KAMMER ASPHALT PAVING CO, INC v EAST CHINA TOWNSHIP SCHOOLS
Docket No. 93937
Supreme Court of Michigan
August 3, 1993
443 MICH 176
Argued May 4, 1993 (Calendar No. 3).
The court, James T. Corden, J., consolidated the cases, and granted summary disposition for the district, finding no legal duty for governmental units to ensure the validity of payment bonds, thereby foreclosing the subcontractors’ negligence claim. It further found that the subcontractors’ unjust enrichment, constructive trust, and breach of contract to a third-party beneficiary claims were insupportable. The Court of Appeals, CAVANAGH, P.J., and CONNOR and R. J. SNOW, JJ., affirmed in an unpublished opinion per curiam (Docket No. 126596). Kammer appeals.
In an opinion by Justice RILEY, joined by Justices LEVIN, BRICKLEY, BOYLE, and MALLETT, the Supreme Court held:
A governmental unit has a duty to verify the validity of a payment bond furnished by a general contractor of a public works project.
1.
2. Because the district failed to notify the plaintiff of the fraudulent nature of the bond, after it had assured the plaintiff that the bond would secure its interest, a reasonable mind could find that the district was unjustly enriched. Thus, the plaintiff must be permitted to go forward in equity for its claim of damages that arose after the certification of the bond and the district‘s verbal assurances of the plaintiff‘s protection by it.
3. A constructive trust may be imposed where necessary to do equity or to prevent unjust enrichment. It may not be imposed upon parties who in no way have contributed to the reasons for imposing it. Examining the evidence in the light most favorable to the plaintiff, the district verbally assured the plaintiff that it was protected by the bond and certified its validity when it provided certified copies. The plaintiff should be permitted to prove at trial that it would not have continued construction without relying upon this representation, and thus that the district received the benefit of the plaintiff‘s labor and that a constructive trust was established.
4. The plaintiff may not recover as a third-party beneficiary as defined by
Affirmed in part and reversed in part.
Chief Justice CAVANAGH, joined by Justice GRIFFIN, concurring in part and dissenting in part, stated that the public works act does not impose a duty on a contracting governmental unit to verify the validity of a payment bond furnished by the general contractor of a public works project. Thus, the plaintiff failed to state a cause of action in negligence.
The district performed its obligations under the general
SCHOOLS — PUBLIC WORKS PROJECTS — PAYMENT BONDS — LIABILITY TOWARD SUBCONTRACTORS.
A governmental unit has a duty to verify the validity of a payment bond furnished by a general contractor of a public works project (
Mager, Monahan, Donaldson & Alber, P.C. (by Lita Masini Popke and Lawrence M. Scott), for the plaintiff.
Thrun, Maatsch & Nordberg, P.C. (by Patrick J. Berardo and Gordon W. Van Wieren, Jr.), for the defendant.
REFERENCES
Am Jur 2d, Contractors’ Bonds § 58.
See ALR Index under Contractors’ Bonds.
RILEY, J. Because we find that
I
Because plaintiff‘s complaint was dismissed on summary disposition, we view the facts in the light most favorable to plaintiff. Stevens v McLouth Steel Products Corp, 433 Mich 365, 370; 446 NW2d 95 (1989).
On April 23, 1987, defendant, East China Township Schools, entered into a general construction contract with a general contractor, Dougherty Construction, Inc., for the construction and renovation of athletic facilities in the district.2 As required by the public works act,3 Dougherty furnished defendant a performance bond4 and a payment bond.5 The bonds were standard, preprinted, American Institute of Architects forms, with the name of the surety, American Seaboard Indemnity & Insurance Company of Peachtree City, Georgia, printed across the top of each bond.
Dougherty entered into a contract with plaintiff, subcontractor Kammer Asphalt Paving Co, for certain base and paving work. In consideration of plaintiff‘s services, Dougherty agreed to pay Kammer $217,906. In October of 1987, plaintiff notified Dougherty, as well as the school district, of its intended performance and its reliance upon the payment bond.
In accordance with the general contract, the project‘s architect, DiGeronimo Associates, disbursed progress payments to Dougherty as the project advanced. Dougherty, however, was not as
On August 15, 1988, defendant discovered that the furnished bonds were invalid and unenforceable—American Seaboard Indemnity & Insurance Company did not exist. Dougherty ignored defendant‘s subsequent demands for valid bonds. On October 21, 1988, defendant issued a notice of termination to Dougherty because of its failure to furnish the required bonds, at which time plaintiff first became aware of the fraudulent nature of the bonds.
