KAFKA CONSTRUCTION, INC., Appellant, v NEW YORK CITY SCHOOL CONSTRUCTION AUTHORITY, Respondent.
Appellate Division of the Supreme Court of New York, Second Department
5 NYS3d 167
Ordered that the order is affirmed, with costs.
On January 15, 2008, the defendant, New York City School Construction Authority (hereinafter the SCA), awarded a contract to the plaintiff, Kafka Construction, Inc. (hereinafter Kafka), to perform certain construction work at Hillcrest High School in Queens County for the sum of $12,463,000. Work commenced on or about February 1, 2008, and a certificate of substantial completion was issued on September 23, 2009.
In early 2011, the SCA purportedly requested that Kafka provide an estimate of the value of the work that was not actually performed, such that a credit could be issued against the contract amount. In response, on February 4, 2011, Kafka issued a change order proposal, which set forth a proposed credit amount in the sum of $192,608.18 to be deducted from the price of the work performed. However, by email dated September 14, 2011, the SCA informed Kafka that it calculated the credit for the work not performed at $814,535. On or about September 29, 2011, Kafka served upon the SCA a notice of claim asserting that the SCA owed it $621,926.82, i.e., the difference between the parties’ proposed credit amounts.
On or about August 30, 2012, after the parties engaged in unsuccessful negotiations regarding the credit, the SCA issued a unilateral change order, claiming that it was entitled to a credit in the sum of $611,090. Rather than executing the change order, Kafka chose to commence the instant action on August 31, 2012.
The SCA subsequently moved pursuant to
The Supreme Court properly granted the SCA’s motion to dismiss the complaint for Kafka’s failure to timely serve a notice of claim upon it. Pursuant to
Here, the certificate of substantial completion was executed by Kafka on September 23, 2009, and the change order proposal was issued by Kafka on February 4, 2011. Accordingly, applying the relevant legal principles to the present matter, the Supreme Court correctly determined that Kafka’s claim accrued, at the latest, on February 4, 2011, when Kafka issued the change order proposal reciting how much it believed should be deducted from the total contract price as a credit to the SCA. At that point, the full amount of Kafka’s claim for the contract value of the work it had performed was ascertainable. Contrary to Kafka’s contention, its claim did not accrue as of the date that the SCA indicated its refusal to pay part of Kafka’s claim by disputing the amount of the credit. Although
In view of the foregoing, we do not reach the parties’ remaining contentions. Mastro, J.P., Leventhal, Miller and Maltese, JJ., concur.
