*606 Opinion
-In this case, we are called upon to decide whether California’s Department of Forestry and Fire Protection (CDF) properly granted an exemption allowing the harvesting of less than three acres of timber without environmental review, when one of the mitigation measures to two prior timber harvesting plans for the same property was that the trees in question remain in place to protect a neighboring property from excessive wind. The trial court decided CDF properly granted the exemption, and entered judgment on the pleadings in plaintiff Paul Katzeff’s action for violations of the California Environmental Quality Act (CEQA) (Pub. Resources Code, 1 § 21000 et seq.), violations of the Z’berg-Nejedly Forest Practice Act of 1973 (§4511 et seq.) (the FPA), and nuisance. We reverse.
I. BACKGROUND
This action was brought against CDF, Gregg Kuljian, and Ed Powers (collectively respondents) in April 2008, seeking to set aside CDF’s approval of an exemption allowing the conversion of less than three acres of timber on Kuljian’s property. According to the first amended complaint and petition for writ of mandate (the complaint), 2 plaintiff and Kuljian own adjoining parcels of property. In 1988, CDF approved a Timber Harvest Plan (THP) on Kuljian’s land (the property) (the 1988 THP). 3 CDF concluded that the THP as proposed would allow wind to be funneled and accelerated, creating a threat of damage to Katzeff’s property and home. Accordingly, as one of the conditions of approval, CDF required that “ ‘no trees ... be removed from within 200 feet of [Katzeff’s home] unless prior approval is obtained from [Katzeff].’ ”
CDF approved another THP for the same location 10 years later, in 1998 (the 1998 THP). Noting the apparent effectiveness of the wind buffer, CDF again required the landowner to refrain from cutting down trees within 200 feet of Katzeff’s house.
Some years later, Powers sold the property to Kuljian. Kuljian could not afford to pay the purchase price, and so as a condition of the sale, he agreed *607 to seek a “conversion exemption” pursuant to section 4584, subdivision (g), and to give Powers the right to log and sell the timber. 4 In the application for the conversion exemption, Kuljian stated he intended to convert the timberland to an orchard. In April 2008, CDF “accepted and thereby approved” the conversion exemption.
In his first cause of action, Katzeff alleged that the conversion exemption violated the FPA and CEQA in that it would destroy a mitigation previously deemed necessary. In his second cause of action, he alleged that Kuljian did not have a bona fide intent to convert the land to an orchard. The third cause of action alleged a claim for private nuisance.
Powers moved for judgment on the pleadings on the ground that the complaint did not state a cause of action. (Code Civ. Proc., § 438, subd. (c)(1)(B).) The trial court granted the motion and dismissed the action in its entirety. Katzeff appealed. 5
H. DISCUSSION
A. Standard of Review
“ ‘Review of a judgment on the pleadings requires the appellate court to determine, de novo and as a matter of law, whether the complaint states a cause of action. [Citation.] For purposes of this review, we accept as true all material facts alleged in the complaint. [Citation.] . . .’ [Citation.] [f] . . . ‘[W]e give the complaint a reasonable interpretation by reading it as a whole and all of its parts in their context. [Citations.] We are not concerned with a plaintiffs possible inability to prove the claims made in the complaint, the allegations of which are accepted as true and liberally construed with a view toward attaining substantial justice. [Citations.]’ [Citation.]”
