SALLY KELLOGG v. MIDDLESEX MUTUAL ASSURANCE COMPANY
(SC 19803)
Supreme Court of Connecticut
August 22, 2017
Palmer, Eveleigh, McDonald, Espinosa, Robinson, D‘Auria and Vertefeuille, Js.*
Argued May 4
All opinions are subject to modification and technical correction prior to official publication in the Connecticut Reports and Connecticut Appellate Reports. In the event of discrepancies between the advance release version of an opinion and the latest version appearing in the Connecticut Law Journal and subsequently in the Connecticut Reports or Connecticut Appellate Reports, the latest version is to be considered authoritative.
The syllabus and procedural history accompanying the opinion as it appears in the Connecticut Law Journal and bound volumes of official reports are copyrighted by the Secretary of the State, State of Connecticut, and may not be reproduced and distributed without the express written permission of the Commission on Official Legal Publications, Judicial Branch, State of Connecticut.
Syllabus
Pursuant to statute (
The plaintiff sought to vacate an arbitration award setting the amount of the insured loss to her property resulting from a tree falling on the roof and chimney of her home during a storm. The plaintiff had filed a claim pursuant to a restorationist insurance policy issued by the defendant insurance company, under which payment of the full restoration cost of the insured property would be made in a two step process, with the defendant first making payment of the actual cash value of the loss, and, once the restoration or replacement was complete, paying the amount actually spent to repair, restore or replace the damaged building. When the plaintiff‘s appraiser and the defendant‘s appraiser were unable to agree on the amount of the loss, the plaintiff invoked the policy‘s appraisal provision, requiring the loss amount to be determined through an unrestricted arbitration proceeding. Under the terms of the policy, the plaintiff and the defendant each appointed one appraiser to serve as an arbitrator, and the two appraisers chose a neutral third party arbitrator to act as the umpire, all three of whom comprised the appraisal panel. After each appraiser independently estimated the loss, the umpire evaluated the differences between the two appraisers’ estimates and set the loss, which was an amount between the two estimates. The defendant‘s appraiser accepted the umpire‘s valuation, which became the panel‘s decision on the amount of the loss. After the plaintiff filed its application to vacate, the defendant moved to dismiss as untimely the plaintiff‘s challenge to that portion of the arbitration award specific to the building. Although the trial court initially stated that it first would rule on the motion to dismiss, it held eight days of trial, covering all aspects of the motion to dismiss as well as the merits of the application to vacate. The trial court denied the motion to dismiss and granted the application to vacate the arbitration award because it violated
- The trial court improperly vacated the arbitration award and substituted its judgment for that of the panel when it determined that the award violated
§ 52-418 (3) : that court‘s disagreement with the panel‘s ultimate conclusions and the amount of the award, in the absence of any determination that the panel engaged in misconduct impacting the fairness of the arbitration procedures, did not establish a violation of§ 52-418 (3) and was not a proper ground for vacating the award; moreover, there was no claim that the arbitrators refused to postpone a hearing or to hear any of the plaintiff‘s evidence, or otherwise committed a procedural error, and there was testimony by the plaintiff‘s appraiser that the defendant‘s appraiser and the umpire considered all of the evidence that the plaintiff‘s appraiser wanted to present to them. - The trial court incorrectly concluded that the panel‘s decision to calculate depreciation when the restorationist insurance policy did not provide for depreciation evidenced a manifest disregard of the law that justified vacating the arbitration award pursuant to
§ 52-418 (a) (4) : the court improperly engaged in a de novo review when it determined that thepanel‘s decision to withhold depreciation was an error obvious and capable of being readily and instantly perceived by the average person qualified to serve as an arbitrator, as the meaning of the policy language was a matter for the panel to decide, and the plain language of the policy permitted the withholding of depreciation until repairs were made or the damaged property was restored or replaced; furthermore, that court misinterpreted the holding in Northrop v. Allstate Ins. Co. (247 Conn. 242), which held only that an insurer could not withhold depreciation from a replacement cost award after a homeowner had incurred a valid debt for repairs, and was not applicable to estimates, such as the estimate obtained by the plaintiff, which generally impose no obligation or debt on homeowners and do not address concerns that the insured will forgo repairs and receive a windfall, and, thus, the panel did not ignore a clearly governing legal principle when it permitted the defendant to withhold depreciation costs until the plaintiff had incurred a valid debt for the repair or replacement of the property.
Argued May 4—officially released August 22, 2017
Procedural History
Application to vacate an arbitration award, brought to the Superior Court in the judicial district of Stamford-Norwalk, where the court, Hon. Kevin Tierney, judge trial referee, denied the defendant‘s motion to dismiss; thereafter, the case was tried to the court, Hon. Kevin Tierney, judge trial referee, who, exercising the powers of the Superior Court, rendered judgment granting the application to vacate, from which the defendant appealed. Reversed; judgment directed.
Stuart Glenn Blackburn, for the appellant (defendant).
Frank W. Murphy, for the appellee (plaintiff).
