56 Mo. App. 192 | Mo. Ct. App. | 1894
— The plaintiff brought this suit before a justice of the peace to recover of defendant telegraph company the' statutory penalty of $200 for the neglect on the part of defendant to transmit a certain dispatch promptly and with impartiality and good faith. Revised Statutes, section 2725.
At a trial of the cause in the circuit court where the plaintiff had judgment, and from which this appeal is prosecuted, it appeared from the evidence that at 7:45 a. M. of June 15, 1892, the plaintiff delivered a day dispatch to the defendant’s operator at Salem, in Dent county, for transmission to W. E. Kendall at Lebanon, Laclede county, the two points being distant one hundred, and forty miles. The dispatch could only be sent by way of Cuba where it was necessary to resend the same to the terminal point. It was received at Lebanon at 5:20 n. M. of the day of its delivery.
These facts established for plaintiff a prima facie right of recovery. It was shown that the usual time required to transmit a dispatch from Salem to Lebanon was from fifteen to forty-five minutes. The length of time intervening between the delivery of the dispatch and its receipt was such as to raise a presumption of negligence. In such case the burden was upon the defendant to show, which it did not, that its wire was engaged as the reason for the delay in transmitting the dispatch. Section 2725, supra. No excuse of any kind was shown for the delay.
The defendant requested the court, sitting as a jury, to declare the law of the case to be that the plaintiff was not entitled to recover, unless it appeared
It is true that by the terms of the contract entered into between the plaintiff and defendant printed on the dispatch sent by plaintiff it was provided that the company would not be liable for damages or statutory penalties, in any case unless the claim therefor was presented in writing within sixty days after the filing of the dispatch with it for transmission. A condition of this kind inserted in a contract for the transmission of a dispatch, though a limitation upon the liability of the company, will be upheld where the time fixed in which the sender’s claim is to be presented is not unreasonably short. The period provided in the condition of the contract in question we think was not unreasonable. Smith-Frazier B. & S. Co. v. Tel. Co., 49 Mo. App. 99.
But the difficulty lying in the defendant’s way is, that while its defense was an affirmative one there was no evidence adduced tending to show that the plaintiff did not comply with the requirement of the stipulation. If the defendant intended to rely on the defense of this contractual limitation it should have offered some evidence to sustain the same. We cannot presume that the plaintiff did not present his claim within the time required by the contract. Plaintiff was not obliged to prove this in order to make out his case. If it was a fact that the plaintiff had omitted to present his claim within the agreed period of time, this was a fact which wpuld bar his recovery and the burden of showing it logically devolved upon the defendant. It follows that the circuit court did not err in rejecting the defendant’s theory of the ease. The finding was for the right party.
But the judgment is erroneous in that it does not
The judgment of the circuit court will, therefore, be reversed and a judgment entered here in conformity to the requirements of the statute just referred to.
The cost of the appeal must be adjudged against the plaintiff.