In
Kennedy Building Associates v. Viacom, Inc.,
Westinghouse, the corporate predecessor of CBS’s corporate predecessor, operated an electrical transformer repair facility on the Kennedy Building property, which resulted in contamination of the property with polychlorinated biphenyls (PCBs) and chlorobenzenes. Westinghouse sold the property in 1980, and a partner in Kennedy Building Associates bought the property and transferred it to Kennedy in 1982.
Kennedy
I,
On remand, the district court held the matter in abeyance for a year and a half until Viacom and the Minnesota Pollution Control Agency could arrive at a substantive plan for remediation.
See
Kennedy was not satisfied with the remediation plan because it would leave contamination in place underground and inside the building. Once the Minnesota *533 Pollution Control Agency had issued the Decision Document, Kennedy sought a contested-case hearing in the agency. When that was denied, Kennedy sought review by writ of certiorari of the agency’s remedy selection. The Minnesota Court of Appeals dismissed the writ on the grounds that the agency’s decision was not final and that “the [agency] order does not preclude [Kennedy] from litigating appropriate remediation in [its] pending federal district court action.” In the Matter of the Kennedy Building Superfund Site Petition for Contested Case Hearing, No. A05-994 (Minn.Ct.App. Aug. 2, 2005).
Back in the district court, Kennedy moved to modify the original injunction to incorporate the requirements of the Decision Document, to order Viacom to remediate the interior of the building, and to require Viacom to post a bond to assure performance of the remedial work that was left contingent in the Decision Document on future demolition or disturbance of the building or its floor. Counsel for Viacom explained at the hearing that Viacom had undergone a corporate reorganization, with the result that the entity called “Viacom” would no longer be responsible for the Kennedy site and that the entity with such responsibility would now be known as “CBS Corporation.” The district court noted that the Decision Document gave Kennedy no right to enforce the remediation plan, that no remediation had taken place so far, and that if Kennedy were to decide to redevelop the property in a way that required excavating deeper than twelve feet, there was no way to assure that remediation would happen promptly enough to make such development commercially feasible.
In light of the evidence adduced at the hearing, the district court issued an injunction including the following requirements:
(1) Viacom was ordered to “perform those actions prescribed in the [Decision Document] which will prevent the release of PCBs and chlorobenzenes into uncontaminated soil and groundwater consistent with the purposes of MERA.”2006 WL 305279 , at *3.
(2) Viacom was ordered to provide to the court and to Kennedy copies of the results of tests required by the Decision Document. In the event a test should show migration of the contaminants, Viacom was obliged to submit a remediation plan within 30 days of receiving the test result. Id.
(3) In the event the future development of the parcel should result in excavation of soils left in place under the Decision Document’s remediation plan (i.e., soil deeper than twelve feet or underneath the building), Kennedy was obliged to notify Viacom, whereupon Viacom was required to submit to the court a remediation plan within 30 days of receiving the notification. Id.
(4) To ensure that the relief in paragraph 3 above would be timely provided and adequately funded, the court required Viacom and its corporate successors to post a bond or irrevocable letter of credit. Id. In a subsequent order, the court set the amount of the bond at $1,311,000 and required that it be maintained for five years. Kennedy Building Associates v. CBS Corp., No. 99-CV-1833 (April 21, 2006).
CBS appeals the injunction making a large number of arguments that can be categorized into three types of objection: the injunction is not sufficiently specific, it is not supported by the evidence before the court, and the court had no power to require CBS to post a performance bond.
We review for abuse of discretion a district court’s issuance of a permanent injunction.
Taylor Corp. v. Four Seasons
*534
Greetings, LLC,
CBS attacks the first item of the injunction, requiring it to perform those requirements of the Decision Document that will prevent the release of PCBs and chloro-benzenes into uncontaminated soil and groundwater “consistent with the purposes of MERA.”
See
CBS further contends that the record does not support the issuance of any MERA injunction because there is no record evidence of continuing releases of PCBs or chlorobenzenes. In
Kennedy I,
we concluded that there were continuing releases within the meaning of MERA. We relied on the district court’s finding of fact after trial that PCBs were continuing to migrate in the soil and groundwater because of the presence of mineral oil in the soil.
CBS also contends that the district court found the plume had stabilized, based on the following statement by the court at the modification hearing: “Now, the MPCA seems to think that that’s all [remediation to twelve feet] that’s needed at this time. It says that the plume has not moved, and right now the condition of the situation is as it is.” The district court made this statement in denying Kennedy’s request for an immediate order to clean up the soil more than twelve feet below the surface. The statement cannot be characterized as a definite finding that the plume has stabilized, any more than the Decision Document can be so characterized; both the Decision Document and the injunction are provisional. Both are premised on the presumption that we cannot be sure what the plume is doing without continuing testing; contaminants may well migrate, and if *535 so, further remediation will be required. The Decision Document requires monitoring “for a minimum of five years and, if the monitoring indicates that the contamination plume is expanding or migrating, the MPCA will require ground water remedial action.” The injunction, of course, requires the same. CBS has by no means shown that the injunction is based on a clearly erroneous finding of fact.
CBS next contends that the district court lacked power to require it to post a performance bond. We begin by examining the language of MERA. Minn.Stat. Ann. § 116B.07 provides:
The court may grant declaratory relief, temporary and permanent equitable relief, or may impose such conditions upon a party as are necessary or appropriate to protect the air, water, land or other natural resources located within the state from pollution, impairment, or destruction.
(Emphasis added.) The statute certainly appears to be broad enough to allow the court to require a bond to be posted for five years to assure that foreseeable events of excavation or groundwater migration will not result in pollution to the soil and water of Minnesota.
CBS relies on
Grupo Mexicano de Desarrollo,
S.A
v. Alliance Bond Fund, Inc.,
Finally, CBS contends that the district court should have abstained from exercising jurisdiction on the grounds of comity and federalism. This argument is substantially redundant of Viacom’s argument on the first appeal that the administrative consent order was entitled to preemptive effect barring MERA relief. We rejected that argument in
Kennedy I
and remanded for refinement of the MERA injunction.
*536 We remand for the district court to specify which requirements of the Decision Document are included as items of the MERA injunction; in all other respects, the order of the district court is affirmed.
