The facts as alleged in the complaint are as follows. On August 19, 1993, the plaintiff, a subcontractor, submitted a bid to the defendant, a general contractor, for the plumbing, heating, ventilating and air conditioning portions of work to be done on a project to renovate Shepaug Valley/Middle High School in Washington Depot, Connecticut. The defendant submitted a bid to perform the construction on the project, which bid named the plaintiff as a subcontractor and incorporated the plaintiff's bid. Thereafter, the defendant was awarded the contract and informed the plaintiff that the plaintiff was named subcontractor. The defendant, however, employed another subcontractor to perform the plumbing, heating, ventilating and air conditioning work on the project.
The defendant moves to strike the third count of the CT Page 3066 plaintiff's complaint on the ground that
General Statutes
The awarding authority shall not permit substitution of a subcontractor for one named in accordance with the provisions of this section or substitution of a subcontractor for any designated subtrade work bid to be performed by the general contractor's own forces, except for good cause.
In Ardmare Construction v. Freeman,
In Unisys Corporation, the court stated, at page 694:
Although in Spiniello Construction Co. the plaintiff who sought the injunction was a bidder, in Ardmare Construction Co. we did not tailor the remedy solely to that class of persons. Indeed, we quoted with approval from Scanwell Laboratories, Inc. v. Shaffer,
424 F.2d 859 ,864 (D.C. Cir. CT Page 3067 1970), the following: "`[T]he public interest in preventing the granting of contracts through arbitrary or capricious action can properly be vindicated through a suit brought by one who suffers injury as a result of the illegal activity, but the suit itself is brought in the public interest by one acting essentially as a "private attorney general."'" (Emphasis added.) Ardmare Construction Co. v. Freedman, supra, 504. In Ardmare Construction Co., we pointed out that the scope of our holding in Spiniello Construction Co. was "to strike the proper balance between fulfilling the purposes of the competitive bidding statutes and preventing frequent litigation that might result in extensive delay in the commencement and completion of government projects to the detriment of the public." Ardmare Construction Co. v. Freedman, supra, 505.
In Milward Corporation v. City of Hartford,
Based on the Milward Corporation case, the plaintiff does not have standing to allege a violation of
Standing is the legal right to set judicial machinery in motion. One cannot rightfully invoke the jurisdiction of the court unless he has, in an individual or representative capacity, some real interest in the cause of action, or a legal or equitable right, title or interest in the subject matter of the controversy. (Citation omitted.)
"If a party is found to lack standing, the court is without CT Page 3068 subject matter jurisdiction to determine the cause." Tomlinson v. Board of Education,
Based on the foregoing, the court must dismiss the third count of the plaintiff's complaint sua sponte.
It is further noted that General Statutes
Any party whose financial interests may be affected by a decision on a claim alleging a violation(s) of the contract bidding procedures set forth in [
4b-91 to4b-100 ] may file a petition with the Commissioner [of Public Works] seeking a ruling on whether there has been a violation.
The Commissioner is then required to designate a presiding officer to hear and rule on the claimant's grievance. Regs. Conn. State Agencies
Therefore, the regulations adopted pursuant to General Statutes
For the reasons stated above the court dismisses the third count of the plaintiff's complaint.
HENDEL, J. CT Page 3069
