“ ‘Attachment is an ancillary or provisional remedy to aid in the collection of a
money demand
by seizure of property
in advance of trial and
judgment.’ ”
(Doyka v. Superior Court
(1991)
In this case, Kemp Bros. Construction, Inc. (Kemp), a prime contractor on two public works projects, sued its former subcontractor, Titan Electric Corporation (Titan), for breach of contract, and sought a pretrial right to attach order. The court found Kemp was entitled to the remedy, not because Kemp had affirmatively shown the probable validity of its claim or established other requisite criteria, as was its burden, but because Titan could not “re-litigate” the issue of its breach of contract. The court’s allusion to the preclusive effect of prior litigation referred to a proceeding at which a Los Angeles Unified School District (LAUSD) hearing officer determined Kemp had grounds under Public Contract Code section 4107, subdivision (a)(3) and (7), 2 for substituting Titan out of its subcontract.
The court erred. “Collateral estoppel is an equitable concept based on fundamental principles of fairness. For issue preclusion purposes it means that a party ordinarily may not relitigate an issue that was
fully and fairly litigated
on a previous occasion.”
(Sandoval v. Superior Court
(1983)
Ordinarily, when the court gives an incorrect legal reason for its ruling, we look for any other correct legal basis on which to sustain the order.
(Rappleyea v. Campbell
(1994)
Such is the case before us, where both the minute order and the reporter’s transcript demonstrate the court never engaged in the process of weighing the evidence because it improvidently agreed with Kemp’s argument that Titan was barred from “re-litigat[ing]” the issue of its alleged breach of contract and ruled accordingly. For that reason, we reverse and remand with directions to the court to weigh the factors relevant to Kemp’s burden of showing entitlement to the attachment order. In exercising its discretion, the court “must consider the relative merits of the positions of the respective parties and make a determination of the probable outcome.”
(Loeb & Loeb
v.
Beverly Glen Music, Inc.
(1985)
FACTS
As a preliminary matter, at the time of oral argument, we considered Kemp’s motion to file a late brief and submitted it for determination in conjunction with our disposition of the appeal on the merits. We further allowed Kemp to present its argument conditionally, subject to being stricken depending on our decision whether to allow the late filing of Kemp’s brief. (See Cal. Rules of Court, rule 8.220(a)(2).) We now grant Kemp’s motion. Because Kemp’s brief was presented to the court and Titan’s counsel only days before oral argument, Titan requested an opportunity to file a reply brief prior to our submission of the case. However, we deem a reply brief unnecessary: Titan carried its burden of affirmatively establishing reversible error in its opening brief and at oral argument.
Turning to the facts, we remind the parties it is not our role to engage in an assessment of the evidence, and our summary does not establish the truth of any facts for any purpose. We simply place the controversy in context by reciting relevant material as variously alleged or attested in the pleadings and papers in the court’s file, including those documents of which Titan and Kemp have requested we take judicial notice. (Evid. Code, § 452, subd. (d).) On remand, neither party may derive any evidentiary benefit or suffer any detriment from our recitation.
The Electrical Subcontracts and Events Leading to Kemp’s Substituting Titan Out
In March 2003, Kemp entered into two prime contracts with the LAUSD for public works improvement projects at Huntington Park Elementary School and the Los Angeles Center for Enriched Studies (LACES). Under subcontracts valued at more than $2 million, Titan agreed to furnish labor, material, and equipment necessary for the electrical portion of both projects.
All went well for a while, but in February 2004, for reasons that are in dispute, Kemp agreed to advance payroll payments to Titan for certain workers on the Huntington project. The advances were to be drawn against Titan’s accounts receivable for work Titan had already completed. Kemp made the payments until the latter part of April, then ceased. When Titan could not meet the payroll on its own, its employees stopped working. Kemp hired A&R Electric (A&R) to replace Titan on the two projects, and by the afternoon of April 29, 2004, A&R, essentially using Titan’s equipment and former employees, began performing the electrical work covered by Titan’s subcontract.