(Ludgate, supra,
*608 B. Requirements of FPA and CEQA
“ ‘Timber harvesting operations in this state must be conducted in accordance with the provisions of the Forest Practice Act. The [FPA] was intended to create and maintain a comprehensive system for regulating timber harvesting in order to achieve two goals: (1) to ensure that “[w]here feasible, the productivity of timberlands is restored, enhanced, and maintained”; and to ensure that “[t]he goal of maximum sustained production of high-quality timber products is achieved while giving consideration to values relating to recreation, watershed, wildlife, range and forage, fisheries, . . . and aesthetic enjoyment.” (. . . § 4513.) . . .’ [Citation.] [][] (2) The [FPA] requires timber owners or operators on private land to submit a timber harvest plan specific to the site and planned logging activity to CDF for approval before harvesting. ...[][] CDF’s approval of timber operations is generally subject to CEQA, but under section 21080.5, the [FPA’s] regulatory scheme has been certified for exemption from CEQA’s requirements for preparation of an environmental impact report (EIR) before approval of a project. [Citation.] ‘Under the terms of section 21080.5, subdivision (c), that certification expressly exempts the timber harvesting plan process from the provisions of chapters 3 and 4 and section 21167 of CEQA. (§ 21080.5, subd. (c).) Chapters 3 and 4 deal, in large part, with the various requirements of an EIR at both the state level (ch. 3) and the local level (ch. 4). Section 21167 sets forth the time within which an action challenging a public agency’s decision under the provisions of CEQA must be filed.’ [Citation.]”
(Ebbetts Pass Forest Watch v. California Dept. of Forestry & Fire Protection
(2008)
Division Five of the First Appellate District explained the relationship between the requirements of the FPA and CEQA in
Friends of the Old Trees v. Department of Forestry & Fire Protection
(1997)
As explained in
Environmental Protection Information Center, Inc. v. Johnson
(1985)
C. Destruction of Mitigation Measure
Katzeff’s first cause of action alleges that CDF violated both the FPA and CEQA by approving a conversion exemption that would destroy a mitigation it had previously deemed necessary under those statutory schemes. Katzeff argues that CDF’s actions constituted improper “piecemealing” of a project, and that an agency may not delete a mitigation required by CEQA without supplemental environmental review. Respondents take the position that the approval was a ministerial act not subject to CEQA and that it bore no relationship to the mitigation measures required by the 1988 and 1998 THP’s. They also argue that the THP’s have long since expired, and with them their mitigation requirements.
Several statutes and rules bear upon the parties’ arguments. Section 4581 forbids anyone to conduct timber operations unless a THP has been *610 submitted to CDF. 6 Section 4590, subdivision (a) provides that a THP is effective for no more than three years, unless extended pursuant to specified procedures. Forest Practice Rules, rule 1039.1 provides that the “effective period of the plan” is “the 3-year period following the date the plan is determined to be in conformance or otherwise becomes effective pursuant to PRC 4582.7. Timber operations shall commence no earlier than the expected date of commencement stated in the plan,” except under certain conditions. The THP’s at issue here were approved in 1988 and 1998. There is no dispute that the right to conduct timber operations under these THP’s has expired.
Conversion exemptions are governed by section 4584 and Forest Practice Rules, rule 1104.1. As we have explained, section 4584 allows the State Board of Forestry and Fire Protection, upon determining that the exemption is consistent with the purposes of the FPA, to exempt from the FPA’s requirements anyone whose activities are limited to, among other things, “[t]he one-time conversion of less than three acres to a nontimber use.” (§ 4584, subd. (g)(1); see § 4521.3.) Rule 1104.1 establishes the requirements for such exemptions. Under rule 1104.1(a), the conversion exemption “is applicable to a conversion of timberland to a non-timber use only, of less than three acres in one contiguous ownership, whether or not it is a portion of a larger land parcel and shall not be part of a THP.” The notice of conversion exemption, which initiates the process, is required to contain certain material, including the names and addresses of the landowner, timber owner, and others; a legal description of the land at issue; certain maps; and a statement by the owner of the land to be converted certifying that the operation is a one-time conversion to nontimberland use, certifying that there is a bona fide intent to convert, specifying what the use will be after the conversion, and certifying that the landowner has not obtained a conversion exemption in the previous five years, unless a waiver had been granted. (FP Rules, rule 1104.1(a)(1).) As relevant here, timber operations conducted under rule 1104.1 are exempt from the conversion permit and THP requirements of the rules related to the conversion of timberland.
