226 Ct. Cl. 527 | Ct. Cl. | 1980
Contracts; Wunderlich Act reveiw; cardinal change; equitable adjustment; breach of contract claim. — Plaintiff, on behalf of its subcontractor Fidelity, seeks reveiw under Wunderlich Act standards of a decision of the Armed Services Board of Contract Appeals and/or a trial de novo. Plaintiff contracted to construct a United States Army hospital at Fort Gordon, Georgia, subcontracting with Fidelity to install an audio-visual nurse call system. As issued, the nurse call specifications contemplated use of a standard product that had been developed by marrying specifications of Executone and Motorola'systems in a way