32 Mass. App. Ct. 480 | Mass. App. Ct. | 1992
After the plaintiffs definitive subdivision plan was denied approval by the city of Taunton planning board (the board), a judge of the Land Court, reviewing the board’s decision under the provisions of G. L. c. 41, § 8IBB, concluded that the board had exceeded its authority. A judgment was entered annulling the board’s decision and remanding the case to the board for further action “not inconsistent with” the judge’s decision. Because the judge’s decision left no basis for the board to withhold its approval of
1. Facts. We draw the material facts from the judge’s findings and from exhibits not in dispute. The plaintiff is a residential real estate development company which holds an option to purchase 138.76 acres of undeveloped farm land in a residentially zoned district of Taunton. The proposed subdivision would yield 154 single family house lots, each containing at least 25,000 square feet of land.
The board approved, with modifications, two preliminary subdivision plans submitted by the plaintiff, see G. L. c. 41, § 81S, one on December 17, 1987, and the other on May 19, 1988. As stated in art. II, § 205, of the board’s rules and regulations, the purpose of the submission of preliminary plans is to “provide for the detailed review of the layout and features of the proposed subdivision by the board, and other city agencies and boards.” This is consistent with G. L. c. 41, § 81M, as amended by St. 1969, c. 884, § 2, which provides, in part, that the “powers of a planning board . . . shall be exercised with due regard for . . . securing adequate provision for water, sewerage, drainage, underground utility services, fire, police, and other similar municipal equipment . . . necessary in a subdivision.”
Fifteen copies of the plaintiff’s preliminary plans were filed with the board in order to permit distribution to, and review and comments by, various city departments, including the board of health, the sewer department, the city engineer, the
A second letter to the board was from the Taunton board of health, dated April 14, 1988. After referring to the same problem of the absence of Dighton’s permission to tie into the South Walker Street sewage line, the board of health concluded that it “cannot approve this subdivision until such time as the question of waste water disposal for this project has been decided and finalized.” The plaintiff received a copy of both letters.
The plaintiff submitted its proposed definitive subdivision plan for approval on September 21, 1988. See G. L. c. 41, § 81U. The judge found that there was no significant change from the second preliminary plan. On November 8, 1988, the board was informed that the board of health “approves the subdivision conditioned upon adequate . . . sewage services [being] available to the site,” and on November 14, 1988, the acting city engineer wrote the board that — aside from the outstanding issue of approvals from Dighton — there was adequate capacity in the system to process the additional discharge flow from the plaintiff’s subdivision.
2. Discussion. The board’s principal argument is that the judge was wrong because the plaintiff’s definitive plans were not in compliance with the board’s regulations. We agree. General Laws c. 41, § 81Q, as inserted by St. 1953, c. 674, § 7, provides that the board’s rules and regulations “shall set forth the requirements of the board with respect to . . . the installation of municipal services [in the subdivision] ... to carry out the purposes of the subdivision control law as set forth in section eighty-one M.” Section 81M, as amended by St. 1969, c. 884, § 2, provides that the subdivision control law, G. L. c. 41, §§ 8IK to 81GG, was enacted to protect the safety, convenience, and welfare of the inhabitants of the
Article II, § 201, of the Taunton board’s rules and regulations provides that “[n]o subdivision plan shall be approved unless it. . . meets the requirements of public safety, including . . . sewerage disposal and drainage facilities.” Section 211(2)(C) of art. II provides that, if the applicant proposes to interconnect with the Taunton municipal sewerage system, the definitive plan must be accompanied by (i) a statement by the supervisor of the sewer department “of the conditions on which the city will sewer the subdivision,” and (ii) a statement of the supervisor approving the engineering features of the proposed sanitary sewers.
The plaintiff’s definitive subdivision plans did not include any statement from the sewer department specifying the conditions on which the city would provide sewerage for the subdivision.
The plaintiff argues that the judge noted the failure of the plaintiff to provide the statements required by the regulation but that the judge was nevertheless correct in concluding that the adequacy of the plaintiff’s proposed sewer tie-in is “best reserved for the board of health and building inspector at the time building permits are applied for, [and therefore] the board acted both unreasonably and prematurely . . . ,”
The board’s decision was correct for a second reason. As described above, the city’s board of health did not give its unconditional approval to the plaintiff’s definitive subdivision plans. To the contrary, the board of health, by letters to the planning board dated November 8, 1988, and February 9, 1989, conditioned its approval upon the availability of the sewer tie-in and, in the February 9 letter, to “all of the issues relative to cellars and watertables and storm water runoff and roadway drainage . . . being specifically addressed by the Taunton Conservation Commission.” See note 3, supra. Subdivision plans must comply with reasonable recommendations of the board of health. United Reis Homes, Inc. v. Planning Bd. of Natick, 359 Mass. 621, 623 (1971). Independence Park, Inc. v. Board of Health of Barnstable, 25 Mass. App. Ct. 133, 135 (1987). In the absence of the approval of the subdivision plans by the board of health, the planning board had no choice but to disapprove the plans because it could not resort to the alternative of modifying the plans to bring them into conformity with the recommendations of the board of health.
So ordered.
The city of Taunton and the town of Dighton were parties to an agree-, ment dated January 3, 1979, under which Dighton was to construct a sanitary sewage system within the town and to dispose of its sewage through the sewage collection and treatment works of Taunton. The resulting system included a line that ran along South Walker Street, but the agreement was silent as to whether a land owner, such as the plaintiff, could tie into that line without the approval of the town of Dighton. As indicated in the text, infra, that issue is the subject of a pending action brought by the plaintiff in the Massachusetts courts.
The board cited additional reasons, but the only reason which remains a live issue in this case is that relating to the sewage tie-in.
Despite this letter, the judge found that the board of health had “issued its approval of Hovnanian’s Revised Definitive Subdivision Plan on February 9, 1989.” The record appendix does not include any action or decision by the board of health on February 9, 1989, other than the letter of that date described in the text of this opinion. It is clear that the approval by the board of health was expressly conditioned upon a variety of material matters.
It is undisputed that the engineering features of the subdivision plans relating to the sewerage system were satisfactory.
The plaintiff provided a letter from the sewer department dated October 17, 1988, in which the superintendent acknowledged the city’s obligation to maintain the South Walker Street line. This letter did not satisfy the plaintiff’s obligations under the regulations with regard to the necessary sewer tie-in. By letter dated January 20, 1989, the plaintiff’s counsel notified the board that suit had been brought to determine whether the South Walker Street line is “public” and to determine whether Dighton must grant the plaintiff permission to tie into the South Walker Street line. This, too, did not satisfy the requirement of the regulations.
The judge relied on Fairbairn v. Planning Bd. of Barnstable, 5 Mass. App. Ct. 171, 185 (1977), but that case, insofar as it might tend to support the judge’s decision, involved the action of the town’s board of health implicating the State Sanitary Code, not the subdivision control law. See id. at 183-185.
There is also statutory authority for the planning board to issue its approval upon the condition that no building be erected without the consent of the board of health, but that authority is limited to those instances where the report of the board of health “require[s]” that arrangement. See G. L. c. 41, § 81U.