71 P. 525 | Kan. | 1903
The opinion of the court was delivered by
Fred. Frey sued the Kansas City-Leavenworth Railway Company, alleging that he had been injured November 30, 1899, by falling into a ditch dug in the public highway by the defendant, and negligently left unguarded. The answer included a general denial. A trial was had, and the jury returned a
The evidence is not incorporated in the record. The findings of the jury are, in substance, that the defendant entered into a contract with the Cleveland Contracting Company, dated May 28, 1899, to construct, build and equip its railroad; that the Cleveland Contracting Company “took charge of, and started to work under said contract” ; that the contract was not completed at the time of the injury; that the operation of cars on the railroad for other than construction purposes began January 15, 1900; that at the time of the injury the Cleveland Contracting Company had not turned over the .road or offered to turn it over to defendant; that the Cleveland Contracting Company hired and had control of the men actually employed in the physical performance of said contract, and had the power to control and discharge them. The only special findings in addition to the foregoing were those numbered 4, 5, and 6, which were as follows :
“4. Who was the person in charge of the men who dug the ditch in question ? Ans. A man named Craig.
“5. For whom was such foreman working? A. Cleveland Contracting Company.
“6. Who paid the foreman and men who dug the ditch? A. Cleveland Contracting Company.”
The brief of the defendant in error is principally devoted to the argument that, notwithstanding the fact that the ditch may have been dug by an independent contractor, whose negligence caused the injury, the defendant is liable, the case falling within each of
Plaintiff in error in its brief, however, contends that the case does not involve any question of law as to the general rule of independent contractors, or as to exceptions to it,-and argues that the special findings negative the allegation of the petition that the defendant company dug the ditch in question, and that, therefore, judgment should have been given against the plaintiff. Its claim in effect is that, to sustain a recovery in this action, plaintiff should have pleaded that the contracting company dug the ditch, but that the circumstances were such as to render the defendant company liable for the negligence of the contracting company; in other words, that the relation of an employer to an independent contractor for whose negligence he is liable on account of some exceptional circumstances is not that of master to servant, or principal to agent, and that, therefore, an allegation that the employer performed an act is not sustained by evidence or a finding that the contractor performed it, even though some principle of law other than respondeat superior renders the employer liable.
With the view we take of the findings, however, it is not necessary to determine the questions of law that are argued in either brief. We hold that the special findings are not necessarily inconsistent with the general verdict for two reasons : First, they do not affirmatively show that the contract between the railroad company and. the construction company did not reserve to the defendant sufficient control to make it liable upon the principle of respondeat superior. The
*300 “It is obvious that the control stipulated for in the contract may be so absolute as to make the discretion of the contractor wholly subordinate to that of the principal, or to that of his engineer, architect, or other superintendent; in which case, the relation of.master and servant is deemed to arise, and the maxim of respondeat superior applies. Whether this is so must depend in each case upon a just interpretation of the contract itself.” (1 Thomp. Neg. §661.)
The jury may have based their general verdict upon evidence that, so far as relates to the construction of this ditch, the contracting company was the agent or servant of the defendant. Such evidence would make the special findings support the allegation of the petition that the plaintiff dug the ditch.
“We cannot assume the existence of facts that would impair the validity of the judgment, but should rather presume the facts to be such as are not inconsistent with those specially found and yet will sustain the judgment that was given.” (Pennell v. Felch, 55 Kan. 78, 39 Pac. 1023.)
Where the evidence is not preserved in the record, the special findings, in order to require this court to reverse a judgment based upon a general verdict, must be necessarily inconsistent with any reasonable theory tenable under the pleadings that would support the judgment. If we assume that the contract here involved, while leaving the contracting company in immediate charge of the workmen, reserved to the defendant a right to direct the methods to be pursued —and there is no finding to the contrary — there remains no inconsistency between the special findings and the general verdict or the petition.
The judgment of the district court will therefore be affirmed.