Kathleen BRYANT et al. v. TOWN OF WISCASSET et al.
Docket: Lin-17-165
Supreme Judicial Court of Maine.
December 19, 2017
2017 ME 234
HUMPHREY, J.
Argued: October 13, 2017
Mary E. Costigan, Esq. (orally), Bernstein Shur, Portland, for appellee Town of Wiscasset
Chris Neagle, Esq. (orally), Troubh Heisler, PA, Portland, for appellees Allen Cohen, Melissa Cohen, and Big Al‘s Outlet, Inc.
Panel: ALEXANDER, MEAD, GORMAN, JABAR, HJELM, and HUMPHREY, JJ.
HUMPHREY, J.
[¶1] Kathleen Bryant and Thomas Bryant appeal from a judgment of the Superior Court (Lincoln County, L. Walker, J.) affirming, pursuant to
I. BACKGROUND
[¶2] In September 2014, the Cohens applied to the Town of Wiscasset Planning Board for a site plan review approval and to the Code Enforcement Officer for a permit for a proposed 35-by-60-foot addition to their storage building. The Cohens’ site plan review application recited, “Fire-works storage approved and inspected by State Fire Marshal[‘]s Office.” The Bryants objected to the application. After an administrative process that involved an initial appeal to and remand from the Board of Appeals, the Planning Board granted the Cohens’ application. The Bryants appealed that decision to the Board of Appeals, and the Board of Appeals issued its final decision on March 24, 2015, affirming the decision of the Planning Board.1 The Bryants appealed to the Superior Court, which affirmed the Planning Board decision on September 21, 2016. Because the decision of the Planning Board is the operative one for purposes of this appeal, the facts recited below are taken from the record before the Planning Board and from the decisions the Planning Board issued on September 22, 2014, and January 12, 2015.2
[¶3] On September 8, 2014, the Planning Board held its first public hearing on the Cohens’ application. Allen Cohen presented the application to the Planning Board.3 The Bryants opposed the application, expressing concerns about the prox-
[¶4] The Bryants appealed from the Planning Board‘s decision to the Board of Appeals, asserting, in relevant part, that (1) the Planning Board failed to review the application against applicable legal standards, particularly National Fire Protection Association Code 1124 (NFPA 1124); (2) the Planning Board‘s findings were not supported by substantial evidence in the record; and (3) Allen Cohen‘s presentation of his application to the Planning Board violated Maine‘s conflict-of-interest law. The Board of Appeals “denied” the appeal, but nonetheless remanded the application to the Planning Board to determine whether the Cohens had written approval from the State Fire Marshal‘s Office for the proposed expansion.
[¶5] On remand, the Planning Board held two hearings in November 2014 and, at the conclusion of the second hearing, unanimously approved the Cohens’ application. The Bryants were not given personal notice of the hearings and did not appear at either hearing. On December 22, 2014, the Bryants filed a second appeal to the Board of Appeals, asserting in relevant part that the Planning Board‘s failure to give them personal notice of the November hearings violated their right to due process.
[¶6] Despite the pending appeal, the Planning Board met in January 2015 to “again consider” the Cohens’ application and to give the Bryants “the opportunity to address the Board on the application.” The Bryants attended the hearing and reiterated their objections to the Cohens’ application. At the January hearing, Allen Cohen displayed for the Board his federal licenses to sell fireworks; the State Fire Marshal‘s signed approval of the property for the storage of fireworks; and a letter from the Wiscasset Fire Department stating that it had “no issues” with the property. The Planning Board again voted on and reapproved the application.
[¶7] In March 2015, the Board of Appeals “denied” the Bryants’ second appeal and affirmed the Planning Board‘s approval of the Cohens’ application.
[¶8] The Bryants appealed the Planning Board‘s decision to the Superior Court, pursuant to
[¶9] On September 21, 2016, the Superior Court affirmed the decision6 of the
II. DISCUSSION
A. Site Plan Review
[¶10] In their Rule 80B appeal, the Bryants first challenge the Planning Board‘s approval of the Cohens’ site plan review application.
[¶11] “Our review of administrative decision-making is deferential and limited.” Wolfram v. Town of N. Haven, 2017 ME 114, ¶ 7, 163 A.3d 835 (quotation marks omitted). “In a Rule 80B appeal, the Superior Court acts in an appellate capacity, and, therefore, we review the [Planning Board‘s] decision directly,” 21 Seabran, LLC v. Town of Naples, 2017 ME 3, ¶ 9, 153 A.3d 113 (quotation marks omitted); see also supra n.2, for errors of law, abuses of discretion, or findings not supported by substantial evidence in the administrative record. Osprey Family Tr. v. Town of Owls Head, 2016 ME 89, ¶ 9, 141 A.3d 1114. The Bryants bear the burden of persuasion because they seek to vacate the Planning Board‘s decision. Wolfram, 2017 ME 114, ¶ 7, 163 A.3d 835.
