108 Kan. 616 | Kan. | 1921
The opinion of the.court was delivered by
The Kansas Milling Company sued John A. Edwards for his failure to carry out a contract of July 15, 1914, for the delivery to it in that month of 5,000 bushels of wheat at 64 cents. Judgment was rendered for the plaintiff and the defendant appeals.
On July 23,, 1914, he wrote the plaintiff that he would be •unable to fill the order from the source he had intended, and five days later he asked an extension' through August and over September. The plaintiff replied that it was compelled to ask delivery by August 10. On August 5, 6 or 7 he talked with the agent of the company and told him he could fill the contract. The agent said not to ship the wheat; that the company could not .take it; that there was an embargo on, war was about to break out, there was financial havoc in Wichita, wheat had dropped and there was no market for it, and the plaintiff was now willing to extend the contract through August or even sixty days. The defendant then said that he had 5,000 bushels ready for delivery and could not hold it as he had no granary and would have to deliver it or dispose of it; that he had some unthreshed wheat on his Snake Creek ranch which he could deliver when it was threshed. The agent said the company would take 5,000 bushels of that wheat — to let it stay in the stack— that it could not take it then, and that the wheat market was way down and payment of wheat drafts was being refused. The defendant agreed to keep 5,000 bushels of the Snake Creek ranch wheat in stack for the plaintiff — keep it and .thresh it when it was wanted, provided it would not cost him anything to do it — provided the plaintiff would take care of it and look after him. The agent agreed to this proposal, saying that the company would make good whatever extra expense or trouble to the defendant was thereby occasioned. It was by reason of
It is a familiar rule that performance of a contract for the sale of a particular article — as for instance the crop from a specified tract — is excused by the accidental destruction thereof. (35 Cyc. 246; 6 R. C. L. 1005; 23 R. C. L. 1431; Note, L. R. A. 1916F 10, 20.) The contract here sued upon was not of that character at its inception, nor is it clear that it became such by subsequent agreement of the parties, assuming that the defendant’s version of the later negotiations is correct. Upon that assumption the plaintiff was not seeking to buy 5.000 bushels of the wheat from the Snake Creek ranch; the defendant might have filled the order with any wheat he was able to procure. The arrangement was entered into to meet the practical difficulties of the situation. The defendant was ready to make immediate delivery of other wheat, but the plaintiff was not able then to receive it. The defendant could not store or otherwise hold the wheat he was then ready to deliver', but could hold the wheat he had in stack and fill the order from this after it was threshed. So for the accommodation of the plaintiff it was agreed that there should be a delay in the shipment, and as this could only be accomplished by the use of the unthreshed wheat, that should be held for the purpose, the plaintiff indemnifying the defendant against any resulting expense or trouble. Whether or not these circumstances would bring the case within the rule relating to contracts for the sale of specific articles, there is room for a plausible contention that the defendant ought not to be held liable for the nondelivery of this wheat as the result of an accidental fire, because delivery would have been made from other wheat if the plaintiff had been ready to accept it.
The necessity of determining the_ rights of the parties under these conditions is in our judgment dispensed with by the action of the jury. The whole defense is based upon the theory of a delay in delivery having been arranged for the benefit of the plaintiff. At the request of the defendant this question among others was submitted to the jury, a negative answer being returned: “Did plaintiff at any time advise defendant to
The jury were instructed that the plaintiff could not recover if it had released the defendant from furnishing the wheat at any time when the defendant was ready, willing and able to comply with the terms of the contract. The evidence in behalf of the defendant was that early in August he had notified the plaintiff that he was ready to fill the contract — to ship the wheat — and had been told not to do so because the plaintiff could not take it. Such a transaction would have amounted for the time being to a release of the defendant from his obligation and the general verdict necessarily implied a finding that it had not taken place.
The jury returned a negative answer to this question, submitted by the defendant: “Did the plaintiff admit to the defendant in January, 1915, that there was only 3,850 bushels of wheat remaining due it on the 5,000-bushel contract of July 15th, 1914?” Complaint is made that this finding is against the undisputed evidence because a letter was produced written by the defendant on December 3, 1914, containing the language “the amount of wheat remaining due on the old contract, after the overages from the other contracts are figured in, is around 3,850 bushels as these statements will show you.” It will be observed that the question specifically related to January, while the letter was written in December.
Complaint is made of the refusal of instructions asked concerning the authority of a person whose agency for the milling company was alleged by the defendant and denied by the plaintiff. Inasmuch as the jury specifically found that he was the plaintiff’s agent, the omission was immaterial.
An attempt was made by the defendant to impeach the verdict by the affidavit of a juror as to how an instruction had been understood by the jury. This of course was ineffectual. (Perry v. Bailey, 12 Kan. 539, 545; 29 Cyc. 984.)
The cause is remanded with directions to modify the judgment by deducting the amount indicated.