Defendant then filed suit in St. Clair Circuit Court against Dougherty Contractors and William Dougherty. In a separate action, plaintiff filed suit against Dougherty, DiGeronimo, defendant, and various members of the East China School Board. Four other subcontractors separately filed similar actions. In response to defendant‘s motion, the trial court consolidated the subcontractors’ five separate suits with defendant‘s action against Dougherty.
Following consolidation of the lawsuits, defendant filed a countercomplaint and third-party complaint for interpleader, naming all of Dougherty‘s subcontractors as parties. Defendant sought to deposit the remaining contract funds6 with the trial court for a determination regarding its proper distribution. Defendant proposed that the
On March 16, 1989, defendant filed a motion for summary disposition pursuant to MCR 2.116(C)(8) and (10) with regard to the subcontractors’ claims against the school district. The circuit court granted defendant‘s motion, finding no legal duty for governmental units to ensure the validity of the bonds, which foreclosed the subcontractors’ negligence claim.8 Furthermore, the court found that the subcontractors’ unjust enrichment, constructive trust, and breach of contract to a third-party beneficiary claims were unsupportable. The Court of Appeals affirmed in an unpublished per curiam opinion. This Court granted plaintiff‘s application for leave to appeal on December 8, 1992.9 441 Mich 894.
II
Because materialmen and contractors may not obtain a mechanics’ lien on a public building,10 the Legislature requires the posting of performance and payment bonds by a general contractor before construction on a public building may commence.
The Court of Appeals, relying on prior author-
The dissent, however, fails to examine the current statute as a whole. “In every exposition of a statute, the intention of the Legislature is undoubtedly the end to be sought . . . .” Leoni Twp v Taylor, 20 Mich 148, 154-155 (1870). Thus, when legislative intent is clearly revealed in an unambiguous statute, the plain language of the statute must be enforced. Farm Products Co v Jordan, 229 Mich 235, 239; 201 NW 198 (1924). Nevertheless, because “a clause which, standing by itself, might seem of doubtful import, may yet be made plain by comparison with other clauses or portions of the same law,” a fundamental principle of statutory interpretation is that “the whole is to be examined with a view to arriving at the true intention of each part . . . .” 1 Cooley, Constitutional Limitations (8th ed), p 127.17 If judicial construction is necessary, the Court must discern the Legislature‘s intent by examining “the object of the statute, the harm which it is designed to remedy, and apply a reasonable construction which best accomplishes the statute‘s purpose.” In re Forfeiture of $5,264, 432 Mich 242, 248; 439 NW2d 246 (1989).
In the instant case, plaintiff requested and was provided copies of the bonds nearly a year before the termination of the project, at which time defendant certified that the bonds were properly executed. Plaintiff, therefore, is entitled to proceed on the negligence count because defendant‘s provision of the certified copies was prima facie evidence that the bonds were valid, and defendant is liable for the resulting damages stemming from its failure to verify the bonds’ validity.24
III
Even though no contract may exist between two parties, under the equitable doctrine of unjust enrichment, “[a] person who has been unjustly enriched at the expense of another is required to make restitution to the other.” Restatement Restitution, § 1, p 12. The remedy is one by which “the law sometimes indulges in the fiction of a quasi or constructive contract, with an implied obligation to pay for benefits received” to ensure that “‘exact
A
The Court of Appeals analysis must be rejected because defendant failed to notify plaintiff of the fraudulent nature of the bonds after it had assured plaintiff the bonds would secure its interests. Defendant was aware over a year before the termination of the contract that Dougherty was failing to compensate plaintiff and other subcontractors, and plaintiff repeatedly informed defendant of its reliance upon the bonds to secure compensation. Indeed, defendant indicated that there was no need to worry because the payment bond protected the subcontractors’ interest. However, defendant knew for approximately seventy-five days that the bonds were fraudulent, and never notified plaintiff until after it terminated its contract with Dough-
B
Whether defendant was unjustly enriched before actual knowledge of the invalidity of the bonds is a closer issue. Although plaintiff indirectly provided defendant a benefit, its contract was with Dougherty, and the benefit it provided was in exchange for compensation. The risk of nonpayment could be understood to rest with plaintiff.27 Moreover, defendant paid the general contractor $1.3 million
IV
A constructive trust may be imposed “where such trust is necessary to do equity or to prevent unjust enrichment . . . .” Ooley v Collins, 344 Mich 148, 158; 73 NW2d 464 (1955). Hence, such a trust may be imposed when property “‘has been obtained through fraud, misrepresentation, concealment, undue influence, duress, taking advantage of one‘s weakness, or necessities, or any other similar circumstances which render it unconscionable for the holder of the legal title to retain and enjoy the property . . . .‘” Potter v Lindsay, 337 Mich 404, 411; 60 NW2d 133 (1953), quoting Racho v Beach, 254 Mich 600, 606-607; 236 NW 875 (1931).28 Accordingly, it may not be imposed upon parties “who have in no way contributed to the reasons for imposing a constructive trust.” Ooley, supra at 158. The burden of proof is upon the person seeking the imposition of such a trust. MacKenzie v Fritzinger, 370 Mich 284; 121 NW2d 410 (1963). The Court of Appeals held that plaintiff failed to allege sufficient facts necessary to establish such a cause of action.29
V
Plaintiff further suggests that the Court of Appeals erred in denying its third-party beneficiary claim.