The presenting issue here is whether a conversion exemption that would destroy a mitigation required under now expired THP’s may be approved without additional environmental review. The parties have drawn our attention to no case precisely on point, and our own research has disclosed none.
Katzeff contends this case is analogous to
Orinda Assn.
v.
Board of Supervisors
(1986)
Several points in Orinda are significant here. First, Orinda states the well-established principle that a project cannot be divided into smaller parts that individually will not have a significant effect on the environment. Second, this rule is applicable even if one of the smaller parts might require only ministerial, rather than discretionary, approval. Third, where conditions are imposed on a project, those conditions—and the policies behind CEQA— cannot be avoided by applying for another approval apart from the larger project. (Orinda, supra, 182 Cal.App.3d at pp. 1171-1172.)
Here, respondents contend, issuance of the conversion exemption was a ministerial action that required no environmental review. Under Orinda, however, even if we accept the argument that the exemption was ministerial, an applicant cannot avoid environmental review of a portion of a larger project simply by securing a separate ministerial permit, particularly where the permit would undo the protective effects of conditions imposed on a project’s approval.
We recognize that
Orinda
is not precisely on point because the demolition permit there was issued while the overall project was under review, while here the conversion exemption took place years later. But if that distinction were dispositive, any mitigation required by CEQA or the FPA could be nullified simply by the passage of time. As Katzeff points out, under this line
*612
of reasoning, the wind buffer mitigation could permissibly be destroyed virtually as soon as it became necessary—that is, after the landowner had completed operations under the THP—because the landowner could simply seek a conversion exemption as soon as the right to conduct timber operations under the THP had expired. The conflict between this result and the intent of CEQA is self-evident.
7
As noted in another context, “[e]xpiration of the [approval] was an abstract occurrence that had no effect on the project’s environmental impacts.”
(Moss v. County of Humboldt
(2008)
We see no principled distinction between a conversion exemption sought immediately after the right to harvest under a THP has expired, and one sought a decade later. Whether or not the legal right to harvest timber has expired, the environmental effects of the harvest are presumed to remain. The wind buffer was required in order to mitigate the effects of the timber harvest on Katzeff’s property, and respondents offer no basis for a conclusion that the mitigation expires as a matter of law once the time to complete the timber harvesting—the very action that creates the need for the mitigation—has expired.
Lincoln Place Tenants Ass'n v. City of Los Angeles
(2005)
The court in
Lincoln Place
further noted that “[although the city cannot ignore the mitigating conditions it imposed on the . . . project it can modify or delete them. After a project has been approved and while it is still being developed a mitigation measure or condition of approval may be changed or deleted if the measure has been found to be impractical or unworkable.”
(Lincoln Place, supra,
130 Cal.App.4th at pp. 1508-1509.) For this, the court relied on
Napa Citizens for Honest Government
v.
Napa County Bd. of Supervisors
(2001)
We likewise presume that CDF adopted the mitigation measure at issue only after due investigation and consideration. In fact, the administrative record indicates that this is the case. The wind impact analysis prepared in connection with the 1988 THP discusses the risk that, as a result of the project, storm winds would become “funneled and accelerated on the southeastern comer,” near Katzeff’s house, and would “deflect off the residual trees along the southern edge of the harvest area and will be directed to the comer.” The analysis reviews the literature on this phenomenon and the ways to minimize its effects, and recommends a buffer strip as a mitigation measure, based on conversations with professors of silviculture at the University of California, Berkeley and at Humboldt State University.
Consistent with the reasoning of the cases we have discussed, we conclude that where a public agency has adopted a mitigation measure for a project, it may not authorize destruction or cancellation of the mitigation— whether or not the approval is ministerial—without reviewing the continuing need for the mitigation, stating a reason for its actions, and supporting it with substantial evidence. There may be good reasons for CDF to conclude that the wind buffer is no longer necessary to protect Katzeff’s house from the effects of the harvesting done pursuant to the 1988 and 1998 THP’s. While the passage of time may have eliminated the need for the mitigation, it does not on its own render the mitigation inoperative, and CDF must justify its decision to allow the buffer strip to be cut down. 8
*615 Accordingly, we conclude the trial court erred in dismissing the first cause of action.