On the same day, April 29, 2004, Kemp submitted a request to LAUSD to authorize the substitution of A&R on both the Huntington and LACES projects. The proceeding is statutory, falling under the Subletting and Subcontracting Fair Practices Act, Public Contract Code section 4100 et seq., which, in pertinent part, confers a statutory right on the subcontractor originally listed by the prime contractor to perform the specified work. (Pub. Contract Code, § 4107;
R.J. Land & Associates Construction Co. v. Kiewit-Shea
(1999)
Titan objected to the substitution. The matter was set for hearing before Mark Hovatter, an engineer and director of LAUSD’s facilities contracts. By the time the hearing went forward in August 2004, both the Huntington and LACES projects had been completed by A&R and another electrical contractor. In November, Hovatter issued two decisions approving Kemp’s substitu tion of Titan on both projects. Hovatter found, “An informal arrangement had been made between Kemp and Titan under which Kemp advanced payments to Titan from February 2004 through April 2004. This was an arrangement above and beyond their contractual requirement and being done by Kemp because they believed it was in their best interest. When Kemp chose to discontinue this action, Kemp was not in violation of its contractual requirement to pay Titan, ffl Once Kemp discontinued their arrangement of early payments to Titan, Titan employees abandoned the project because they had not been paid by Titan. It was apparent during the hearing that Titan made no reasonable effort to timely complete the work Kemp could reasonably expect Titan to perform.” Hovatter granted Kemp’s request to substitute Titan as subcontractor on both projects under Public Contract Code section 4107, subdivision (a)(3) and (7).
Kemp’s Lawsuit and Application for Writ of Attachment
Kemp then filed a civil action against Titan, alleging breach of contract as to both projects and seeking some $1.5 million in damages. The same day it filed its complaint, Kemp sought an ex parte right to attach order against Titan’s accounts receivable, alleging it had heard from a third party that Titan was going to receive a seven-figure settlement in another matter and the anticipated asset had to be earmarked quickly for Kemp’s benefit lest Titan’s owners flee the country with the money. Kemp further claimed it had shown a probability of succeeding on the merits of its lawsuit because Hovatter had conclusively determined Titan breached the subcontract. 3
The court denied ex parte relief, but scheduled a hearing two weeks later. After
The right to attach order is in the inscrutable amount of $684,915.97. Kemp sought $1.5 million in damages, and neither the order, the moving papers, nor any other documentation we have uncovered in our comprehensive search of the record, discloses how the court calculated the attachment amount down to the last penny. Moreover, respondent did not direct our attention or, so far as we can ascertain, the trial court’s attention to any contract provision setting forth the formula or mechanism for calculating the damages flowing from Titan’s alleged performance default. 5
DISCUSSION
Titan advances a number of arguments for reversing the right to attach order. Because one ground is dispositive, we do not discuss the others. As we have noted,
ante,
“ ‘the plaintiff has the burden of proving (1) that his claim is one upon which an attachment may be issued and (2)
The rules of collateral estoppel have been addressed by our Supreme Court for at least 140 years. As recently reiterated by that court, “ ‘Collateral estoppel precludes relitigation of issues argued and decided in prior proceedings.’ ”
(Pacific Lumber Co.
v.
State Water Resources Control Bd.
(2006)
The party asserting collateral estoppel bears a “heavy” burden of proving all of these factors
(Pacific Lumber, supra,
The case here does not meet the threshold requirements for application of collateral estoppel. In the first place, Hovatter’s decision in the substitution proceeding makes
no
mention of any of Kemp’s or Titan’s rights or obligations under the subcontract. Quite to the contrary, it expressly finds the advance payroll payment agreement between Kemp and Titan was an “informal arrangement,” “above and beyond” their contractual relationship.
