Thе bankruptcy court disallowed the contingent claim Jumper Development Group (“Juniper”) filed against the consolidated chapter 7 estate of Hemingway Transport, Inc. (“Hemingway”) and Bristol Terminals, Inc. (“Bristol”) for anticipated response costs for the removal and remediation of hazardous substances discovered on property previously purchased by Juniper from the Hemingway-Bristol chapter 11 estate. Juniper’s companion claim for cleanup-related attorney fees was disallowed as well. The district court affirmed and Juniper appeals. The chapter 7 trustee (“trustee”) cross-appeals the allowance of Juniper’s priority claim for past cleanup costs as an administrative expense.
I
BACKGROUND
Between 1963 and 1982, Hemingway and Bristol continuously owned or operated a trucking business conducted from a twenty-acre parcel of land located in Woburn, Massachusetts (“facility”). 1 In May 1980, the Massachusetts Department of Environmental Quality Engineering (DEQE) discovered seventeen corroded drums leaching a semi-solid, tar-like substance onto a 13.8 acre “wetlands” area at the facility. DEQE informed Hemingway that the substance contained petroleum constituents. DEQE received assurances from Hemingway that the drums would be removed. The drums were still at the facility when DEQE conducted its last site inspection, in August 1982.
In July 1982, Hemingway and Bristol filed chapter 11 pеtitions. With the approval of the bankruptcy court, appellant Juniper, a local land developer, purchased the facility from debtor-in-possession Bristol for $1.6 million on April 29, 1983. Prior to the purchase, Juniper’s representatives conducted an on-site inspection but did not walk the *920 wetlands area where DEQE had discovered the drums; Juniper contends that the area was submerged at the time. Seven months after the sale, the Hemingway-Bristol chapter 11 reorganization proceeding was converted to a chapter 7 liquidation proceeding, and a chapter 7 trustee was appointed.
In April 1985, drums containing various solvents and pesticides classified as “hazardous substances” under the Comprehensive Environmental Response, Compensation, and Liability Act (“CERCLA”), 42 U.S.C. §§ 9601-9657, 9601(14) (1981), were discovered at the facility, in the same wetlands area, by the United States Environmental Protection Agency (“EPA”). The following December, Juniper, then the “owner” of the facility, received notice that the EPA considered Juniper a “potentially responsible party” (“PRP”) under CERCLA, see id. § 9607(a). Shortly thereafter the EPA issued an administrative order requiring Juniper to remove the hazardous substances from the facility at its own expense. See id. § 9606. Juniper claims $92,088 in response costs incurred pursuant to the EPA administrative order. 2
Juniper initiated an adversary proceeding against the Hemingway-Bristol estate for CERCLA response costs already incurred under the EPA аdministrative order and for future response costs required to complete the anticipated cleanup and remediation. Initially, the bankruptcy court denied the trustee’s motion for summary judgment on Juniper’s CERCLA claim. The court determined that Juniper’s CERCLA claim, if ultimately allowed, would be entitled to priority payment from the chapter 7 estate as an administrative expense of the chapter 11 estate, since Juniper’s exposure to CERCLA liability had arisen from its postpetition agreement to purchase the facility from the chapter 11 estate.
In re Hemingway Transp., Inc.,
The trustee renewed the motion for summary judgment on Juniper’s claim for
future
response costs, and moved for reconsideration of the “administrative expense priority” ruling previously entered by the bankruptcy court. The bankruptcy court then disallowed Juniper’s claim for
future
response costs, pursuant to Bankruptcy Code § 502(e)(1)(B), 11 U.S.C. § 502(e)(1)(B), on the ground that Juniper was the holder of a contingent CERCLA contribution claim based on a debt owed EPA for which Juniper, Hemingway, and Bristol were jointly and severally liable, in connection with which Juniper had yet to incur any liability by the time of the allowance of its claim.
In re Hemingway Transp., Inc.,
Following trial on Juniper’s $92,088 claim for CERCLA response costs previously incurred, the bankruptcy court ruled that Hemingway and Bristol were rеsponsible
*921
parties “liable” to the EPA, as they either owned or operated the facility at the time a passive “disposal” of hazardous substances occurred at the facility.
In re Hemingway Transp., Inc.,
The bankruptcy court allowed Juniper’s claim for past response costs in the amount of $38,763 as an administrative expense entitled to priority payment,
id.
at 382, but disallowed the $54,000 claim on the ground that attorney fees are not recoverable in a private action under 42 U.S.C. § 9607(a)(4)(B).
Id.
at 383. Juniper appealed the rulings disallowing its claim for future response costs and for attorney fees. The trustee cross-appealed the order allowing Juniper’s $38,763 priority claim for administrative expense. The district court affirmed.
In re Hemingway Transp., Inc.,
II
DISCUSSION
A. Juniper’s Appeal: Disallowance of Future Response Costs (11 U.S.C. § 502(e)(1)(B).
1. The Intersection of CERCLA and the Bankruptcy Code.
Juniper finds itself stranded at the increasingly crowded “intersection” between the discordant legislative approaches embodied in CERCLA and the Bankruptcy Code.
See In re Chateaugay Corp.,
*922
At the same time, however, CERCLA section 9613(f) is aimed at promoting equitable allocations of financial responsibility by authorizing PRPs subjected to pending or completed EPA enforcement actions under 42 U.S.C. §§ 9606 and 9607(a)(4)(A) to initiate private actions for full or partial
contribution
from nonsettling PRPs by way of impleader or an independent action.