Any person for whose benefit a promise is made by way of contract, as hereinafter defined, has the same right to enforce said promise that he would have had if the said promise had been made directly to him as the promisee.
(1) A promise shall be construed to have been made for the benefit of a person whenever the promisor of said promise has undertaken to give or to do or refrain from doing something directly to or for said person.
The Court must objectively determine “from the form and meaning of the contract itself” whether a party is a third-party beneficiary as defined in
At best, plaintiff is an incidental beneficiary of the general contract. As noted by this Court in Greenlees v Owen Ames Kimball Co, 340 Mich 670, 676; 66 NW2d 227 (1954), plaintiff has no remedy under the contract between Dougherty and defendant:
“An incidental beneficiary has no rights under the contract. A third person cannot maintain an action upon a simple contract merely because he would receive a benefit from its performance or because he is injured by the breach thereof. Where the contract is primarily for the benefit of the parties thereto, the mere fact that a third person would be incidentally benefited does not give him a right to sue for its breach.”
The Court of Appeals dismissal of the third-party beneficiary claim, therefore, is affirmed.
VI
Because we find that
LEVIN, BRICKLEY, BOYLE, and MALLETT, JJ., concurred with RILEY, J.
CAVANAGH, C.J. (concurring in part and dissenting in part). I concur with the majority‘s conclusion that the trial court properly granted summary disposition with regard to the third-party beneficiary count. I write separately, however, because I dissent from the majority‘s holding that the public works act1 imposes upon a contracting governmental unit the duty to verify the validity of payment bonds. Furthermore, I would hold that the trial judge properly granted the defendant‘s motion for summary disposition with regard to the plaintiff‘s negligence, unjust enrichment, and constructive trust claims.
I
The majority‘s holding is contrary to the history of the public works act, the clear and unambiguous directives of the entire act, as well as federal case law interpreting similar legislation.
A
An early version of the public works act explicitly imposed a duty on a contracting governmental unit to require payment bonds:
When public buildings or other public works are about to be built, repaired or ornamented under contract at the expense of the State, or of any county, city, village, township or school district thereof, it shall be the duty of the board of officers or agents, contracting on behalf of the State, county, city, village, township or school district, to require sufficient security by bond for the payment by the contractor of all subcontractors and for the payment for all labor performed and materials furnished in the erection, repairing or ornamenting of such building or works. [1905 PA 187, § 1,
MCL 570.101 ;MSA 26.321 . Emphasis added.]
Accordingly, this Court held that a governmental unit is liable to subcontractors for damages incurred because of the government‘s failure to require a payment bond for a public project. “[A] total failure to require such bond is such a breach of duty as authorizes an action by the party injured against members of the board or municipal body in their individual capacity.” Alpena v Title Guaranty & Surety Co, 158 Mich 678, 680; 123 NW 536 (1909). Smith v Hubbel, 142 Mich 637, 644-645; 106 NW 547 (1906).2
The statute, as presently enacted, however, does not impose a duty on a governmental unit:
Before any contract, exceeding $50,000.00 for the construction, alteration, or repair of any public building or public work or improvement of the state or a county, city, village, township, school district, public educational institution, other political subdivision, public authority, or public agency hereinafter referred to as the “governmental unit,” is awarded, the proposed contractor, hereinafter referred to as the “principal contractor,” shall furnish at his or her own cost to the governmental unit a performance bond and a payment bond which shall become binding upon the award of the contract to the principal contractor. . . . [
MCL 129.201 ;MSA 5.2321(1) . Emphasis added.]
