95 Minn. 293 | Minn. | 1905
This appeal is from an order overruling a general demurrer to a complaint which alleges that at a designated time, in the city of Faribault, plaintiff was at work repairing one of the public streets therein
The accident occurred more than thirty days previous to the commencement of the action, and it was insisted by the defendant city, that inasmuch as it did not appear that plaintiff had served the notice of his claim thirty days after it occurred, and before suit, under the terms of chapter 248, p. 459, Laws 1897, it could not be maintained.
The provisions of this statute relate to a defective bridge, street, public works, or places therein enumerated; and we think it very clear, from the history of the law requiring notice to municipalities of injuries tthereon, and its subsequent development, that it never was intended to ■•apply to the relations between master and servants when the latter are injured by reason of failure of the former to provide a reasonably safe rplace for the servant to work, or as to any absolute duties which are «enjoined by law upon the employer. The object of the notice when required is well understood to be to give the municipality an opportunity to investigate, and to protect against fictitious claims. The treason for the rule hardly applies in a case where its own servants are injured in such work by the negligence of the master, but specifically to cases where the public are interested in using within their rights the-property of the city. With reference to such injuries, when they occur, the municipality would seldom have notice or opportunity to obtain the requisite information of the cause thereof, or the evidence of the city’s negligence, to enable it to defend, after long delay. This would not apply to an injury of the kind happening in this case, for it must be presumed that, with reference to its own servants, and the violation of its duties to them, it has and ought to have the same notice as other persons occupying the relation of employer over the persons who are in direct relation with it. While a very strict and technical construction of the statute might bring the case within its letter, we are very clear it was not within its spirit, and, if it is desired that it should be, the relief must be obtained from the legislature.
The order appealed from is affirmed.