See
42 U.S.C. § 9613(f).
5
Thus, targeted PRPs, relying on the ultimate financial accountability of more “culpable” PRPs, are encouraged to initiate prompt response efforts, at their own expense, in cooperation with the EPA.
See
H.R.Rep. No. 253, 99th Cong., 1st Sess. 80,
reprinted in
1986 U.S.C.C.A.N. 2835 (“Private parties may be more willing to assume the financial responsibility for some or all of the cleanup if they are assured that they can seek contribution from others.”);
In re Dant & Russell, Inc.,
On the other hand, Bankruptcy Code § 502(e)(1)(B) often serves to forestall CERCLA’s intended equitable allocation of responsibility, as occurred in this case when the bankruptcy court disallowed Juniper’s estimated claim for $6.2 million in anticipated future CERCLA response costs. Section 502(e)(1)(B) provides, in pertinent part:
[T]he court shall disallow any claim for reimbursement or contribution of an entity [viz., Juniper] that is liable with the debtor [Hemingway-Bristol] on or has secured, the claim of a creditor [EPA], to the extent that—
(B) such claim for reimbursement or contribution is contingent as of the time of allowance or disallowance of such claim for reimbursement or contribution ....
11 U.S.C. § 502(e)(1)(B). There can be little doubt that, but for section 502(e)(1)(B), the Hemingway-Bristol estate would share some measure of financial responsibility for the anticipated $6.2 million in future response costs on which the Juniper claim is based.
Nevertheless, section 502(e)(1)(B) would mandate disallowance of the Juniper claim against the Hemingway-Bristol chapter 7 estate if Juniper is jointly liable with the Hemingway-Bristol estate on the
same
“debt” for estimated future CERCLA respоnse costs to EPA, and Juniper’s right to payment on its claim — denominated a claim for reimbursement or contribution — remained “contingent” at the time of its disallowance.
See In re Provincetown-Boston Airlines,
2. Applicability of Section 502(e)(1)(B) to CERCLA Claims.
Section 502(e)(1)(B) was enacted for one purpose — “to prevent[ ]
competition between a creditor and his guarantor
for the limited proceeds of the estate.” H.R.Rep. No. 595, 95th Cong., 1st Sess. 354 (1977); S.Rep. No. 989, 95th Cong., 2d Sess. 65 (1978), U.S.Code Cong. & Admin.News 1978, pp. 5787, 5851, 6310 (emphasis added). Normally, section 502(e)(1)(B) is invoked against claims based on debts or obligations arising from voluntary contractual relationships. Even in the context of a CERCLA-based, quasi-“tort” obligation, however, the practical need for section 502(e)(1)(B) is evident; that is, but for section 502(e)(1)(B),
see infra
note 6, an estimation of Juniper’s claim for anticipated response costs,
see
11 U.S.C. § 502(c)(1), would entitle Juniper to share in the distribution of the insolvent chapter 7 estate under Bankruptcy Code § 726(a), 11 U.S.C. § 726(a),
see, e.g., In re Butterworth,
The Code’s expansive definition of “claim” permits automatic allowance of most “contingent” claims, see Bankruptcy Code §§ 101(4), 502(a), 11 U.S.C. §§ 101(4), 502(a), against a chapter 7 estate upon timely filing, see id. §§ 501, 726; Fed.R.Bankr.P. 3002(c). The bankruptcy court simply estimates the amount of the claim for purposes of its allowance, see id. § 502(c)(1), discounting its value to reflect the uncertainty of the contingency, in order to enable the holder to share in the distribution of the insolvent estate. 6 On the other hand, where the filing of a contingent claim for contribution or reimbursement entails risk that the assets of the chapter 7 estate will be exposed to “double-dipping” by holders of the same underlying claim against the estate, section 502(e)(1)(B) mandates dis-allowance of the contingent claim. The sole purpose served by section 502(e)(1)(B) is to preclude redundant recoveries on identical claims against insolvent estates in violation of the fundamental Code policy fostering equitable distribution among all creditors of the same class. The “double-dipping” threat in the present case would result from the allowance and estimation of Juniper’s contingent claim, and the allowance of an EPA claim, for the same future CERCLA response costs against the chapter 7 estate.
Section 502(e)(1)(B) is a fair and reasonable measure as applied against a contract guarantor or surety. Confronted with the prospect that its contingent claim for reimbursement or contribution against a chapter 7 debtor estate may be subject to disallowance under section 502(e)(1)(B), an entity may elect to cause its contingent contract claim to become “fixed” prior to disallowance,
see
Bankruptcy Code § 502(e)(2), by
*924
itself satisfying the debt due the creditor of the debtor estate, leaving the entity as the sole holder of a claim against the estate based on that debt.
7
See, e.g., In re Baldwin-United Corp.,
Although section 502(e)(1)(B) may have been' devised
primarily
with contract-based codebtor relationships in mind
(e.g.,
guaranties, suretyships), however, its language (“liable with”) has been found too plain and inclusive to exempt “joint and several” tort-based obligations from disallowance,
see, e.g., In re American Continental,
Finally, we discern no inherent incompatibility between section 502(e)(1)(B) and the congressional policies underlying CERCLA, such as might enable a court reasonably to conclude that Congress implicitly exempted CERCLA co-obligation claims. Although on occasion section 502(e)(1)(B) may impede CERCLA’s
subsidiary
policy of
*925
promoting equitable allocations of environmental cleanup costs among responsible parties, pre-“fixing” disallowance does not conflict with CERCLA’s
primary
goal — encouraging targeted PRPs to initiate cleanup efforts as expeditiously as practicable in the expectation that their contingent claims may become “fixed” in time for allowance against the debtor estate.
