In an action to recover damages for
Ordered that the judgment is reversed insofar as appealed and cross-appealed from, on the law and the facts, without costs or disbursements, and the matter is remitted to the Supreme Court, Suffolk County, for entry of a judgment in accordance herewith.
The facts underlying this appeal are set forth in the decision and order made upon the parties’ prior appeal to this Court (see, Kaiser v Fishman,
At the retrial on damages, both parties presented the testimony of expert witnesses to establish the cost to cure the defects in the dwelling. The plaintiff’s expert witness, James V. Zizzi, a licensed building contractor with experience in construction of beachfront homes set atop pilings, estimated that it would cost $214,764 to bring the dwelling into conformance with the plans and specifications. He identified the work needed to be done, solicited bids from subcontractors, and factored in the costs for general labor and materials. Zizzi factored in the costs of physically moving the house in order to add six additional pilings to the 14 existing pilings to conform to the original plans, as well as reconfiguring the six pilings that were drilled in incorrect locations. Zizzi’s estimate did not provide for the replacement of the nonconforming "two by eight” floor joists installed by the defendant. Rather,
The defendant’s expert witness, August LaRuffa, a structural engineer also experienced in the design of homes erected on pilings, submitted an estimate of $30,555 to modify the structure. LaRuffa, who inspected the house on two occasions and who reviewed the original plans, recommended, among other things, the addition of flitch plates to reinforce the "whalers” or main girders notched into the pilings, and emphasized that his recommendations were not structurally necessary but, rather, were required to render the structural elements equal to or better than called for by the plans and specifications. Mr. LaRuffa did not provide an estimate of the cost to upgrade the heating system, nor did his estimate provide for the disturbance of the existing pilings or moving the dwelling to insert additional pilings.
Following a nonjury trial, the court determined that it would be an unreasonable and unconscionable waste to remove or destroy the existing habitable house and that any defects which constituted a breach of contract could be cured by strengthening the existing structure. Essentially adopting the defendant’s expert’s remedial approach, which called for the repair of the structure without physically lifting it off of its pilings, the court awarded the plaintiff $60,000 in cost-to-cure damages, with interest from August 9, 1984, to April 30, 1990, at 9%, and $16,653.21 for out-of-pocket expenses together with interest of $866.42, calculated at a rate of 9% for the period from October 1, 1989, to April 30, 1990. These amounts were offset by the amount due from the plaintiff to the defendant as of the date of the plaintiff’s default, May 5, 1982, under the terms of the purchase money mortgage ($49,849.63) together with interest at 16% from May 5, 1982, to July 2, 1985 ($25,214.90) and interest from July 2, 1985, to April 30, 1990, at 9% ($21,670.27). Based upon those figures, the plaintiff’s total award amounted to $11,705.38. Asserting that that award is inadequate, the plaintiff now appeals. The defendant cross-appeals from (1) so much of the judgment as
Where, on appeal from a judgment rendered after a nonjury trial, it appears that on all of the credible evidence a finding different from that of the trial court would not have been unreasonable, then this Court must weigh the relative probative force of conflicting testimony and inferences (see, Shipman v Words of Power Missionary Enters.,
The plaintiff established that his expert’s proposed method of repairs would best place the plaintiff in the position he would have been in had the defendant performed the contract in accordance with the plans and specifications. The defendant’s expert did not provide for the correction of all of the defects in construction and failed to conduct a structural
Having determined that the plaintiff’s expert’s method of cure is the one to be adopted, it follows that the plaintiffs evidence as to the cost of that cure, to wit, $214,764, must be credited, as only the plaintiff adduced proof as to the cost of the necessary repairs. Indeed, the defendant completely failed to offer any evidence as to the costs to fix the dwelling so as to conform to contract plans and specifications, opting only to estimate the cost of insufficient and less expensive remedial measures. "[W]here an adverse party fails to present valid evidence on valuation, the court is obliged to accept the remaining expert testimony unless it 'provides a sufficient explanation for its decision and there is other evidence in the record to support the court’s determination’ ” (Yonkers City Post No. 1666 v Bottiglieri,
Additionally, we find that the trial court erred in awarding interest on damages for breach of contract from August 9, 1984, the date of the commencement of the first trial. A plaintiff in a breach of contract case is entitled to interest from the earliest ascertainable date the cause of action accrued (see, CPLR 5001 [b]; M. C. D. Carbone, Inc. v Town of Bedford,
We also find that the trial court erred in awarding interest with respect to sums expended in the mitigation of damages from the date the second trial commenced, i.e., October 1, 1989. The parties stipulated to the amount expended by the plaintiff in mitigating damages, the dates these expenses were incurred, as well as the daily interest to be computed thereon. While CPLR 5001 (b) permits the court to choose a "single reasonable intermediate date” to compute interest where damages were incurred at various times, there was no need to use such a date since the parties stipulated to the amounts owed. The trial court should have utilized this information and calculated interest on each expenditure from the date which it was incurred. We note that most of the sums expended by the plaintiff in mitigating damages were prior to 1983. Since interest is "simply the cost of having the use of another person’s money for a specified period [and] [i]t is intended to indemnify successful plaintiffs for the nonpayment of what is due them” (Love v State of New York,
Finally, inasmuch as the mortgage made no provision for the payment of interest following maturity of the underlying debt, we find that the trial court should have awarded interest on the unpaid balance due on the mortgage at the rate of 16% until the date the defendant exercised his option to accelerate the mortgage, and at the rate of 9% thereafter (see, Ward v Walkley,
