29 Pa. Super. 480 | Pa. Super. Ct. | 1905
Opinion by
The plaintiff brought her action of trespass against the defendant to recover for damagesto her dwelling house and lot occasioned, as she alleged, by the overflow of a stream across which a dam was formed by the debris carried down the stream against the gas pipe of the defendant which crossed the stream beneath a bridge which spanned it.
The situation is graphically described by a witness of the plaintiff who said, in answer to queries : “ Q. What did you see ? A. I saw an old tree stuck in there against the pipe and against them braces, and a lot of old doors from the Ashley shops and rubbish and briars and everything, right in there tight up against the pipe. Q. Was the water passing under the bridge then or going out the other side above the bridge ? A. Going out the other side. There was a little going through, but not much. Q. How was the creek on the lower side of the bridge with reference to the channel being full or not ? A. It was not overflowing the banks on the lower side of the bridge.”
The jury having found for the plaintiff, the conditions described have been found to have existed and the responsibility of the defendant is thereby established.
We have twenty-one assignments of error, which are discussed under three distinct propositions by the appellant.
1. The first is as to the admission of the testimony of a witness of the plaintiff who testified as to the damages sustained by the plaintiff, based upon the cost of the repairs necessary to
2. In a number of offers, running through various assignments of error, the defendant finally made the following offer: “I propose now to prove by the witness that in 1879 and 1880 this creek was in the same condition as it was in the flood of 1901, as to the height of the banks and the condition generally of the land adjacent to the creek, including the property in dispute; that in those years there were several extraordinary floods ; that no extraordinary flood has been had there since, until the flood in question, and that during those floods in the later seventies and fore part of eighty, the banks overflowed properties along the creek, among them the property in question, and that at the same time there were no obstructions in the way of gas pipe, or anything of that kind, or any bridge to interfere with the natural flow of the water. I propose also to prove by the witness that extraordinary floods were there for the last time in 1880 and that there was no gas pipe or gas main under any of the bridges, and that at that time the banks overflowed and inundated, among others, the property in question.” If the offer had gone a little further and had offered to prove that the property was damaged as well as overflowed or inundated, there could have been no question as to the admissibility of the offer. Even as the offer was made, it may have had some relevancy from some points of view. Why the defendant should have offered the testimony, however, and why the plaintiff should have objected to it is not clearly apparent, the inference being irresistible, if the offer had been made good,
The offer relating to the general character of the flood, as to the amount of rainfall and snow and the condition of temperature existing at the time of the flood, were fairly admissible. It seems to us, therefore, that the sustaining of the objections complained of in the 12th, 13th, 14th, 15th, 16th and 17th assignments of error was erroneous, although as to some of them it appears that the court did not sustain the objections on the ground that the evidence was irrelevant and immaterial, but that the facts stated in the offer had already been shown.
3. The defendant presented several points for charge, all of which were practically affirmed, with the exception of the first and second, the second being : “ Second, The measure of damages to plaintiff’s premises, the injury not being shown to be permanent, is the cost of restoring it to its former condition,
The defendant’s point clearly outlined the true measure of damages.. It was correct in principle and clear and intelligible in form and substance. It was not alleged that the damages sustained exceeded the value of the building and hence the point covered the entire ground. The defendant was, therefore, entitled to have it affirmed, particularly in view of the fact that the rule had not been clearly and fully set forth in the general charge. The general rule of the cases, as gathered in 2 P. & L. Dig. of .Dec. 2600, is that “ An answer may also be by reference to the general charge, if this sufficiently covers the point; and the refusal of a point fully covered in the general charge is not assignable for error. A point may be refused without being read to the jury, if the law applicable to the case has been correctly stated in the general charge, or the
4. The eighteenth assignment of error complains of the language employed by the trial judge in the general charge, in which he says, quoting the entire sentence, of which the defendant assigns for error but a portion : “ If the rise of water and consequent injury to plaintiff’s property, in case it was injured, was due wholly and entirely to the act of God in making a great flood, the company should not pay. But, if the company were partly negligent and its negligence produced injury to this woman’s property, it must pay.” Strictly speaking, the company could not be partly negligent. It was either negligent or it was not so. What the court evidently meant was that if the negligence of the company conspired with the act of God to cause the injury, and the injury was due primarily to the negligence of the company, it was liable. The principle is correct. The form of its statement is perhaps somewhat objectionable, although we would not regard it ground for reversal, if it stood alone.
We regard the refusal of the court to affirm the defendant’s second point as the principal error in the ease. How far the defendant’s case was hurt by the ruling out of the testimony contained in the offers as to which complaint is made there may be a question; but, so far as they were in any way relevant, they should have been received, and, inasmuch as the case goes back for a new trial, we have devoted some space to their consideration.
Judgment reversed and a new venire awarded.