See In re Charter Co.,
Accordingly, we conclude that Congress did not exempt CERCLA claims from disal-lowance under section 502(e)(1)(B).
3. Burdens of Proof in Section 502(e)(1)(B) Litigation.
In the litigation of a section 502(e)(1)(B) objection to a contingent claim, however, the proper allocation of burdens of proof and production may be decisive. A proof of claim which comports with the requirements of Bankruptcy Rule 3001(f) constitutes
prima facie
evidence of the validity and amount of the claim.
See
Fed.R.Bankr.P. 3001(f). The interposition of an objection does not deprive the proof of claim оf presumptive validity unless the objection is supported by
substantial evidence. Norton Bankruptcy Law & Practice, Bankruptcy Rules
at 191 (1992);
see also In re Beverages Int’l, Ltd.,
4. Hemingway-Bristol “Liability” on Joint Obligation.
At the time it allowed Juniper’s claim for past response costs, the bankruptcy court determined that Hemingway-Bristol had owned or operated the facility when the passive “disposal” of hazardous substances occurred and that Hemingway-Bristol had actual knowledge of the presence of the leaking barrels. Hence, Hemingway-Bristol is a “covered person,” strictly liable to the EPA for future response costs pursuant to 42 U.S.C. § 9607(a)(4)(A).
Juniper nonetheless suggests that the term “liable with” should be interpreted in light of the singular legislative purpose underlying the section 502(e)(1)(B) contingent claim disallowance provision. Like any other claim for contribution, says Juniper, its claim for future CERCLA response costs could pose no “double-dipping” threat were the EPA, for whatever reason, not to participate in any distribution from the chapter 7 estate. Moreover, the EPA has elected not to assert a claim against the estate, despite considerable prodding by Juniper. Rather, the EPA repeatedly has manifested its intention to forego any immediate claim against the chapter 7 estate in favor of administrative enforcement actions against other PRPs, such as Juniper. 9 The trustee responds that the literal language of section 502(e)(1)(B) directs disallowance of the codebtor’s [Jumper’s] contingent claim even though the creditor [EPA] has not filed a proof of claim by the time the codebtor’s claim is considered for allowance.
Section 502(e)(1) directs disallowance of the claim of a eodebtor who is liable with the debtor on the “claim of a creditor.” The pivotal terms — “claim” and “creditor” — are defined. A “claim” is a “right to payment, whether or not such right is reduced to judgment, liquidated, unliquidated, fixed, contingent, matured, unmatured, disputed, undisputed, legal, equitable, secured, or unse *926 cured.” Bankruptcy Code § 101(4), 11 U.S.C. § 101(4) (emphasis added). A “creditor” is an “entity that has a claim against the debtor that arose at the time of or before the order for relief concerning the debtor.” Id. §§ 101(9), 301 (“The commencement of a voluntary ease under a chapter of this title constitutes an order for relief under such chapter.”).
The EPA presumably holds a prepetition claim against the chapter 7 estate, since its contingent “right tо payment” accrued while Bristol and Hemingway owned or operated the facility at which the hazardous waste “disposal” occurred.
Cf. In re Chateaugay,
The co-liability clause in section 502(e)(1), viz., “liable with the debtor,” interpreted in light of its singular purpose, might permit allowance of a non-fixed codebtor claim for CERCLA contribution if the creditor were foreclosed from participating in any distribution from the estate under Bankruptcy Code § 726(a). . Nevertheless, though we reject the trustee’s contention that the EPA might yet demonstrate “excusable neglect” warranting an extension of time to file a proof of claim, 10 we must examine other means which may remain open to EPA’s participation in any chapter 7 distribution.
The EPA may participate in a distribution to unsecured creditors under section 726(a)(2)(C) if it was never scheduled as a “creditor” of the estate, and had no actual knowledge of the proceedings in time tо file a proof of claim.
See In re Global Precious Metals, Inc.,
In this case, however, the harsh results occasioned by Bankruptcy Code § 502(e)(1)(B) are mitigable through recourse to Bankruptcy Code § 501(e), which *927 provides that, “[i]f a creditor does not timely file a proof of such creditor’s claim, the debt- or or the trustee may file a proof of such claim.” See also Fed.R.Bankr.P. 3004. Although section 501(e) is permissive (“may file”), rather than mandatory, and is designed principally to prevent creditors from depriving debtors of the benefit of a discharge under Bankruptcy Code § 727, 11 U.S.C. § 727, cf. supra note 8, in these circumstances there are sound reasons to require the chapter 7 trustee to shoulder the initial burden of filing a surrogate claim in behalf of the EPA as a precondition to obtaining simultaneous disallowance of Juniper’s contingent claim under section 501(e)(1)(B).
