84 Ct. Cl. 110 | Ct. Cl. | 1936
delivered the opinion of the court:
The plaintiff on September 12, 1931, entered into a contract with the defendant by which the plaintiff agreed to furnish all labor and materials and to perform all work required for the construction of the United States Post Office Building and Court House at Trenton, New Jersey, except elevators and foundations, for the sum of $749,500 according to specifications, schedules, and drawings which were made a part of the contract. The building was to be completed within 480 calendar days after the date of receipt of the notice to proceed. On September 24,1931, the plaintiff was notified to proceed, which fixed the date of final completion as January 16, 1933. The defendant furnished the site and also the concrete foundations for the building, which was to be a five-story structure, with the exterior front and two sides of oolitic limestone and ornamental terra cotta, and the back principally of limestone and brick. The interior of the building was to be constructed principally of structural steel and reinforced concrete floors.
Shortly prior to the commencing of the work, the plaintiff prepared a schedule of its contemplated progress of each class of work and furnished a copy of it to the defendant. Each of plaintiff’s subcontractors was also furnished a copy and was required by the plaintiff to adhere to the schedule of his own particular work. This schedule of progress plaintiff planned to adhere to and it was an essential part of the contract arrangements, expected cost, and the amount of its bid. Under this progress schedule the steel work was to begin on September 25, 1931, and be completed in three months; the limestone and brick work were to begin about January 4, 1932; the terra cotta work a day or two after-wards; and the limestone, brick, and terra cotta work were
The plaintiff’s claims fall into two classes. The first is for damages caused the plaintiff due to the fact that the defendant delayed the plaintiff in the completion of the work. The second class consists of items for extra work performed under the terms of the contract for which the plaintiff claims additional compensation.
The Government agreed to furnish the foundations but when the plaintiff entered upon the work it was found that the foundations were out of place from three inches to two feet. The Government employed; the plaintiff to correct these errors and defects and paid the plaintiff for this work and allowed an extension of time of 13 days for the completion of the contract. During these 13 days, while the foundations were being put in proper alignment, the plaintiff was prevented from proceeding with its work and the orderly progress of its work was thrown out of schedule; the superintendent, the plant, and the workmen were idle; and an additional expense was placed upon the plaintiff in the sum of $1,635.01. It is too well established to require citation of authority that the Government can be required to make compensation to a contractor for damages which he has actually sustained by defendant’s default in its performance of its undertaking to him. United States v. Smith, 94 U. S. 214. The defendant does not deny this proposition but contends as a defense that the plaintiff in March 1933, wrote a letter to the defendant in which it stated that no claim for loss would be made on this item. At that time the contract had been completed and the plaintiff was en
About a month after the plaintiff had entered upon the work, it notified the defendant of the subcontractor to whom it had given the contract for the manufacture of the terra cotta and requested that full size drawings for and models of ornamental, plain, and colored plaster for the terra cotta work for the exterior of the building, which were to be furnished by the Government, be delivered to its subcontractor. The defendant delayed in furnishing these drawings and models and the plaintiff repeatedly protested against the unreasonable delays and warned the defendant of the loss which would result, stating that it would hold the defendant for reimbursement of all damages it sustained by reason of the Government’s failure to furnish them. The Government admits that it delayed the plaintiff 62 days in the furnishing of these drawings and models and granted an extension of time for the completion of the contract for this period. Owing to the disruption of its progress schedule and the idleness of its force of workmen and plant, the plaintiff incurred an additional overhead expense of $9,651.74. In addition to this overhead, the plaintiff had contracted with its subcontractor, who had the contract for the placing of the limestone front, for the use of its scaffolding for the purpose of putting in place the terra cotta work. Owing to the delay of the Government in furnishing the drawings and models for the terra cotta work, the limestone had been placed in position and the scaffolding had been removed, and the plaintiff was put to the additional expense of erecting a new scaffolding in the sum of $984.34.
We next come to the three items which are for work within the terms of the contract but for which the plaintiff claims extra compensation by reason of the fact that the specifications furnished by the Government did not comply with the code requirements of the city of Trenton. In all three instances the claims are under $500 and therefore do not require authorization in writing. We do not feel that it is necessary to state the facts in each of these items as they are fully set out in the special findings of fact and, therefore, it is only necessary to say that the plaintiff had the right to assume that the specifications as drawn by the Government complied with the municipal code of the city in which the building was to be erected and the contractor could not be expected to violate a law of the municipality in order to keep within the specifications of the contract. In each instance, the contracting officer’s representative orally instructed the plaintiff to comply with the municipal code, but in each instance payment was subsequently refused for the extra work performed. Upon the completion of the building, this work was accepted by the Government and the Government has received the benefit of it. The plaintiff is entitled to recover these three items, amounting to $279.00, $370.21, and $159.94, or a total of $809.15. Suburban Contracting Company v. United States, 76 C. Cls. 533; Venable Construction Company v. United States, 114 Fed. 763; and Griffiths v. United States, 77 C. Cls. 542.
The next claim made by the plaintiff is for the furnishing of heat for 30 days from November 15 to December 14,
In our opinion, the furnishing of this temporary heat by the plaintiff would have been unnecessary if plaintiff had not been delayed by the Government in the performance of its work, and, having been delayed by the Government, it is entitled to recover the actual damages it has sustained, which in this case is ‘the additional expense it has incurred. The plaintiff is entitled to recover on this item the sum of $1,200.
Plaintiff is entitled to a judgment in the sum of $14,-286.24. It is so ordered.