D„ E. *
m. DISPOSITION
The judgment is reversed. The stay of timber operations heretofore imposed by writ of supersedeas shall remain in effect pending finality of this opinion.
Ruvolo, P. J., and Sepulveda, J., concurred.
Notes
All undesignated statutory references are to the Public Resources Code. Rule references cited as the Forest Practice Rules in text and as FP Rules parenthetically are to title 14 of the California Code of Regulations.
Because this case comes to us after the trial court granted a motion for judgment on the pleadings, we accept as true all material facts of the complaint.
(Ludgate Ins. Co. v. Lockheed Martin Corp.
(2000)
At the time, Kuljian did not own the property. As we will discuss, the complaint alleges that he bought the property shortly before the complaint was filed in 2008.
Section 4584, a portion of the FPA, provides in pertinent part: “Upon determining that the exemption is consistent with the purposes of this chapter, the board may exempt from this chapter, or portions thereof, a person engaged in forest management whose activities are limited to any of the following: [f] . . . [f] (g)(1) The one-time conversion of less than three acres to a nontimber use. . . .”
Katzeff s notice of appeal was filed after the trial court made its order granting Power’s motion for judgment on the pleadings as to all causes of action, but before judgment had been entered. We will treat it as having been filed immediately after entry of judgment. (Cal. Rules of Court, rule 8.104(e)(2).) On appeal, CDF has filed a respondent’s brief addressing the first and second causes of action. Powers has joined CDF’s brief and made additional arguments addressing all three causes of action. Kuljian has filed a one-page brief in which he “generally adopts” the other respondents’ arguments.
Section 4582 sets out the necessary contents of a THP.
In any case, it appears that removal of the trees now at issue was part of the original 1988 THP proposal. The official response of the director of forestry to significant environmental effects raised during the THP evaluation process stated that storm winds were predicted to be ffinneled and accelerated “as a result of this operation,” noted that Katzeff’s home was within 200 feet of the southeast boundary of the plan, and provided that no trees should be removed within 200 feet of his home without prior approval. Furthermore, a “Wind Impact Analysis” prepared by CDF in December 1987 indicated that Katzeff’s cabin and outbuildings were “near the southeast comer of the harvest area [and were] within striking distance of edge trees,” and suggested as a mitigation measure that a wind buffer strip be left on the southeast corner of the harvest area. This discussion implies cutting down the trees Powers now seeks to harvest in fact was part of the original project as contemplated.
As our discussion indicates, our conclusion here does not depend on whether the issuance of a conversion exemption is ministerial or discretionary. We note, however, that the rules applying to conversion exemptions direct that significant adverse impacts should be taken into account when addressing a proposed conversion. Forest Practice Rules, rule 1104.1 (a)( 1)(E)(2) requires the notice of conversion exemption to include a statement by the owner of the timber certifying that, among other things, “there is [a] ‘bona fide intent[,’] as defined in CCR 1100(b), to convert.” Rule 1100(b) defines bona fide intent to mean “a present, sincere intention of the applicant to conform with and successfully execute the conversion plan, as determined by the Director in accordance with provisions of [rule] 1105.2.” Rule 1105.2 provides: “The Director shall determine the applicant’s bona fide intention to convert in light of the present and predicted economic ability of the applicant to carry out the proposed conversion; the environmental feasibility of the conversion, including, but not limited to, suitability of soils, slope, aspect, quality and quantity of water, and micro-climate; adequacy *615 and feasibility of possible measures for mitigation of significant adverse environmental impacts', and other foreseeable factors necessary for successful conversion to the proposed land use.” (Italics added.)
See footnote, ante, page 601.