[¶12] The Bryants contend that the Planning Board erred when it approved the site plan review application because the Planning Board failed to ensure that the Cohens’ fireworks storage building complied with NFPA 1124.9 Although interpretation of an ordinance is a question of law, and therefore reviewed de novo, see Wolfram, 2017 ME 114, ¶ 7, 163 A.3d 835, “we accord ‘substantial deference’ to the Planning Board‘s characterizations and fact-findings as to what meets ordinance standards.” Bizier v. Town of Turner, 2011 ME 116, ¶ 8, 32 A.3d 1048.
[¶13] The Wiscasset site plan review ordinance requires that hazardous materials, including fireworks, be stored in accordance with the standards of the federal or state agency that deems them hazardous. Wiscasset, Me., Site Plan Review Ordinance Art. VIII § 9(L) (Nov. 2012). The Office of the State Fire Marshal is the state agency that regulates fireworks. See
[¶14] According deference to the Planning Board‘s findings, we conclude that there was substantial evidence before the Planning Board to support its conclusion that the Cohens’ fireworks storage building and the proposed expansion complied with NFPA 1124: Allen Cohen asserted multiple times that he had State Fire Marshal approval, there is documentation that the property was approved for the storage
B. Procedural Due Process Violations
[¶15] The Bryants next allege in their Rule 80B appeal that their procedural due process rights were violated when the Planning Board failed to provide them with personal notice of its November meetings. “We will vacate a planning board‘s decision if, as a result of [ex parte] communications, the decision results in procedural unfairness,” see Duffy v. Town of Berwick, 2013 ME 105, ¶ 18, 82 A.3d 148 (quotation marks omitted), but an adjudicative body “may disregard nonprejudicial failure to comply strictly with notice requirements.” Town of Ogunquit v. Dep‘t of Pub. Safety, 2001 ME 47, ¶ 11, 767 A.2d 291. Whether the effect of procedural unfairness denies a party due process is a question of law that we review de novo. See Wolfram, 2017 ME 114, ¶ 20, 163 A.3d 835.
[¶16] The Planning Board held a fourth meeting in January 2015 to consider the Cohens’ application after the Bryants informed the Planning Board that they had not received notice of the November meetings. The Planning Board voted to reaffirm its approval only after hearing the Bryants’ objections for the second time. In view of the Planning Board‘s remedial action, including notice to the Bryants of the January meeting and providing them an opportunity to be heard, and the resulting lack of prejudice to the Bryants, we conclude that the Planning Board did not violate the Bryants’ due process rights. See Town of Ogunquit, 2001 ME 47, ¶¶ 13-14, 767 A.2d 291 (holding that the court erred when it dismissed the action for procedural defects because the Town took adequate remedial measures and no prejudice resulted to the petitioners).
C. Conflict-of-Interest Violation
[¶17] The Bryants also allege in their Rule 80B appeal that the Planning Board‘s decision is void pursuant to Maine‘s conflict-of-interest law,
D. Independent Claims
[¶18] The Bryants’ independent claims (Counts 2, 3, and 4) collectively rely on the same factual allegations and issues—conflict-of-interest and procedural due process violations, and violations of the laws, regulations, and ordinances regarding the storage of fireworks—and seek the same ultimate relief as their Rule 80B appeal. Those issues were thoroughly discussed and properly addressed by the court in its judgment on the Rule 80B appeal; and any further discussion of those claims would be duplicative. See Kane v. Comm‘r of the Dep‘t of Health and Human Servs., 2008 ME 185, ¶ 32, 960 A.2d 1196; Adelman v. Town of Baldwin, 2000 ME 91, ¶ 7, 750 A.2d 577. Accordingly, the Bryants’ appeal of the judgments on their independent claims are dismissed as moot because the issues have “lost [their] controversial vitality,” and any further “decision by this [C]ourt would not provide [the Bryants] any real or effective relief.”10 See Sparks v. Sparks, 2013 ME 41, ¶ 9, 65 A.3d 1223 (quotation marks omitted).
The entry is:
Judgment of Superior Court affirmed with respect to the Rule 80B appeal. Appeals dismissed with respect to the judgments on the independent claims.