JWK International Corporation appeals the orders of the United States Court of Federal Claims granting the United States’ and LTM’s motion for judgment upon the administrative record, and denying JWK’s motions for judgment upon the administrative record and preliminary injunction. See JWK Int’l Corp. v. United States, No. 01-26C (Fed. Cl. April 13, 2001). Because the Navy’s decision not to conduct discussions with respect to JWK’s cost proposal under Federal Acquisition Regulation § 15.306(d)(3), 48 C.F.R. § 15.306 (2001), was in accordance with law, we affirm.
In response to a request for proposals, JWK International Corporation (“JWK”), the incumbent contractor, submitted a proposal to the Navy for a contract to continue to supply acquisition logistics management integration services. Proposals were evaluated in the areas of technical, management, past performance, and cost. According to the RFP, the cost factor was the least important. LTM Inc. (“LTM”) was the only other bidder. The relevant ratings of JWK’s initial proposal were: marginal for technical, marginal for management, and adequate for cost, considering its 1.5 percent proposed annual average labor rate escalation. LTM received a marginal for technical, satisfactory for management, and adequate for cost, considering its 3 percent escalation rate.
The Navy entered into discussions with both JWK and LTM about the respective weaknesses of their proposals. The Navy did not discuss cost with either bidder because both of their cost proposals were rated as adequate. When the final revised proposals were submitted, JWK received a rating of marginal for technical, and satisfactory for management, compared with LTM’s satisfactory for technical, and highly satisfactory for management. The Navy applied a cost realism adjustment to both cost proposals, increasing JWK’s cost to $167,191,517 and LTM’s to $169,993,563. The Navy awarded the contract to LTM based upon its superior non-cost factor ratings. JWK filed a post-award bid protest in the United States Court of Federal Claims. The court granted the United States’ and LTM’s motion for judgment upon the administrative record, and denied JWK’s motions for judgment upon the administrative record, preliminary injunction, and injunction pending appeal. JWK appeals.
Discussion
We have jurisdiction to review the judgments of the Court of Federal Claims under 28 U.S.C. § 1295(a)(3) (1994). We review the court’s grant of summary judgment upon the administrative record without deference. We reapply the summary judgment standard in an independent review to determine whether the moving party is entitled to judgment as a matter of law.
Advanced Data Concepts, Inc. v. United States,
The question here is whether Federal Acquisition Regulation § 15.306(d)(3) requires a contracting officer to enter into cost discussions with bidders whose cost proposals are deemed adequate. Section 15.306(d)(3) states in relevant part:
The contracting officer shall ... discuss with, each offeror still being considered for award, significant weaknesses, deficiencies, and other aspects of its proposal (such as cost, price, technical approach, past performance, and terms and conditions) that could, in the opinion of the contracting officer, be altered or explained to enhance materially the proposal’s potential for award. The scope and extent of discussions are a matter of contracting officer judgment.
48 C.F.R. § 15.306(d)(3) (2001).
JWK argues that cost discussions must always be conducted under section 15.306(d)(3) even if the cost proposal is not a significant weakness or deficiency because cost is always material. JWK as
Under section 15.306(d)(3), whether discussions should be conducted lies within the discretion of the contracting officer. 48 C.F.R. § 15.306(d)(3). All aspects of the discussions, their subject, breadth, and extent, are within the purview of the contracting officer.
Id.
Under the regulation, aside from areas of significant weakness or deficiency, the contracting officer need not discuss areas in which a proposal may merely be improved. Therefore, absent bad faith or an abuse of discretion, the contracting officer need not conduct discussions.
See T & M Distrib., Inc. v. United States,
In this case, the contracting officer did not engage in cost discussions with JWK because the Navy had determined that the cost proposal was acceptable. The contracting officer determined that cost was not an area of weakness with “a flaw that -increases the risk of unsuccessful contract performance,” or a deficiency with “a material failure ... to meet a Government requirement ... that increases the risk of unsuccessful contract performance to an unacceptable level.” 48 C.F.R. § 15.301 (2001). The Navy had estimated that the contract would cost $164,206,050, and JWK’s adjusted bid was $167,191,517. The contracting officer’s judgment that a 1.79 percent difference in cost was not a weakness or deficiency, and his decision not to enter into cost discussions with JWK were neither in bad faith nor an abuse of discretion.
To prevail in its bid protest, JWK must additionally show that any significant error in the procurement process prejudiced the award.
Statistica, Inc. v. Christopher,
Conclusion
Accordingly, the judgment of the United States Court of Federal Claims is affirmed.
AFFIRMED.
