it
“1.
“2. Owner (defendants) agrees to retainthe services of builder (plaintiff) for the above project, said services to be as follows:
“a. Development of plat layout, to show building placement, total buildings, recreation area, parking, etc.
“b. On approval of area plat by both owner and city, builder will cause plans of proposed buildings to be drawn, for loan submission.
“c. Assist owner in obtaining adequate financing for completion of project, through first and secondary financing.
“d. Erect apartment buildings on owner’s ground in accordance with approved plans and specifications.
“3. Owner agrees to contract with builder to erect all buildings built at the above location, on a turn key basis, as services outlined in paragraphs 2a, b, c and d are performed.
“4. . . .
“5. Cost of the project shall be quoted as a ‘not to exceed figure,’ but in an amount not more than the proceeds from available financing, first and secondary financing. . . .
“. . . In the event owner contracts with a builder other than this company for buildings at the above location it is expressly understood by and between the parties to this agreement that builder shall be due a fee in the amount of $4,000.00, due and payable at that time.”
To us this agreement means that when plaintiff has performed 2a, b and c, defendants can then opt to: (1) have plaintiff “erect all buildings built,” or (2) contract “with a builder other than [plaintiff]” and pay plaintiff a “fee” of $4,000, or (3) build it themselves, or (4) not build at all. Plaintiff did perform 2a, b and c. Defendants opted for (2), another builder, plaintiff says, but failed to pay it the “fee.” It sued and a verdict for $4,000 followed. Plaintiff moved for inclusion of interest in the judgment from the “time” that defendants so opted
Defendants’ defenses are many, most in the way of avoidance rather than straight denial. They do deny they opted for (2) and assert it was (3), hence they owe nothing. Did they or didn’t they build it themselves? If they didn’t, then plaintiff is right, for the apartment was built. Our review of the evidence on this point discloses a factual question which was resolved by the verdict, indeed answered specifically. This answer by the jury is not against the manifest weight of the evidence, therefore, defendants’ citation of Pedrick v. Peoria & Eastern R. Co., 37 Ill2d 494,
In avoidance, defendants argue that plaintiff violated the Illinois Architectural Act (Ill Rev Stats 1965, c 10½) by agreeing to and indeed performing architectural services without being licensed. Plaintiff agrees that it is not a corporation which can offer and engage in such services but denies that it either agreed to or did so. The practice of architecture as defined in the Act, § 2, includes the offering or furnishing of professional services in connection with the construction or erection of any building, structure or project. Is this agreement an offer by plaintiff to perform architectural services? Even if it is not, did they do so in fact? If the answer is yes to either question, plaintiff’s right to recover becomes murky, to say the least.
We are of the opinion that offering to develop a plat layout (2a) to show placement, total buildings, etc., is not so connected with “construction” that it partakes of doing what architects do. If this is so, then performance likewise is outside of the Act. To be sure, there is a nexus between the layout and construction in the sense that placement must precede construction— but then so must the idea itself. “Construction” at the
Likewise with regard to 2b, causing plans of the proposed building to be drawn for loan submission, is not a statement by plaintiff that it will perform architectural services, rather, it is an agreement that they will cause such plans to be drawn for such purpose — loan submission — which may or may not be eventually connected with the projected construction and which may or may not be drawn by an architect — it all depends on how much detail the banker wants. We cannot assume that the implementation of this condition without more renders this contract void from its very beginning. It is neither an “offering” nor a “furnishing” so long as performed for the stated purpose.
The proof is that at plaintiff’s behest a non-Illinois architect prepared these plans for such purposes. In causing such to be prepared and limiting their use to the stated end — loan submission — plaintiff was not playing architect. Of course, since plaintiff did not build
Next, defendants say that their contract and plaintiff’s performance of it took place when plaintiff, a foreign corporation, lacked authority to transact business in Illinois, hence plaintiff lacked standing to sue. Section 157.125 of the Corporations Act, (Ill Rev Stats 1965, c 32) provides in part:
“No foreign corporation transacting business in this state without a certificate of authority shall be permitted to maintain an action at law or in equity in any court of this State, until such corporation shall have obtained a certificate of authority.”
