73 Mo. App. 439 | Mo. Ct. App. | 1898
This is an action brought in the name of Kansas City to the use of certain Jaborers who did work in grading a street for which defendant McDon-aid had a contract. The other defendants were McDonald's sureties on the contract, wherein, according to the city charter, the contractor covenanted to pay for all labor and materials furnished in the prosecution of the work and defendants Russel and Wyman signed the contract as guarantors that said covenant should be performed. The circuit court sent the case to a referee with authority to find the facts and declare the law. The referee found that McDonald, the contractor, was indebted to
The sole question is one of limitation. Was the action begun within the time provided in the city charter ? The right of action has its origin under the provisions of section 20, article 9, Kansas City charter of 1889, which provides that “contracts for making city improvements on streets, etc., * * * shall containa covenant on the part of the contractor or contractors with the city, to pay for the work and labor of all laborers, etc., * * * and performance of such covenant shall be guaranteed by two or more sureties signing the contract. * * * No action shall be brought or prosecuted for the benefit of the laborers, teamsters, etc., * * * unless the suit be commenced within three months after the completion of the work to be done under the contract and acceptance thereof by the city.” The above italicised words of the charter must fix the rights of these litigants. It will be seen that this special statute of limitation begins to run when the work is completed and accepted by the city. This suit was instituted on the twenty-sixth day of February, 1896. The question is whether at that date more than three months had expired since the grading of the street was finished and accepted by the proper city authorities. If so, then the action was barred, otherwise it was not. In order to save the right of action, it is clear then that the completion and acceptance must have been not earlier than November 26, 1895.
“ ‘I hereby certify that I have caused to be carefully measured and computed the amount of work done under this contract, and that the above quantities and amounts are correct.
“ ‘On November 15th, 1895, the city engineer reported the contract in question completed and ready for ■'acceptance and payment in special tax bills. (See his certificate on page 21.) I hereby certify that the above work has been completed in accordance with the specifications and recommend the acceptance of the work, and know of no reason why the tax bills should not be issued in accordance with the contract and specifications therefor.’ To the same instrument, and of the same date, is the following certificate:
“ ‘The Board of Public works hereby accepts said work.
“ ‘By order of the Board of Public Works.
“ ‘Peter H. Tiernan,
“ ‘President.
“ ‘(Seal). “ ‘Attest: “ ‘H. P. Langworthy, Secretary.’
“On November 20th, 1895, the list of property to be assessed and chargeable with the cost of the work under the contract in question, which was referred to the city assessor on November 12th, was received from the city assessor, the assessment having been completed. On November 22d, the cost of grading under the contract was apportioned to the different pieces of property by the engineering department. On Tuesday, November 26th, 1895, the board of public works computed the cost of grading College avenue from 24th to 26th street as provided by ordinance 6193, approved February 28th, 1895. This is shown by the testimony of R. M. Godfrey, testifying from the records of the board of public works which he had before him. On November 26th, we also find the following entry made by the city engineer:
“ 'Work accepted and estimate approved for $475.20, this 26th day of November, 1895.
“ 'H. H. Filley, City Engineer,
“ ‘Tax bills issued November 27th, 1895.
“ 'John Malony, Chief Clerk.’
“The above testimony is undisputed.”
Mr. Fidler, the referee, then proceeds to discuss the question as to whether or not the work of the contractor was accepted by the city on November 15 or
The contention of plaintiff’s counsel, based on that provision of the contract which in effect stipulates that before . the contractor shall receive pay for his work the same shall be “completed in the manner set forth in this agreement to the satisfaction and acceptance of the city engineer,” can have no weight in determining who, under the charter, has authority to represent the city in accepting the work. For even if we concede that the contract is subject to the interpretation given by counsel, then it is manifestly opposed to the terms of the municipal charter, and in so far as it so conflicts can have no force or effect.
We agree then with the referee that this action can not be maintained, because commenced more than three months after the "’work was completed and accepted by the city. It follows that the judgment, which was for the plaintiffs, must be reversed.