First, even if the chapter 7 trustee were to decline to act as an EPA surrogate, Juniper could force the trustee’s hand. Under a parallel Code provision, Juniper itself would be permitted to file a surrogate claim for the EPA. See Bankruptcy Code § 501(b), 11 U.S.C. § 501(b) (“If a creditor [EPA] does not timely file a proof of such creditor’s claim, an entity [Juniper] that is hable to such creditor with the debtor ... may file a proof of such claim.”). 13 Were it to resort to the surrogate-claim procedure, Juniper would be required to show simply that “the original debt [due EPA by Hemingway-Bristol would] be diminished by the amount of the distribution [to the EPA on the surrogate claim].” . Fed.R.Bankr.P. 3005(a). Of course, even this modest burden would be obviated if the surrogate claim were to be superseded by the EPA’s filing of its own proof of claim. See id. 14
More importantly, mandatory resort to the trustee’s option to file a surrogate proof of claim under section 501(c) more readily comports with the allocation of the burden of proof under section 502(e)(1)(B), which would require the trustee to come forward with
substantial
support for the section 502(e)(1)(B) objection to Juniper’s proof of claim, and hence, substantial evidence that Hemingway and Bristol were “liable” to the EPA.
See supra
Section II.A.3. In addition, the trustee has title and ready access to the debtors’ records,
see
Bankruptcy Code § 521(4), 11 U.S.C. § 521(4) (“[D]ebtor shall ... surrender to trustee all property of the estate, including books, documents, records, and papers_”);
In re Bentley,
Although disallowance of Juniper’s CERC-LA claim under section 502(e)(1)(B) is not strictly foreclosed by EPA’s failure to file timely proof of its claim, we cannot overlook the fact that the trustee’s reliance on section 502(e)(1)(B) may occasion a pointless financial loss to Juniper and result in a windfall to the chapter 7 estate, notwithstanding Juniper’s best efforts to induce EPA to file its claim. In this vein, we note that resort to subsections 501(b) and (c) would not compel EPA’s participation in the bankruptcy proceedings,
cf. In re Hemingway Transp.,
Accordingly, we vacate the bankruptcy court order disallowing Jumper’s claim under section 502(e)(1)(B). On remand, the bankruptcy court should prescribe a reasonable bar date by which the chapter 7 trustee must elect whether to file a surrogate EPA claim pursuant to Bankruptcy Code § 501(c), without prejudice to Juniper’s right to submit a surrogate claim under subsection 502(b) as well. 15 Should the trustee not file a timely surrogate claim (and should Juniper not do so), the section 502(e)(1)(B) objection should be dismissed, and the court should estimate Juniper’s direct claim against the chapter 7 estate pursuant to normal claim-allowance procedures. See Bankruptcy Code § 502(c).
5. Juniper’s “Liability” on Joint Obligation.
In the event the trustee should file a surrogate claim in behalf of the EPA pursuant to sections 501(c) and 726(a)(2)(C) following remand, we outline the standards governing its consideration by the bankruptcy court.
Juniper’s “contribution” claim differs in one important respect from codebt- or claims normally subjected to disallowance under section 502(e)(1)(B). In the typical contractual relationship between a principal and its surety or guarantor, the codebtor’s (surety’s or guarantor’s) obligation on the common debt arises at the same time as the creditor’s (principal’s) “right to payment” from the debtor — during the prepetition period — which necessarily means that both the creditor and the codebtor hold prepetition claims against the debtor estate. Here, on the other hand, regardless whether the EPA has a prepetition or a postpetition claim, Juniper’s “right to payment” from Hemingway-Bristol arose, at the earliest, when it purchased the facility from the Hemingway-Bristol chapter 11 estate in April 1983. Only then did Juniper become an “owner and operаtor” of the contaminated facility, hence a “covered person” under CERCLA. 16 Since *929 Juniper undeniably holds a postpetition “claim,” Bankruptcy Code §§ 101(9), 301, 11 U.S.C. §§ 101(9), 301, its “proof of claim” under Bankruptcy Code §§ 501 and 502 is no less readily — and presumably even more accurately — characterized as “a request for payment of an administrative expense” under Bankruptcy Code § 503(a). See Bankruptcy Code § 348(d), 11 U.S.C. § 348(d) (providing that claims arising after the filing of a chapter 11 petition and before conversion to chapter 7 shall be treated as prepetition claims, unless they qualify as “administrative expenses” under section 503(b)). 17
Bankruptcy Code § 503(b)(1)(A) enables an entity to file a request for payment of an administrative expense, including “the actual, necessary costs and expenses of preserving the estate.” “As a general rule, a request for priority payment of an administrative expense pursuant to Bankruptcy Code § 503(a) may qualify if (1) the right to payment arose from a postpetition transaction with the debt- or estate, rather than from a prepetition transaction with the debtor, and (2) the consideration supporting the right to payment was beneficial to the estate of the debtor.”
In re Hemingway Transp., Inc.,
In the context of their arm’s-length purchase-sale transaction in 1983, we must presume that Juniper and the chapter 11 estate were cognizant of the federal and state environmental laws then in effect, and that, notwithstanding Juniper’s resulting status as an “owner or operator” of the contaminated facility, the chapter 11 estate could remain liable for any response costs later incurred by Juniper and for which the debtors (or the debtor estate) were liable under CERCLA section 9607(a), an obligation explicitly provided for presently in 42 U.S.C. §§ 9607(a)(4)(B) and 9613(f).
