Wendt, Barnes & Thornburg LLP, Indianapolis, IN, Attorneys for Appellee.
A. Richard M. Blaiklock, Charles R. Whybrew, Edward D. Thomas, Lewis Wagner, LLP, Indianapolis, IN, Attorneys for Appellant Hemlock Semiconductor Corporation and Hemlock Semiconductor, LLC.
MAY, Judge.
[1] Kennedy Tank and Manufacturing Company appeals the denial of its motion to dismiss a lawsuit Emmert International brought against Kennedy. The Indiana statute of limitation on which the trial court appears to have relied1 is preempted by a federal statute establishing a shorter limitations period. As Emmert did not bring its lawsuit within that period, Kennedy‘s motion should have been granted, and we must therefore reverse.2
Facts and Procedural History
[2] In April 2011, Kennedy hired Emmert International to transport a piece of
[3] Kennedy would not pay Emmert the additional amounts. Between June and August of 2013 the parties discussed submitting the dispute to arbitration, and on January 22, 2015, Emmert sued Kennedy for breach of contract, or in the alternative, unjust enrichment. On February 13, 2015, Kennedy moved to dismiss3 on the ground Emmert did not bring the action within the eighteen-month limitations period set forth in
Discussion and Decision
[4] Kennedy moved to dismiss Emmert‘s complaint pursuant to
[5] Our standard of review of a grant or denial of a motion to dismiss pursuant to
[6] A motion to dismiss under
[7] Because federal law is the supreme law of the land under the Supremacy Clause of the United States Constitution, state laws that interfere with or are contrary to federal law are invalidated under the preemption doctrine. In re Beck‘s Superior Hybrids, Inc., 940 N.E.2d 352, 356 (Ind.Ct.App.2011). When conducting a preemption analysis we start with a presumption that Congress did not intend to supplant state law. Id.
[8]
[9] It determined the statutory language expresses Congress’ intent that the eighteen-month statute of limitations shall apply to all carriers who bring civil actions to recover charges for transportation of interstate goods.
Arctic is a motor carrier and all deliveries at issue were interstate. Therefore, the plain meaning of the statute states that Arctic must bring its claims to recover Freight Charges within eighteen months of the claims’ accrual (i.e., within eighteen months of delivery or tender of delivery).
Id.
[10] In the absence of explicit preemption language, we examine the structure and purpose of the federal statute for implicit preemptory intent. Basileh, 912 N.E.2d at 818. Preemptive intent may be inferred if the scope of the statute indicates that Congress intended federal law to occupy the legislative field4 (“field
It does not appear our Indiana appellate courts have addressed the preemptive effect of
[11] A Georgia appellate court surveyed decisions addressing this question in Exel Transp. Servs., Inc. v. Sigma Vita, Inc., 288 Ga.App. 527, 654 S.E.2d 665, 669 (2007). It held
Moreover, “nothing in the text or context of
[12] The court in Arctic Express also surveyed a number of federal decisions, all of which found preemption:
This Court is persuaded by the logic in the recent case of CGH Transp. Inc. v. Quebecor World Logistics, Inc., 2006 WL 1117659, 2006 U.S. Dist. LEXIS 22657 (E.D.Ky. Apr. 24, 2006) [aff‘d, 261 Fed.Appx. 817 (6th Cir.2008)]. In CGH Transport, the Eastern District of Kentucky was faced with precisely the same facts present in the instant case: the carrier claimed that the shipper had not paid its bills for freight charges, and the shipper sought to defend itself under the eighteen-month statute of limitations in
49 U.S.C. § 14705(a) . The carrier argued that under Central Transport Int‘l v. Sterling Seating, Inc., 356 F.Supp.2d 786 (E.D.Mich.2005) and Transit Homes [of Am., Div. of Morgan Driveaway, Inc. v. Homes of Legend, Inc., 173 F.Supp.2d 1185 (N.D.Ala.2001)] its state law claims were not preempted by federal law, and therefore, the eighteen-month statute of limitations did not apply. Id., 2001 WL 1464152, *2, at *4. The court found that while the carrier could bring state-based causes of actions, it had to do so within the federal statute of limitations:Central Transport and Transit Homes considered whether the Interstate Commerce Commission Termination Act (“ICCTA“) gave rise to a cause of action for unpaid shipping charges for the purposes of establishing federal question jurisdiction. However, as neither case discussed the applicable statute of limitations, they are distinguishable from the instant case. That [the carrier‘s state law] claims are not preempted by federal law does not preclude the defendants from relying on federal law to provide an affirmative defense. [The carrier here] states that its claims are based on breach of contract; unjust enrichment/quantum meruit; conversion; a constructive trust theory; and fraud. Even so styled, as these causes of action attempt to recover charges for interstate transportation and services, they are subject to the eighteen-month statute of limitations. Artful pleading will not cloak a plaintiff‘s claim from the otherwise applicable law.
Id. at *2, at *5 (internal citations omitted) (emphasis added). Similarly, in the case at bar, just because Arctic can bring its state-law claims, because the parties agree that they are not preempted by federal law, it does not follow that a federal-law statute of limitations defense is unavailable to Del Monte.