Wystan M. Ackerman filed a brief for the Property Casualty Insurers Association of America as amicus curiae.
Opinion
D‘AURIA, J. In this appeal, we consider whether the trial court properly vacated an arbitration award setting the amount of an insured loss caused by a tree falling on the insured‘s home. We conclude that the trial court improperly substituted its judgment for that of the appraisal panel, and we therefore reverse the trial court‘s judgment.
The plaintiff, Sally Kellogg, is the owner of a historic property in the city of Norwalk (property). She insured the property through a “[r]estorationist” policy issued by the defendant, Middlesex Mutual Assurance Company. This restorationist policy was different from a typical homeowners policy in that it had no monetary policy limit, and it covered the replacement or restoration cost of the property without deduction for depreciation. Under the policy, payment of the full restoration cost would not be immediate, but would be made in two parts, with depreciation initially withheld. The policy required the defendant to first pay the actual cash value of the loss. Once the restoration or replacement was complete, the policy required the defendant to pay the amount “actually spent to repair, restore or replace the damaged building.”1 This two step process is typical in replacement cost policies, intended to address concerns that a homeowner might accept the full restoration cost but not actually restore the property, thus receiving a windfall.2
While the restorationist policy was in effect, the property suffered a casualty loss when a four and one-half ton tree fell onto the roof and chimney during a storm, damaging the interior, exterior, and foundation of the home. Shortly after the incident, the plaintiff filed a claim on her restorationist policy. Because the plaintiff‘s and the defendant‘s adjusters were unable to agree on the amount of the loss, the plaintiff invoked the policy‘s appraisal provision. That provision required the loss amount to be determined through an unrestricted arbitration proceeding, meaning that the arbitrators are empowered to decide issues of law and fact, and the award is not conditioned on judicial review. See Industrial Risk Insurers v. Hartford Steam Boiler Inspection & Ins. Co., 273 Conn. 86, 89 n.3, 868 A.2d 47 (2005).
To establish the appraisal panel, the plaintiff and the defendant, pursuant to the restorationist policy, each appointed one appraiser to serve as an arbitrator, and these two appraisers chose a neutral third arbitrator to act as an umpire. The appraisers each independently set the loss and submitted their valuations to the umpire. The plaintiff‘s appraiser claimed the damage was in excess of $1.6 million, but the defendant‘s appraiser believed the property could be restored for approximately $476,000. The appraisers fundamentally disagreed on two issues: the extent of damage caused
The defendant‘s appraiser accepted the umpire‘s valuation, which became the appraisal panel‘s decision on the amount of the loss, and the panel issued its arbitration award in two parts: first, it awarded $578,587.64 for “replacement or restoration cost” of the building on the property, which the panel depreciated to its actual cash value of $460,170.16, with the difference withheld until the plaintiff completed repairs, and, second, the panel later awarded an additional $79,731.68 for the actual cash value loss to the plaintiff‘s personal property.
Subsequently, the plaintiff filed an application with the Superior Court seeking to vacate the arbitration award, alleging it was defective under
The trial court initially stated that it would first rule on the motion to dismiss, but it then went on to hold eight days of trial, covering all aspects of the motion to dismiss as well as the merits of the application to vacate the arbitration award, before ultimately deciding both at the same time. Even though the parties had submitted all factual and legal issues to unrestricted arbitration, the trial court took evidence on the entire appraisal process, including evidence on valuation of the loss, despite the defendant‘s repeated objections that such a process was beyond the scope of an application to vacate and would constitute a substitution of the trial court‘s judgment for that of the appraisal panel. The trial court overruled the objections, stating in one instance: “This is a case involving the testimony right
On cross-examination of the plaintiff‘s appraiser, the defendant elicited testimony establishing the propriety of the arbitration proceedings. Although the plaintiff‘s appraiser disagreed with the amount of the panel‘s award, he did not question the umpire‘s conduct. To the contrary, he stated that the umpire had accepted all of the evidence he wanted to present to him, and the umpire never refused to hear any evidence regarding the loss. Nor did the plaintiff‘s appraiser accuse the umpire of being partial or unfair.