If the Legislature had not been concerned with alleviating the statutory duty imposed on a governmental unit contracting for a public project, then there would have been no need to remove the words imposing such a duty. While we are not privy to the Legislature‘s reasons for excluding the language that imposed the duty, such a change facilitates the public policy favoring individual involvement in public service, while simultaneously providing a remedy for unpaid subcontractors.3 Regardless of the Legislature‘s motives, the clear effect of the change is apparent:
[T]he mere fact that the legislature enacts an amendment indicates that it thereby intended to change the original act by creating a new right or withdrawing an existing one. Therefore, any material change in the language of the original act is presumed to indicate a change in legal rights. . . . This is a rule peculiar to amendments and other
acts purporting to change the existing statutory law. [1A Sands, Sutherland Statutory Construction (4th ed), § 22.30, p 265.]4
It is obvious that the Legislature was aware of the explicit statutory duty imposed on a governmental unit contracting for the construction or improvement of a public project. It is equally apparent that the Legislature was aware of this Court‘s line of cases imposing the statutory mandate. Armed with this knowledge, the Legislature excluded the language from the public works act that imposed the duty on a governmental unit to require the necessary bonds. Accordingly, we must give effect to its action.
Furthermore, the clear language of the statute supports the conclusion that the statute no longer imposes a duty on a governmental unit to require a bond.5 The statute, as presently enacted, requires the general contractor to furnish to the governmental unit payment and performance bonds. The statute clearly and unambiguously delegates the duty to the general contractor, not the government unit. “If the language employed in a statute is plain, certain and unambiguous, a bare reading suffices and no interpretation is necessary.” Dussia
B
The majority‘s holding is also contrary to federal case law applying the federal counterpart of the public works act, the Miller Act.7 Federal precedent applying the Miller Act, while not controlling, is instructive because of the similarities between the two acts and because the Michigan statute is modeled after the Miller Act. Pi-Con, Inc v AJ Anderson Construction Co, 435 Mich 375, 381; 458 NW2d 639 (1990). In Arvanis v Noslo Engineering Consultants, Inc, 739 F2d 1287 (CA 7, 1984), the general contractor of a federal public works project failed to furnish a payment bond as
Realizing that a party cannot be liable in negligence absent a duty to act, the United States Court of Appeals for the Seventh Circuit inquired into whether the Miller Act imposed a duty on the government to require a payment bond. The court, on the basis of the clear directives of the statute, answered unequivocally that it did not.
The statute requires only that contractors obtain performance and payment bonds. The statute places no affirmative obligation on the government, and says absolutely nothing about when the contractor fails to furnish the bond. The Act grants a very narrow and specific position: the right to sue on the bond (if there happens to be one) . . . . [Id. at 1290.]
While the court acknowledged that there was a gap in the statute, it recognized that it could provide no remedy—“especially in view of the very narrow remedy actually granted by the statute.”9 Id.
Having found no statutory duty for governmental units to require or verify the validity of a payment bond, I would affirm the trial court‘s holding that the plaintiff failed to state a cause of action in negligence.10
II
The majority holds that the trial court improperly dismissed the plaintiff‘s claims of unjust enrichment and constructive trust. When reviewing orders granting a party‘s motion for summary judgment, the Court must view the evidence in a light most favorable to the opposing party. If reasonable minds could disagree regarding the conclusions to be drawn from the facts, the order granting summary judgment must be reversed. If, however, reasonable minds could not disagree, the order of summary disposition must be affirmed. DiFranco v Pickard, 427 Mich 32, 54; 398 NW2d 896 (1986).
A
The plaintiff readily admits that neither an express contract nor a contract implied in fact between the plaintiff and the defendant existed. The plaintiff asks this Court, however, to imply a contract in law in order to prevent the defendant from being unjustly enriched to the detriment of the plaintiff.
When a party is unjustly enriched, the law generally requires the benefited party to provide restitution for the benefit received. Courts often employ the legal fiction of a contract implied in law or quasi contract to justify payment where no contract exists. Detroit v Highland Park, 326 Mich 78, 100; 39 NW2d 325 (1949). To recover under this theory the plaintiff must show that the defendant received a benefit from the plaintiff and that it would be unjust for the defendant to retain that benefit. Buell v Orion State Bank, 327 Mich 43, 56; 41 NW2d 472 (1950). We must be cautious in applying this doctrine, however, because the mere fact that a benefit has been conveyed does not necessarily indicate that it is unjust for the party to retain that benefit.
