Pacific Coast Construction, Inc., and Fong Holdings, LLC, and Peter Fong (collectively, “Fong”) petition for reconsideration of our decision in
Ken Hood Construction v. Pacific Coast Construction,
In our original opinion, we concluded — contrary to the trial court’s conclusion — that the parties had formed a contract for Pacific Coast to build a restaurant on land owned by Fong in Washington County.
In its petition for reconsideration, Pacific Coast notes that our disposition did not include a remand to the trial court on the contract claim. “A remand is necessary,” Pacific Coast asserts, “to permit the trial court to make a determination that the contract was breached, and for damages.” For his part, Fong asserts that, in light of our disposition of the contract claim, we were required to address his assignment of error challenging the quantum meruit award.
We agree with Pacific Coast that remand is necessary for the trial corut to determine whether Fong breached the contract and, if so, what damages Pacific Coast suffered. We also agree with Fong that we must address his challenge to the trial court’s award in quantum meruit. For the reasons set out below, we reverse on that assignment of error.
As we explained in our original opinion, Pacific Coast sought the same amount of damages under two alternative theories: contract and quasi-contract, or
quantum meruit. Id.
Pacific Coast’s theory was that it had a contract with Fong and that Fong had breached that contract. But it also alleged, in the alternative, that, if there were no contract, it would be entitled to the same damages as a measure of the value of its services under a
quantum meruit
theory.
See Mount Hood Community College v. Federal Ins. Co.,
The trial court, having concluded that there was no contract, proceeded to the second step of the sequential analysis and addressed whether Pacific Coast was entitled to damages under a quantum meruit theory; it ultimately awarded those damages. In light of our conclusion that the parties had a contract, that was error. Accordingly, we reverse the award of damages under the quantum meruit claim and remand for the trial court to consider Pacific Coast’s contract claim.
In our original opinion, we also concluded — again, contrary to the trial court’s conclusion — that Pacific Coast had timely filed its construction lien.
Ken Hood Construction,
Reconsideration allowed; former opinion modified and adhered to as modified; former disposition withdrawn; reversed and remanded on appeal and on cross-appeal; award of attorney fees to Fong reversed.