After the proceedings concluded, the court denied the defendant‘s motion to dismiss4 and granted the plaintiff‘s application to vacate. The court determined that the arbitration award violated
First, the trial court disagreed with the amount of the arbitration award. Relying on a valuation based on its own conclusions, the court decided that the award to the plaintiff was insufficient. The court identified thirty-four instances in which the plaintiff had claimed damage to a specific portion of the property and the panel awarded less than the plaintiff had requested, sometimes awarding nothing at all. The court apparently believed that by awarding less than the plaintiff had requested, the panel had prejudiced the plaintiff‘s “substantial monetary rights” and, therefore, the plaintiff had sustained her burden of proof under
Second, the court ruled that the decision of the appraisal panel “evidenced a manifest disregard of the nature and terms and conditions of the [r]estorationist insurance policy,” and, therefore, the plaintiff had sustained her burden under
When considering a motion to vacate an unrestricted arbitration award, a trial court should not substitute its judgment for that of the arbitrators. “Judicial review of arbitral decisions is narrowly confined. . . . When the parties agree to arbitration and establish the authority of the arbitrator through the terms of their submission, the extent of our judicial review of the award is delineated by the scope of the parties’ agreement. . . . When the scope of the submission is unrestricted, the resulting award is not subject to de novo review even for errors of law so long as the award conforms to the submission. . . . In other words, [u]nder an unrestricted submission, the arbitrators’ decision is considered final and binding; thus, the courts will not review the evidence considered by the arbitrators nor will they review the award for errors of law or fact.” (Emphasis added; internal quotation marks omitted.) Comprehensive Orthopaedics & Musculoskeletal Care, LLC v. Axtmayer, 293 Conn. 748, 753-54, 980 A.2d 297 (2009). Furthermore, “[e]very reasonable presumption and intendment will be made in favor of the award and of the arbitrator‘s acts and proceedings.” Bic Pen Corp. v. Local No. 134, 183 Conn. 579, 585, 440 A.2d 774 (1981).
In light of these constraints, a court may vacate an unrestricted arbitration award only under certain limited conditions: “(1) the award rules on the constitutionality of a statute . . . (2) the award violates clear public policy . . . [or] (3) the award contravenes one or more of the statutory proscriptions of
I
Section
In the present case, there was no claim that the arbi-
The trial court nevertheless vacated the arbitration award on the basis of its own disagreement with the appraisal panel‘s ultimate conclusions on the issue of valuation. The trial court disagreed with thirty-four aspects of the arbitration award and would have issued a greater award for these items. For example, the trial court indicated that the panel should have awarded the plaintiff more than $150,000 to repair the property‘s chimney, rather than the $19,000 it did award. In other instances, the trial court took issue with the panel‘s decision not to award any money for certain claimed damage, which the panel determined was not entitled to coverage because it was not related to the tree falling on the house. The trial court used these points of disagreement as the basis for its conclusion that the decision of the appraisal panel had prejudiced the “substantial monetary rights” of the plaintiff. In the absence of any determination that the appraisal panel engaged in misconduct impacting the fairness of the arbitration procedures, the trial court‘s disagreement with the appraisal panel‘s ultimate conclusions cannot justify vacating its award. The appraisal panel was specifically empaneled to value the loss. Although it is clear that the trial court disagreed with the amount of the award, this disagreement does not establish that the arbitrators violated
II
The trial court‘s second justification for vacating the arbitration award pursuant to
Section
In the present case, the trial court concluded that the award of the appraisal panel met all three prongs of the manifest disregard of the law test. See id. The trial court determined that the award satisfied the first prong—the error was obvious and capable of being readily and instantly perceived by the average person qualified to serve as an arbitrator—because the panel withheld depreciation in a policy that provides for no depreciation. The meaning of the policy language was a matter for the panel to decide, however, and the trial court should not have engaged in a de novo review of this issue. See Harty v. Cantor Fitzgerald & Co., 275 Conn. 72, 80, 881 A.2d 139 (2005) (when submission to arbitrator is unrestricted, “the courts will not review the evidence considered by the arbitrators nor will they review the award for errors of law or fact” [internal quotation marks omitted]). More importantly, the trial court‘s conclusion is contradicted by the plain language of the policy, which clearly permits the withholding of depreciation until repairs are made or the damaged property is replaced. See footnote 1 of this opinion.
Furthermore, the trial court‘s conclusion that the panel‘s award satisfied the second and third prongs of the manifest disregard of the law test was also incorrect. The trial court interpreted our decision in Northrop to hold that an insurer may not withhold payment for depreciation whenever a homeowner had obtained an estimate for repairs in excess of the actual cash value award, as the plaintiff did in the present case. But Northrop held only that an insurer could not withhold depreciation from a replacement cost award after a homeowner had incurred a valid debt for repairs. Northrop v. Allstate Ins. Co., supra, 247 Conn. 251-52. Northrop does not apply to estimates, which generally impose no obligation or debt on the homeowners and, unlike the incurrance of a valid debt, do nothing to address concerns that the insured will forgo repairs and receive a windfall. Consequently, we conclude that the trial court misinterpreted our holding in Northrop, and, thus, the panel did not ignore governing law or principles when it permitted the defendant to withhold depreciation costs until the plaintiff had incurred a debt for the repair or replacement of the property.
We conclude, therefore, that the trial court improp-
The judgment is reversed and the case is remanded with direction to render judgment denying the plaintiff‘s application to vacate the arbitration award.
In this opinion the other justices concurred.
* The listing of justices reflects their seniority status on this court as of the date of oral argument.
Notes
“(a) . . . (1) We will pay the cost to repair, restore or replace, without deduction for depreciation . . . .
“(2) We will pay no more than the actual cash value of the damage until actual repair, restoration or replacement is complete. Once actual repair, restoration or replacement is complete, we will settle the loss according to the provisions of (a) (1) above.”