See O’Neil,
On the other hand, we agree that Mammoth Mart priority is unavailing to Juniper insofar as its right to contribution for future response costs remains “contingent” at the time the bankruptcy court considers Juniper’s claim for allowance against the debtor estate. Only “actual” administrative expenses, not contingent expenses, are entitled to priority payment under Bankruptcy Code § 503(b)(1)(A). Even though Juniper’s postpetition contribution claim, once allowed, would be entitled to priority treatment under section 503(b), the parallel restrictions in section 502(e)(1)(B) pose an additional hurdle. Under its clear terms, section 502(e)(1)(B) does not apply exclusively to “creditors,” or in other words, to holders of prepetition claims for reimbursement or contribution. Section 502(e)(1)(B) refers to the holder of the claim as an “entity,” not as a “creditor” of the estate. 18 Accordingly, Juniper’s priority “claim for reimbursement or contribution” would be allowable if either: (1) Juniper and the chapter 11 estate are not strictly, jointly, and severally liable (“liable with the debtor”) on the EPA debt under the liability provisions of the CERCLA statute, or (2) Juniper’s response costs have become “fixed” and “actual” (i.e., have been expended by Juniper for remediation or paid over to the EPA) by the time Juniper’s claim is considered for disallowance. As Juniper’s contingent claim for future response costs is, by definition, not “fixed,” Juniper cannot escape the consequences of sectiоn 502(e)(1)(B) unless it is not strictly and jointly “liable” with Hemingway-Bristol on the EPA debt. Cf. infra *931 Section II.C. (Mammoth Mart administrative expense priority would attach to Juniper’s “fixed” claim for past response costs). We turn, therefore, to the question of Juniper’s alleged liability to the EPA.
The threshold question is whether Juniper is even asserting a
direct
CERCLA claim against the chapter 7 estate, or merely a
derivative
claim for “contribution” from the chapter 7 estate. CERCLA section 9613(f) is the sole statutory basis for a right to “contribution,”
see supra
note 5 and accompanying text, but CERCLA prescribes other remedial provisions as well. Unlike section 9613(f), a private right of action for CERC-LA response costs- under section 9607(a)(4)(B) is available to
“any person”
who incurs necessary response costs, presumably without regard to whether the plaintiff is an EPA target,
ie.,
a PRP or “covered person” under section 9607(a).
See
42 U.S.C. § 9601(21) (“person” includes “corporation”). Section 9607(a)(4)(B) simply requires the private-action plaintiff to prove that (1) a release of a “hazardous substance” from the subject “facility” occurred or is threatened; (2) the defendant comes within any of four categories of “covered persons,” which include current owners or operators of the facility,
see
42 U.S.C. § 9601(9)(B), as well as the owners and operators of the facility at the time the contamination occurred; (3) the release or threatened release has caused (or may cause) the claimant to incur response costs;
19
and (4) the response costs are “necessary” and “consistent with the national contingency plan.”
See Dedham Water Co. v. Cumberland Farms Dairy, Inc.,
For instance, a
neighboring
lаndowner, who is neither a current nor a past owner or operator of the contaminated facility, hence not strictly liable as a “covered person” under section 9607(a), may incur response costs as a result of a threatened release and potential migration of hazardous substances from an adjoining property, and may assert a right of action under section 9607(a)(4)(B).
See, e.g., Dedham Water,
Because Juniper’s initial complaint in the instant adversary proceeding invoked generic claims for “contribution” and “indemnification,” without attribution to any statutory source, the bankruptcy court specifically requested Juniper “to amend Count I [of its complaint] to include the statutory prerequisite [sic] of 42 U.S.C. § 9607(a)(4)(B).” Although the amended complaint represents at best an imperceptible improvement over its predecessor, the bankruptcy court apparently considered it adequate to assert such a *932 claim. 21 Juniper’s amended complaint bears this out. It alleges that (1) Juniper is a current owner of the facility, but not that it is a “covered person” under section 9607(a); (2) Hemingway and Bristol fraudulently concealed the presence of hazardous wastes at the facility prior to the 1983 sale; and (3) Juniper neither knew nor had “reason to know” of the contamination until 1985.
The bankruptcy court concluded that Juniper, as the current “owner” of the facility, undoubtedly would be “liable” to the EPA in an enforcement action simply by virtue of its
prima facie
status as a “covered person” under section 9607(a).
22
The undefined term “liable” is common to both CERCLA § 9607(a) and Bankruptcy Code § 502(e)(1)(B). Its construction presents a question of law subject to plenary review.
See In re Erin Food Serve., Inc.,
Of course, not all “covered persons” are strictly liable for response costs. The harsh effects of the strict liability rule are subject to mitigation through resort to certain affirmative defenses. Section 9607(b) expressly provides that “[tjhere shall be
no liability
under section [9607](a) ... for a person otherwise liable who can establish by a preponderance of the evidence [the following defenses].... ”
See also Environmental Transp. Sys. v. ENSCO, Inc.,
[T]he [buyer] must have undertaken, at the time of acquisition, all appropriate inquiry into the previous ownership and uses of the property consistent with good commercial or customary practice in an effort to minimize liability. For purposes of the preceding sentence the court shall take into account any specialized knowledge or experience on the part of the [buyer], the relationship of the purchase price to the value of the .property if uncontaminated, commonly knoum or reasonably ascertainable information about the property, the obviousness of the presence or likely presence of contamination at the property, and the ability to detect such contamination by appropriate inspection.
42 U.S.C. § 9601(35)(B) (emphasis added);
see also United States v. Pacific Hide & Fur Depot, Inc.,
Thus, under either section 501(e)(1)(B) or section 503(a), Juniper’s participation in any distribution from the chapter 7 estate hinges entirely on the validity of its “innocent landowner” defense. Notwithstanding its relevance, the “innocent landowner” defense was never explicitly considered by the bankruptcy court in connection with the trustee’s motion for summary judgment disallowing Juniper’s CERCLA claim pursuant to section 502(e)(1)(B), nor in connection with its earlier provisional ruling on Juniper’s entitlement to administrative priority. Cf. supra note 17. The record contains mixed signals on the “innocent landowner” defense. In a May 19, 1987 letter to Juniper, the EPA opined that Juniper would not be entitled to the “innocent landowner” defense, for several reasons: Juniper (1) knew in 1983 that the facility was in close proximity (200 feet) to a larger Superfund site already included on the national priority list; (2) made no preacquisition inquiry of EPA or DEQE concerning possible contamination in the area; and (3) did not obtain available maps showing an unpaved access road to the allegedly inaccessible portion of the facility where the drums were found.