Even where a person has received a benefit from another, he is liable to pay therefor only if the circumstances of its receipt or retention are such that, as between the two persons, it is unjust for him to retain it. The mere fact that a person benefits another is not of itself sufficient to require the other to make restitution therefor. [Restatement Restitution, § 1, comment c, p 13.]
It is undisputed that the plaintiff bestowed a benefit to the defendant through the paving work completed on the project. However, it is not unjust
B
Similarly, the plaintiff‘s request for the imposition of a constructive trust on the amount of the contract fund not paid to Dougherty must fail. Like a contract implied in law or quasi contract, a constructive trust is imposed as a remedy to prevent unjust enrichment.12
The constructive trust, as it was put by Mr. Justice Cardozo, “is the formula through which the conscience of equity finds expression. When property has been acquired in such circumstances that the holder of the legal title may not, in good conscience, retain the beneficial interest, equity converts him into a trustee.” [Kent v Klein, 352 Mich 652, 656; 91 NW2d 11 (1958). Citation omitted.]
The remedy of a constructive trust will be imposed when it is inequitable under the circumstances13 to allow one to retain property.
The plaintiff‘s constructive trust theory must fail for the same reason the unjust enrichment claim failed: the defendant has not been unjustly
III
The public works act does not impose a statutory duty on a contracting governmental unit to verify the validity of the payment bond furnished by a general contractor of a public works project. Absent a duty owed to the plaintiffs, the plaintiffs cannot maintain an action in negligence. Furthermore, the trial court properly dismissed the plaintiffs’ claims of unjust enrichment, constructive trust, and breach of contract to a third-party beneficiary.
Accordingly, I would affirm the judgment of the Court of Appeals.
GRIFFIN, J., concurred with CAVANAGH, C.J.
Notes
See also Adamo Equipment Rental Co v Mack Development Co, Inc, 122 Mich App 233, 236; 333 NW2d 40 (1982). The majority refers to City of Ingleside v Stewart, 554 SW2d 939 (Tex Civ App, 1977), as support for its conclusion that the trial court improperly dismissed the plaintiff‘s unjust enrichment claim. Ante, p 187. Chief Judge Nye, the author of the Stewart opinion, explained the parameters of Stewart in Corpus Christi v Acme Mechanical Contractors, 736 SW2d 894, 899 (Tex App, 1987):The necessity for providing some means of protecting contractors, subcontractors, laborers, or materialmen, who perform labor or furnish materials for improvement of real property has been recognized in this state prior to the time that it was a state. See 2 Territorial Laws 331 (1827). . . .
To [fulfill] the state‘s basic policy to protect laborers and materialmen in construction work contracts . . . the Legislature adopted the forerunner of [
MCL 129.201 et seq. ;MSA 5.2321(1) et seq. ]. The purpose of that statute was to provide protection in the construction of public buildings where protection is not afforded by the mechanics’ lien law . . . . [Milbrand Co v Dep‘t of Social Services, 117 Mich App 437, 440; 324 NW2d 41 (1982).]
The facts that compelled the Stewart court to impose liability on the city on the basis of quantum meruit are distinguishable in several respects. The general contractor in Stewart failed to post the statutorily mandated bonds upon the advice of the city‘s architect. Furthermore, “there was other evidence that the City impliedly agreed to pay the appellee [subcontractor] for its work.”In effect, this Court held that a subcontractor who was able to prove that the City had “stepped into the shoes of the general contractor and chose to supervise and finish the job and pay some of the laborers and subcontractors,” was liable to the subcontractor on the theory of quantum meruit.
The trial court specifically found and the evidence supports such findings that the City initiated a dual payee system [each check drawn from the construction project‘s fund was made out to the general contractor and the subcontractor to be paid] and took over the job when the contractor overspent his withdrawals. The record showed that the City assumed and undertook the duties of the general contractor and paid the laborers and subcontractors. [Stewart at 944.]
The case at bar does not present a factual situation warranting a determination of unjust enrichment. The school district did not step into the shoes of the general contractor, nor did it act in such a manner that would allow the plaintiff to infer that the school district would pay the subcontractors for their services.
Contrary to the assertions of the dissent, this analysis is independent of the status of the governmental entity, i.e., the city need not step into the shoes of the general contractor to be held liable for its failure to ensure a validly executed bond protects the subcontractors.
