K-CON, INC., Appellant v. SECRETARY OF THE ARMY, Appellee
2017-2254
United States Court of Appeals for the Federal Circuit
November 5, 2018
Appeal from the Armed Services Board of Contract Appeals in Nos. 60686, 60687, Administrative Judge Kenneth David Woodrow, Administrative Judge Mark N. Stempler, Administrative Judge Richard Shackleford.
ROBERT J. SYMON, Bradley Arant Boult Cummings LLP, Washington, DC, argued for appellant. Also represented by ARON C. BEEZLEY.
JESSICA R. TOPLIN, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, DC, argued for appellee. Also represented by JOSEPH H. HUNT, ROBERT E. KIRSCHMAN, JR., STEVEN J. GILLINGHAM.
Before REYNA, BRYSON, and STOLL, Circuit Judges.
K-Con, Inc. and the Army entered into two contracts for pre-engineered metal buildings. The Armed Services Board of Contract Appeals (“Board“) held that bonding requirements were included in the contracts by operation of law at the time they were awarded, pursuant to the Christian doctrine.1 See G. L. Christian & Assocs. v. United States (Christian I). K-Con appeals. We conclude that the two contracts are construction contracts and that, under the Christian doctrine, the standard bond requirements in construction contracts were incorporated into K-Con‘s contracts by operation of law. Accordingly, we affirm.
I
K-Con claims that, after the Army awarded two contracts for pre-engineered metal buildings, the Army delayed issuance of a notice to proceed for two years, resulting in $116,336.56 in increases in costs and labor. According to K-Con, this delay was due solely to the government‘s decision to add to each contract the performance and payment bonds set forth in
In September 2013, the government awarded to K-Con task orders for the design and construction of a laundry facility and the construction of a communications equipment shelter at Camp Edwards, Massachusetts. The contracting officer issued both solicitations using the General Services Administration eBuy system using Standard Form 1449, Solicitation/Contract/Order for Commercial Items. Neither solicitation included an express requirement
In October 2013, the Army instructed K-Con to provide performance and payment bonds in accordance with
K-Con appeals, seeking reversal of the Board‘s determination. K-Con argues that the contracts were not construction contracts and, alternatively, that the bond requirements were not incorporated into the contracts by way of the Christian doctrine. Based on these arguments, K-Con requests a remand to the Board to determine the amount to be awarded for K-Con‘s claims. We have jurisdiction under
II
A
K-Con first argues that the Board erred in holding that the contracts at issue are construction contracts. K-Con asserts that they are contracts for commercial items, which do not carry mandatory bonding requirements. The government responds that both contracts are patently ambiguous as to whether they are construction contracts and, thus, it was incumbent on K-Con to inquire as to whether the contracts were for construction or commercial items. Because it did not do so, the government contends that K-Con is precluded from now arguing that the contracts are for commercial items. We agree.
“A patent ambiguity is present when the contract contains facially inconsistent provisions that would place a reasonable contractor on notice and prompt the contractor to rectify the inconsistency by inquiring of the appropriate parties.” Stratos Mobile Networks USA, LLC v. United States, 213 F.3d 1375, 1381 (Fed. Cir. 2000). This is distinct from a latent ambiguity, which exists when the ambiguity is “neither glaring nor substantial nor patently obvious.” Cmty. Heating & Plumbing Co. v. Kelso, 987 F.2d 1575, 1579 (Fed. Cir. 1993) (citing Mountain Home Contractors v. United States, 425 F.2d 1260, 1264 (Ct. Cl. 1970)). We review de novo both the existence of an ambiguity and whether any ambiguity is patent or latent because they are both issues of law. Stratos, 213 F.3d at 1380 (citing Grumman Data Sys. Corp. v. Dalton, 88 F.3d 990, 997 (Fed. Cir. 1996)).
We conclude that the contracts were patently ambiguous. On the one hand, as the Army admits, if the contracts had been issued using the standard construction contract form, they would have been construction contracts without any ambiguity. But that is not what happened here. Instead, these contracts issued using the standard commercial items contract form. The line item descriptions even included the phrase “FOB: Destination,” which is typically used for commercial items contracts. J.A. 31, 53.
On the other hand, there were many indications that the contracts were for construction, not commercial items. For example, the contract line item descriptions for both contracts, which “identify the supplies or services to be acquired,” were for construction activities. See generally
Because the solicitations contained contract language that was patently ambiguous, K-Con cannot argue that its interpretation was proper unless K-Con contemporaneously sought clarification of the language from the Army. See Grumman, 88 F.3d at 998 (addressing the issue in the context of a bid protest). K-Con did not seek such clarification and therefore cannot now argue that the contracts should be for commercial items.
B
We now turn to K-Con‘s second argument. According to K-Con, even if the contracts were properly considered construction contracts, the Board erred in holding that the contracts included bond requirements under the Christian doctrine.
Here, the relevant regulation is
As prescribed in 28.102-3(a), insert a clause substantially as follows:
Performance and Payment Bonds — Construction (OCT 2010) . . .
(b) Amount of required bonds. Unless the resulting contract price is $150,000 or less, the successful offeror shall furnish performance and payment bonds to the Contracting Officer as follows:
(1) Performance bonds (Standard Form 25). The penal amount of performance bonds at the time of contract award shall be 100 percent of the original contract price.
(2) Payment Bonds (Standard Form 25-A). The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.