The EPA opinion is not necessarily dispos-itive as to the allowability of a claim or an administrative expense request. Nеvertheless, after trial on the issue of Hemingway’s liability for past response costs, the bankruptcy court noted (notwithstanding Juniper’s contention that the drums were located in an area which was inaccessible at the time of the 1983 sale) that
“easy access
to the location of the barrels is possible along the City of Woburn’s sewer easement, which parallels the MBTA tracks.”
In re Hemingway Transp.,
On the other hand, the record indicates that the bankruptcy court may have considered Juniper’s responsibility for any contamination extremely minimal, especially in comparison to Hemingway-Bristol. For example, in allowing Jumper’s contribution claims for
past
response costs, the bankruptcy court allocated
total
financial responsibility to Hemingway-Bristol,
see supra
note 4, despite the fact that the court also found no evidence that Hemingway-Bristol, throughout twenty years’ occupancy, ever generated or deposited hazardous wastes at the facility. The bankruptcy court further found that Juniper was never “apprised of the presence of hazardous wastes.... ”
In re Hemingway Transp.,
Since the bankruptcy court’s dis-allowance of Juniper’s claim must be vacated on independent grounds, see supra Section II.A.4, on remand the trustee will have the burden to file a surrogate claim in behalf of the EPA and the burden to come forward with substantial evidence that Juniper is not entitled to an “innocent landowner” defense. The ultimate burden of proof on that defense, however, will remain with Juniper. The *934 bankruptcy court should determine whether Jumper made “all appropriate” preacquisition inquiry pursuant to 42 U.S.C. § 9601(35), a factual finding which would be subject to clear error review only. Should the bankruptcy court find that Jumper did not have notice or actual knowledge of the contamination at the time it purchased the facility in 1983, Juniper’s claim for past and future response costs should be estimated 25 and allowed as administrative expenses entitled to priority. 26 On the other hand, if Juniper did not take all appropriate steps to protect itself from CERCLA liability, its lack of diligence exposed it to the harsh consequences of strict, joint and several liability under CERCLA. In that event, Juniper’s claim would be subject to the section 502(e)(2) “fixing” requirement and Juniper would not be entitled to administrative expense priority with respeсt to any allowable CERCLA claim.
B. Juniper’s Appeal: Disallowance of Attorney Fees (42 U.S.C. § 9607(a)).
Juniper argues for an award of attorney fees pursuant to 42 U.S.C. § 9607(a)(4)(B), which makes no reference to “attorney fees” in private cost recovery actions. Juniper contends that the term “necessary costs of response” should be broadly construed to encompass attorney fee awards so as to advance CERCLA’s remedial purposes by inducing PRPs to cooperate in initiating prompt cleanup efforts. We affirm on the grounds advanced in the well-reasoned district court opinion. See In re Hemingway Transp., Inc., 108 B.R. at 383.
Absent an explicit statutory authorization, a party is not entitled to recover attorney fees simply because it prevailed in the litigation.
Runyon v. McCrary, 427
U.S. 160, 185,
Juniper argues, nonetheless, that only a small portion of its attorney fees were incurred in preparation for the “response cost” recovery litigation itself, the greater portion having been incurred to ensure that Juniper’s “response” was in compliance with the administrative order issued by the EPA. We conclude that the present claim was waived. At trial, Juniper’s attorney fee billings were admitted in evidence. Juniper suggested no distinction between attorney fees incurred for litigative and administrative purposes.
27
Jumper’s failure to advance the present contention below deprived the bankruptcy court of an opportunity to consider it, thereby waiving the claim.
See In re LaRoche,
C. The Trustee’s Cross-Appeal: Administrative Expense Priority for Past Response Costs.
The trustee appeals the allowance of Jumper’s claim for past response costs as an administrative expense entitled to priority distribution. The bankruptcy court ruled that Juniper’s CERCLA liability resulted from its postpetition purchase of the facility from Hemingway-Bristol, debtor in possession, during the course of the chapter 11 proceeding. The bankruptcy court found that it would bé fundamentally “unfair” not to allow Juniper to receive payment of its contribution claim in advance of other creditors.
See supra
note 17 (noting court’s reliance on
Reading Co. v. Brown,
We affirm the allowance of Juniper’s claim for past response costs as an administrative expense entitled to priority distribution under Bankruptcy Code §§ 503(b)(1)(A), 507(a)(1) and 726(a)(1).