In the second place, as noted,
ante,
the issue a party seeks to preclude must have been
identical
to and “
‘necessarily decided
in the former proceeding.’ ”
(Pacific Lumber, supra,
Our conclusion that there was no determination of breach of contract issues in the substitution proceeding is reinforced by the absence of any suggestion in the record that the parties
submitted
anything other than statutory substitution issues to Hovatter. We do not decide there can never be a collateral estoppel flowing from the hearing officer’s findings in a statutory substitution proceeding: That question is not before us. But under the circumstances here, where there is no evidence the issue of Titan’s alleged breach of contract was “fully and fairly litigated on a previous occasion”
(Sandoval v. Superior Court, supra,
DISPOSITION
The attachment order is reversed. The case is remanded with directions to the trial court to weigh all relevant factors in accordance with this decision and determine whether Kemp carried its burden of establishing the criteria for obtaining relief. Titan shall recover its costs on appeal.
Bedsworth, Acting P. J., and O’Leary, J., concurred.
Respondent’s petition for review by the Supreme Court was denied May 9, 2007, S150602.
Notes
All further statutory references are to the Code of Civil Procedure unless otherwise stated.
Respectively, the referenced provisions allow substitution “[w]hen the listed subcontractor fails or refuses to perform his or her subcontract” (Pub. Contract Code, § 4107, subd. (a)(3)), and “[w]hen the awarding authority, or its duly authorized officer, determines that ... the subcontractor is substantially delaying or disrupting the progress of the work.” (Pub. Contract Code, § 4107, subd. (a)(7).)
In its cross-complaint, Titan alleges 11 causes of action, including, inter alia, breach of contract, conversion, trespass to chattels, and promissory estoppel.
At oral argument, Kemp’s counsel made a somewhat equivocal assertion that the trial court did not really rely on a collateral estoppel theory. In light of the fact that Kemp raised and urged the collateral estoppel issue at the 11th hour in the trial court and justified it as grounds for affirmance in its last minute respondent’s brief, we find disingenuous the argument that the trial court went straight to an evaluation of the evidence supporting Kemp’s right to an attachment order and ruled solely on that ground. Moreover, as discussed more fully, post, the argument regarding such judicial deliberations is utterly without support in the record.
We mention this glaring omission because an attachment order may be issued only if the claim sued upon is, inter alia, for money based upon a contract and is of a “fixed or readily ascertainable amount.” (§ 483.010, subd. (a).) Although damages need not be liquidated, they must be measurable by reference to the contract sued upon, and their basis must be reasonable and certain.
(CIT Group/Equipment Financing, Inc. v. Super DVD, Inc.
(2004)
In passing, we note a further problem with the trial court’s determination. While giving collateral estoppel effect to Hovatter’s decision, the court observed Titan had not yet exhausted its administrative remedies, i.e., the decision had not achieved finality. Ironically, absent finality, collateral estoppel does not apply.
(Pacific Lumber, supra,
Certain facts of which we have taken judicial notice arose
after
the court issued its order. These facts bolster our conclusion that collateral estoppel does not apply. Briefly, Hovatter, in response to Titan’s postorder request for clarification,
amended
his decision, unequivocally stating, “[T]he breach of Titan’s subcontract with Kemp Brothers was
not
an issue that was addressed during the substitution hearing.” (Italics added.) Then, when Titan petitioned for writ of administrative mandate from Hovatter’s decision, the superior court, denying relief, observed, “Titan Electric’s contention that LAUSD has no power to decide whether Titan Electric or Kemp Bros, breached the subcontract between them, is irrelevant because the hearing officer
clearly stated in writing that such issue was not addressed during the substitution hearing.”
(Italics added.) As a matter of law, collateral estoppel does not apply where the court or, in this case, hearing officer, has expressly refrained from deciding an issue.
(Stark v. Coker
(1942)
Obviously, it would be unfair to use this postjudgment rationale for reversing a court that was in the dark when it issued its order, and we do not do so, but we perceive no unfairness in noting our appraisal of the record did not miss its mark.