Neither contract expressly incorporated this required clause. However, under the Christian doctrine, a court may insert a clause into a government contract by operation of law if that clause is required under applicable federal administrative regulations. See Gen. Eng‘g & Mach. Works v. O‘Keefe, 991 F.2d 775, 779 (Fed. Cir. 1993) (citing Christian I, 312 F.2d at 424, 427). In Christian, the Court of Claims concluded that the standard termination clause required by the Armed Service Procurement Regulations must be read into the contract, even though the contract lacked a termination clause. Christian I, 312 F.2d at 424–26. Accordingly, the court denied the contractor‘s breach-of-contract claim when the government terminated the construction contract for its own convenience. Id. at 427. For a court to incorporate a clause into a contract under the Christian doctrine, it generally must find (1) that the clause is mandatory; and (2) that it expresses a significant or deeply ingrained strand of public procurement policy. See Gen. Eng‘g & Mach. Works, 991 F.2d at 779.
We review the Board‘s determinations on the applicability of the Christian doctrine de novo. Id. at 779-80 (applying de novo review to determine whether the Christian doctrine incorporated a contract clause regarding material handling costs by operation of law). In applying a de novo review, however, we give “careful consideration and great respect” to the Board‘s legal interpretations in light of its considerable experience in the field of government contracts, including its experience in interpreting the FAR. Fruin-Colnon Corp. v. United States, 912 F.2d 1426, 1429 (Fed. Cir. 1990); see Titan Corp. v. West, 129 F.3d 1479, 1481 (Fed. Cir. 1997). We turn now to the two prongs of the Christian doctrine analysis.
1
Under the first prong of the Christian doctrine, we examine whether the bonding requirements are “mandatory” in government construction contracts. See Gen. Eng‘g & Mach. Works, 991 F.2d at 779–80. We conclude that they are because they are required by statute.
The statute,
K-Con argues that
2
Under the second prong of the Christian doctrine, we examine whether the payment and performance bond requirements “express a significant or deeply ingrained strand of public procurement policy.” See Gen. Eng‘g & Mach. Works, 991 F.2d at 779–80 (discussing Christian I, 312 F.2d at 426; G. L. Christian & Assocs. v. United States (Christian II), 320 F.2d 345, 350–51 (Ct. Cl. 1963)). We conclude that they do.
Payment bonds are intended to provide security for those who furnish labor and materials in the performance of government contracts. F.D. Rich Co. v. United States ex rel. Indus. Lumber Co., 417 U.S. 116, 121 (1974). For private contracts, subcontractors and suppliers can obtain a mechanic‘s lien against the improved property to ensure that they are paid. Id. at 122. Government property, however, cannot be subject to subcontractors’ and suppliers’ liens. Thus, the payment bonds requirement was created to provide, in government contracts, an alternative remedy to protect those who supply labor or materials to a contractor on a federal project. See id. Performance bonds protect the government by ensuring that a
The Miller Act was enacted in 1935 and re-codified in 2002. See Miller Act, 49 Stat. 793 (1935); Revision of Title 40, United States Code, “Public Buildings, Property, and Works,” Pub. L. No. 107-217, § 3131, 116 Stat 1062 (2002). Since its enactment, the statute has consistently required performance and payment bonds, even though the contract threshold value for the requirement has increased. Compare 49 Stat. 793 (1935) ($2000), with 116 Stat. 1062 § 3131 (2002) ($100,000), with
Moreover, Grade-Way is distinguishable on its facts. The issue in Grade-Way was whether the lowest bidder‘s bid was nonresponsive for failing to include a statutorily-required minimum wage provision. The Davis-Bacon Act required the bid to “contain a provision stating the minimum wages to be paid various classes of laborers and mechanics.”
K-Con similarly relies on Grade-Way to assert that the Christian doctrine is inapplicable because applying it would require K-Con to provide a service that it did not offer. In Grade-Way, the Claims Court noted that “application of a doctrine of contract construction developed by the courts, such as the Christian Doctrine with respect to incorporation by operation of law, cannot be applied in direct conflict
Finally, K-Con characterizes other Christian doctrine cases as applying only to “contract administration-type provision[s].” Appellant Br. at 27. In Grade-Way, the court noted:
The Christian doctrine has been applied essentially to clauses involving the government‘s administration of a contract (such as terminations, changes, and the like), but not to specific terms and specifications. Moreover, the clauses customarily encompassed by that doctrine have contained provision for compensation to the contractor for any increased costs (if not, in all cases, including profits or consequential damages). We know of no authority which would apply the Christian doctrine to a situation of this type or which would permit the reading into a solicitation of higher wage determinations (with no [concomitant] increase in the bid price).
Grade-Way, 7 Cl. Ct. at 271; see Gen. Eng‘g & Mach. Works, 991 F.2d at 780 (incorporating payments clause that required separate cost pools); Chris Berg, Inc. v. United States, 426 F.2d 314, 317–18 (Ct. Cl. 1970) (holding that missing “mistake in bids” clause required under the Armed Services Procurement Regulation be incorporated into the contract because the clause was written for the protection of contract bidders); Appellant Br. at 27 (citing Christian II, 320 F.2d at 349 (incorporating termination for convenience provision)). Even if we were to accept K-Con‘s premise that the provisions in other Christian doctrine cases are “administration-type provision[s],” we are aware of no case that limits the Christian doctrine to such “administration-type” provisions. Indeed, we have applied the Christian doctrine to substantive provisions like the one in this case. For example, in S.J. Amoroso, we applied the Christian doctrine to require, under the Buy American Act, that the contract at issue “contain a provision that in the performance of the work” only American materials will be used. 12 F.3d at 1075–76. Ultimately, we do not find K-Con‘s arguments persuasive, and we agree with the Board‘s conclusion that the
III
We conclude that K-Con is barred from arguing that the contracts at issue are not
AFFIRMED
COSTS
No costs.