See Norris v. Lumbermen’s Mut. Cas. Co.,
Ill
CONCLUSION
We vacate the bankruptcy court’s section 502(e)(1)(B) disallowance of Juniper’s claim for future response costs. On remand, the bankruptcy court shall permit the chapter '7 trustee and Juniper a reasonable time within which to file surrogate claims in behalf of the EPA under sections 501(b) or 501(c) of the Bankruptcy Code. Should the trustee file a timely surrogate claim, and should Juniper choose to press for simultaneous allowance of its so-called “direct” claim, the court should determine whether Juniper would be entitled to an “innocent landowner” defense pursuant to 42 U.S.C. § 9601(35)(B). If Juniper is so entitled, its claim for “contribution” should be allowed as an administrative expense. If not so entitled, its claim should be disallowed unless and until Juniper “fixes” its right to contribution by actually incurring any such response costs by the time its claim is considered for allowance. If the chapter 7 trustee elects not to file a surrogate claim under section 501(b), thereby waiving the section 502(e)(1)(B) objection to Juniper’s direct claim against the chapter 7 estate, the cоurt should receive evidence relating to the extent of Juniper’s anticipated response costs and should allow Juniper’s claim as an administrative expense of the chapter 11 estate.
The order disallowing an award of attorney fees, and the order allowing Juniper’s claim for past response costs as an administrative expense, are affirmed. The order disallowing Juniper’s claim for future response costs is vacated and remanded to the bankruptcy court for further proceedings consistent with the opinion herein; costs to neither party.
Notes
. Hemingway began business operations at the facility shortly after acquiring it in 1963. In 1974, Hemingway sold the facility to Woburn Associates, but continued to occupy it under a leaseback arrangement with Woburn. In 1980, Bristol, a wholly owned Hemingway subsidiary, acquired the facility from Woburn.
. Juniper alleges that an engineering firm was paid $30,208 to remove the drums; an environmental consulting firm was paid $7,880 to monitor the removal action; and a law firm was paid $54,000 to ensure adequate compliance with the EPA order.
In April 1988, EPA demanded $2.1 million in CERCLA contribution from Juniper for costs incurred by EPA in assessing and evaluating the site. The PRP notice advised that Juniper would be notified of future "cleanup response costs” as well. In February 1989, EPA sent PRP notices to Hemingway and Bristol, as former owner-operators of the facility. See infra note 9.
. Although count I of the original Juniper complaint did not assert a right to CERCLA contribution, when the trustee's motion for summary judgment on count I was denied the bankruptcy court allowed Juniper to amend count I to assert a claim for contribution under 42 U.S.C. § 9607(a).
In re Hemingway Transp.,
. The defendant in an EPA enforcement action would have an especially heavy burden to establish that the shared responsibility of the PRPs is divisible, so as to elude imposition of joint and several liability.
Cf. O'Neil,
(i) the ability of the parties to demonstrate that their contribution to a discharge, release or disposal of a hazardous waste can be distinguished;
(ii) the amount of the hazardous waste involved;
(iii) the degree of toxicity of the hazardous waste involved;
(iv) the degree of involvement by the parties in the generation, transportation, treatment, storage, or disposal of the hazardous waste;
(v) the degree of care exercised by the parties with respect to the hazardous waste concerned, taking into account the characteristics of such hazardous waste; and
(vi) the degree of cooperation by the parties with Federal, State or local officials to prevent any harm to the public health or the environment.
Environmental Transp. Sys., Inc. v. ENSCO, Inc.,
. Section 9613(f)(1) provides:
Any person may seek contribution from any other person who is liable or potentially liable under section [9607(a)], during or following any civil action under section [9606] or under section [9607(a) ]. Such claims shall be brought in accordance with this section and the Federal Rules of Civil Procedure, and shall be governed by Federal law. In resolving contribution claims, the court may allocate response costs among liable parties using such equitable factors as the court determines are appropriate. Nothing in this subsection shall diminish the right of any person to bring an action for contribution in the absence of a civil action under section [9606] or section [9607],
42 U.S.C. § 9613(f).
. Under CERCLA § 9607(a)(4)(B),
see
pp. 930-31
infra,
"contribution” relief is restricted to damages for
past
response costs
(i.e.,
costs already "incurred”). On the other hand, section 9613(g)(2) authorizes a declaratory judgment action to determine liability for response costs which "will be binding on any subsequent action or actions to recover further response costs or damages,” a form of relief plainly encompassed within Juniper's amended complaint.
See In re Chateaugay Corp.,
. Section 502(e)(2) provides:
A claim for reimbursement or contribution of such an entity that becomes fixed after the commencement of the case shall be determined, and shall be allowed under subsection (a), (b), or (c) of this section, or disallowed under subsection (d) of this section, the same as if such claim had become fixed before the date of the filing of the petition.
11 U.S.C. § 502(e)(2).
. EPA enforcement actions generally are excepted from the automatic stay provisions.
See
Bankruptcy Code § 362(b)(4), 11 U.S.C. § 362(b)(4);
New York v. Exxon Corp.,
. In a May 1987 letter to Juniper, the EPA suggested that it had already exercised its discretion to refrain from asserting an enforcement action against the chapter 7 estate, at least as of that time. Two years later, however, the EPA sent PRP notices to Hemingway and Bristol.
. In a chapter 7 case, proofs of claim must be filed within ninety days after the first date set for the first meeting of creditors. Fed.R.Bankr.P. 3002(c).
See In re Chirillo,
. Bankruptcy Code § 726(a)(2)(C) provides for "payment of any allowed unsecured claim, other than a claim of a kind specified in paragraph (1), (3), or (4) of this subsection, proof of which is ... tardily filed under section 501(a) of this title, if (i) the creditor that holds such claim did not have notice or actual knowledge of the case in time for timely filing of a proof of such claim- under section 501(a) of this title; and (ii) proof of such claim is filed in time to permit payment of such claim.” 11 U.S.C. § 726(a)(2)(C). The appellate record does not disclose whether EPA was listed as a creditor. In addition, it is conceivable, though unlikely, that EPA’s CERCLA claim might be entitled to share in any subordinate distribution under section 726(a)(3), as an “allowed unsecured claim proof of which is tardily filed,” even if EPA was scheduled, or had actual notice of the case prior to the bar date.