[13] The Arctic Express court went on to note that
while the state causes of action themselves may not be preempted by federal law, the state statute [sic] of limitations are in direct conflict with
49 U.S.C. § 14705(a) , and would therefore be preempted by such time limitation.... In this case, the Bankruptcy Court, nor any party, has explained why a six-year state law statute of limitations does not directly conflict with an eighteen-month statute of limitations under federal law. The purpose of the Interstate Commerce Act was to provide a uniform system of regulations for the transportation of goods and people in interstate commerce for the nation, and to do away with inconsistent state policies. See S. Pac. Transp. Co. v. Commercial Metals Co., 456 U.S. 336, 344, 102 S.Ct. 1815, 72 L.Ed.2d 114 (1982). Permitting Ohio‘s state statute of limitations to trump the federal statute of limitations at49 U.S.C. § 14705(a) would certainly “stand as an obstacle” to Congressional intent. Therefore, in this case, to the extent that Ohio law provides otherwise, Ohio law is preempted by49 U.S.C. § 14705(a) .
[14] The trial court in the case before us found no conflict preemption because “there is no reason why a shipper would not be able to comply with both statutes, at the same time, by bringing a claim prior to the 18 month deadline in the ICCTA.” (Appellant‘s App. at 10.) It cited to no legal authority to support the premise that there is no “conflict” if a party can comply with both statutes simply by bringing an action within the shorter limitations period, and in light of the Arctic Express reasoning, we decline to so hold. The Indiana statute of limitations is preempted by the federal statute.
Conclusion
[15] As Emmert did not bring its action against Kennedy within the applicable limitations period, Kennedy‘s motion to dismiss should have been granted. We must therefore reverse.
[16] Reversed.
NAJAM, J., concurs.
RILEY, J., concurs in part, and dissents in part, with separate opinion.
RILEY, Judge concurring and dissenting.
[17] I concur with the majority‘s determination that
[18] On appeal, Emmert insists that even if the eighteen-month federal statute of limitations applies—as this court holds that it does, its claim should not have been dismissed because Kennedy should be estopped from asserting the statute of limitations as an affirmative defense. As detailed by the majority in Footnote 2, Emmert‘s argument on this issue is devoid of any cogent reasoning or appropriate citations.
[19] In its Complaint, Emmert asserted that in completing its performance pursuant to its contract with Kennedy, it incurred expenses of $691,301.03 in addition to the original contract price of $197,650. According to Emmert, after it delivered Kennedy‘s equipment on November 11, 2011,
Kennedy paid Emmert $150,000 but refused to pay any additional amounts owed Emmert. The parties continued to discuss their dispute into January 2013. In June—August 2014, the parties even discussed submitting their dispute to arbitration for resolution. Then, in September 2014, Kennedy for the first time advised Emmert that it refused to pay Emmert anything additional, asserting that Emmert‘s claim for the owed amounts—attributable to the valued service it provided Kennedy—was now time-barred pursuant to
49 U.S.C. § 14705(a) .
(Appellant‘s App. pp. 14-15).
[20] Subsequently, in response to Kennedy‘s motion to dismiss, Emmert filed a response arguing that there were factual questions as to whether principles of equitable estoppel precluded dismissal. “The federal doctrine of equitable estoppel applies to federal statutes of limitation.” F.D.I.C. v. Kime, 12 F.Supp.3d 1113, 1119 (S.D.Ind.2014). As the Seventh Circuit Court of Appeals has explained, “[e]quitable estoppel suspends the running of the statute of limitations during any period in which the defendant took active steps to prevent the plaintiff from suing, as by promising the plaintiff not to plead the statute of limitations pending settlement talks or by concealing evidence from the plaintiff that he needed in order to determine that he had a claim.” Singletary v. Cont‘l Ill. Nat‘l Bank & Trust Co. of Chi., 9 F.3d 1236, 1241 (7th Cir.1993). “Equitable estoppel necessarily raises questions of fact.” F.D.I.C., 12 F.Supp.3d at 1119.
[21] In this case, Emmert asserted that
[t]he facts here fit the ... definition for equitable estoppel perfectly. The parties discussed resolution of this dispute for months after Kennedy Tank refused to pay Emmert in full. They continued to discuss resolution, including the option of submitting their dispute to arbitration, even after the [eighteen]-month statute of limitations on which Kennedy Tank now relies had expired.
During those months of discussion and potential resolutions, Kennedy Tank never mentioned
§ 14705(a) , directly or indirectly. Instead, it continued to negotiate with Emmert. Only after Kennedy Tank was certain that the [eighteen]-month statute had passed did it refuse Emmert full payment and claim any lawsuit to recover the amount it owed Emmert would be time-barred.Simply, Kennedy Tank strung Emmert along long enough to avoid payment to Emmert. Kennedy Tank “by words, acts, and conduct led [Emmert] to believe that it would acknowledge and pay the claim, if, after investigation, the claim were found to be just, but when, after the time for suit had passed, [it broke] off negotiations and denie[d] liability and refuse[d] to pay.” Those facts, asserted in Emmert‘s complaint, raise a question of fact regarding application of equitable estoppel that prevents dismissal of Emmert‘s claims....
(Appellant‘s App. p. 302) (fifth, sixth, seventh, and eighth alterations in original) (quoting Bomba v. W.L. Belvidere, Inc., 579 F.2d 1067, 1071 (7th Cir.1978)). In addition, Emmert raised the same equitable estoppel argument during the hearing on Kennedy‘s motion to dismiss.
[22] Because the trial court ruled in Emmert‘s favor—i.e., it denied Kennedy‘s motion to dismiss on its finding that
