181 Mass. 587 | Mass. | 1902
In each declaration there were three counts, and each verdict was a general one and may have been rendered upon either count. Without so deciding, we assume in favor of the defendant that upon the evidence neither plaintiff could recover upon the first count of his or her declaration. But no request was made for a separate ruling upon those counts. The three requests of the defendant were for general rulings that upon the evidence the plaintiffs were not entitled to recover; that under the provisions of St. 1898, c. 578, they could not recover, and that the actions should have been brought against the town and not against the defendant. Assuming in favor of the defendant that an exception was taken to the refusal to give these three requests and was intended to be saved by the bill, it must be overruled if upon the evidence the plaintiffs were entitled to go to the jury upon the second or the third counts. The distinctive allegation of the second counts is that the defendant in the repair of its railway negligently produced and allowed to remain in the highway a deep excavation dangerous to travellers. This count is founded upon the liability imposed upon street railway companies by the provisions of St. 1898, c. 578, § 11. That section requires the company to replace surface material disturbed by it in the making of repairs and to restore the street to as good condition as existed at the time of such disturbance, and makes the company liable for any loss or injury suffered by any person in the repair of its railway or while replacing the surface of any street so disturbed and resulting from the carelessness, neglect or misconduct of its agents or servants engaged in the work.
The third counts proceed upon the common law liability of any person who creates and maintains a dangerous excavation in a public way, and they allege that the defendant negligently created and caused or permitted to be maintained a deep excavation in the highway dangerous to travellers.
Although the evidence would not justify a verdict upon the first counts, the three requests were refused rightly if the evidence would justify a finding that the defendant made the excavation in the repair of its railway as alleged in the second counts,
It was in evidence that before the excavation was made water ran down near the north rail to a railway switch near by. The natural tendency of water so running would be to carry sand and gravel into the switch and impede its operation. The excavation started at the north rail and went towards and under the south rail and connected with a gutter beyond the south rail. It deepened gradually in its course from the north rail and it had the appearance of having been made by digging and not of having been washed out. While it was there employees of the defendant were at work upon the track replacing old ties with new ones within a few yards of the excavation. This would justify the inference that the excavation had been made for the purpose of diverting a flow of water from the defendant’s switch, and as that would be serviceable to the defendant and to no one else that it was made by the party whose interest it would serve. Besides this the defendant although it introduced evidence made no attempt to show that it did not cause the excavation to be made, or by whom it was made, except to show by the cross-examination of one of the plaintiffs’ witnesses that there was a hydrant south of the track near the excavation and that the hydrant had been repaired several weeks before the accident. It is matter of common knowledge that the motormen and conductors of a railway company, if no others of its servants, pass over and have the opportunity to observe its tracks daily. In the absence of any evidence introduced on the part of the company the evidence justified a finding that the company made and maintained the excavation for its own purposes. For this reason the three instructions stated were rightly refused.
The same considerations dispose of the refusal to rule that there was no evidence on which the plaintiffs could go to the jury upon the third count, and to the submission to the jury of the question, answered by them- in the affirmative, whether the
Exceptions overruled.