It is true that at the time the agreement was entered into and plaintiff did what it did it was without authority to do so. But, it obtained the authority prior to filing suit. We read this section to mean that an out of state corporation with an Illinois based cause of action can’t sue until it has a certificate. This being so, plaintiff is in not out of court.
Even so, defendants tell us that the $4,000 “fee” is really a penalty and not a fee or liquidated damages and since plaintiff neither alleged nor proved damages none can be recovered. The last paragraph of the agreement seems perfectly plain. It says that if defendants select someone other than plaintiff to build after they have performed, there shall be due plaintiff “a fee in
The services required of plaintiff on paper were substantial. The fee was to be paid only if they did not get the job. The services were performed — though what actually was done is germane only in discovering whether the words actually used meant something else, that might give us a clue that “fee” means “penalty.” Plaintiff did appear before the plan commission of the city, the change in zoning was effected, it did prepare a feasibility study and the plans did help to secure a commitment for a substantial loan — $190,000. Plaintiff then solicited bids. All this took some doing and in the doing considerable time and some expense. The amount — $4,000 —is not out of line with these services, indeed, reasonable in every respect. Again, we are not saying that the fee should be paid because plaintiff performed these services, rather performance demonstrates that the “fee” is not a penalty — the exaction of an exorbitant sum of money which “does not, in fact, cause anything like equivalent damage to [plaintiff].” Burnett v. Nolen, 336 Ill App 376,
If defendants hadn’t built the building there would have been no fee. If defendants had built it there would have been no fee, and if plaintiff had built it, again, there would have been no fee. But, as we have seen, defendants opted otherwise, and the fee condition became operative. It doesn’t seem a bit unreasonable to us that a very important part of the consideration for this contract was
Apropos here is the following from Burnett v. Nolen, 336 Ill App 376,
“. . . For many years it has been the policy of the courts to constitute themselves the guardians and protectors of the individual who, though competent to contract, has entered into an improvident agreement to pay an exorbitant sum of money in event of his default in some respect which does not, in fact, cause anything like equivalent damage to the other party. Such a provision is called a ‘penalty,’ and the courts refuse to enforce it. On the other hand, courts do not desire to prohibit the parties from agreeing upon a reasonable sum as liquidated damages for breach of contract, especially where the possible damages are of such a nature they cannot be readily calculated or proved. . . .
“The following are some, but not all, of the elements considered by the courts in an attempt to solve the problem: ... (3) The fact that the contract does not purport to require or prohibit a certain act, but merely gives the option to do a particular thing or, in the alternative, pay a stipulated sum. The court may then hold the party had his election.”
What about fraud? Defendants say that they were lulled into the agreement by misrepresentations that the building would not exceed a certain sum. Misrepresentations, as we know, can in some circumstances constitute a fraud and vitiate an agreement. It is an affirmative defense in our context. Thus it must be alleged
Is plaintiff entitled to interest from “that time,” May 1, 1965, to be included in the judgment rendered December 8, 1967? Section 2 of the Interest Act, Ill Rev Stats 1965, c 74, reads:
“Creditors shall be allowed to receive at the rate of five (5) per centum per annum for all moneys after they become due on any bond, bill, promissory note or other instrument of writing; . . . .”
For interest to attach, prior to judgment, absent an agreement, the amount must be fixed, or determinable, and due, in the sense, that a debtor-creditor relationship has come into being. Here, the instrument very clearly said that the fee — indubitably, a fixed amount— would become “due and payable at that time” that defendants opted not for plaintiff but for another builder. It seems clear to us, at that instant interest began to run. The fact that the parties could reasonably differ as to defendants’ liability is not a consideration so far as
Accordingly, the judgment against defendants will be affirmed and the cross-appeal of plaintiff allowed. The cause is remanded with directions that plaintiff’s motion be allowed.
It is so ordered.
Affirmed in part; reversed in part and remanded.
CRAVEN, P. J. and MILLS, J., concur.