See In re Melenyzer,
. Of course, the bankruptcy court might condition its allowance of a codebtor’s claim on the ultimate failure of the creditor to file a proof of claim.
See
Bankruptcy Code § 502(j), 11 U.S.C. § 502(j) ("A claim that has been allowed or disallowed may be reconsidered for cause.”). Instead of automatic disallowance, some courts have suggested that the bankruptcy court sharply discount the codebtor's claim to offset this all-or-nothing contingency, or direct that any distribution to the codebtor be placed in trust, to be expended only to reduce the common debt.
See In re Allegheny Int'l., Inc.,
. The equitable considerations underlying the section 501(b) surrogate-claim procedure have been described as follows:
Section 501(b) and Rule 3005 protect the co-debtor against the danger that the creditor, faced with the bankruptcy of the prime debtor, might decide to rely on the solvency of the codebtor and therefore, to abstain from filing a proof of claim. In such a case, while there might be a prospect of securing at least partial satisfaction from the assets of the debtor, the creditor would forego this possibility and merely proceed with his claim against the co-debtor. By the time the creditor decided to take such action, any period fixed for the filing of claims might have elapsed. Indeed, the debtor’s estate might have been fully administered by the trustee so that the codebtor would be left without the possibility of even partial reimbursement to the extent he has satisfied the claim of the debtor’s creditor. The debt- or’s discharge would remove the possibility that his codebtor could secure indemnification from him at some future time_ [T]he unwillingness of th[e] creditor to take the necessary steps in the administration of bankruptcy to insure ... participation [in distribution of the debtor’s assets] would not deny the ability of the codebtor to do so.
See Lawrence D. King, Collier on Bankruptcy ¶ 509.02, at 509-6 (15th ed. 1991) [hereinafter Collier on Bankruptcy].
. Although the EPA can no longer file a "timely” proof of claim now that the bar date has passed, see supra note 10, its forbearance triggers the trustee’s and Juniper’s rights to file a proof of claim in EPA's behalf. Under Bankruptcy Rules 3004 and 3005(a), the trustee and Juniper normally would have only thirty days from the bar date to file their surrogate claims. But insofar as EPA "did not have notice or actual knowledge of the case in time for timely filing of a proof of ... claim,” Bankruptcy Code § 726(a)(2)(C)(i), see also supra note 11 and accompanying text, the EPA can yet file a belated claim that can receive payment along with other timely-filed unsecured claims, so long as "proof of such claim is filed in time to permit payment of such claim.” Id. § 726(a)(2)(C)(ii). Thus, the trustee and Juniper, as EPA surrogates, can avail themselves of the section 726(a)(2)(C) "extended filing” provision.
. Unlike a creditor filing in its own behalf, or a trustee seeking to avail the debtor of the full benefit of a chapter 7 discharge, in this case the chapter 7 trustee may have little incentive to maximize any surrogate claim in behalf of EPA, thus depleting any pro-rata dividend available to other unsecured creditors. A similar problem may arise if any superseding proof of claim filed by EPA were to understate (in Juniper's view) the chapter 7 debtors’ share of the CERCLA obligation. We do not construe subsections 501(b) and (c) as suggesting that the trustee could preempt a surrogate EPA claim by Juniper under section 501(b) asserting that the chapter 7 estate’s CERCLA liability to EPA is greater than that asserted in the trustee's section 501(c) surrogate claim. Rather, the bankruptcy court should entertain evidence from the trustee and Juniper, for the purpose of estimating the value of the EPA claim under section 502(c).
. The bankruptcy court implicitly acknowledged as much when it approved Juniper’s request for
past
response costs as an administrative expense: "Juniper’s cause of action under CERCLA arose when the property containing the
*929
drums was transferred to Juniper or, alternatively, when Jumper expended money in response to the EPA's administrative order.”
In re Hemingway Transp.,
. Courts have long recognized a category of allowable administrative expenses resulting in no discernible benefit to the debtor estate,
see In re Charlesbank Laundry, Inc.,
In citing
Reading
and
Charlesbank
as support for its provisional decision granting Juniper administrative priority for its postpetition contribution claims, the bankruptcy court focused entirely on the
debtors’
failure to disclose the environmental risk prior to the 1983 sale, and the perceived "unfairness” in the "debtor attempting to transfer its liability or potential for liability under state or federal environmental laws” in those circumstances.
See In re Hemingway Transp.,
. "Creditor” means an "entity that has a claim that arose at the time of or before the ordеr of relief." Bankruptcy Code § 101(9), 11 U.S.C. § 101(9).
. "Response costs,” 42 U.S.C. § 9601(25), include costs incurred in "removal” actions, which address immediate threats to public health and safety caused by hazardous substances, 42 U.S.C. § 9601(23), and costs incurred in “remedial” actions, directed at long-term or permanent remediation of the contamination, 42 U.S.C. § 9601(24).
. Section 9607(a) provides, in pertinent part:
(1) [T]he owner and operator of a vessel or a facility,
(2) [A]ny person who at the time of disposal of any hazardous substance owned or operated any facility at which such hazardous substances were disposed of ... shall be liable for—
(A) all costs of removal or remedial action incurred by the United States Government or a State ...
(B) any other necessary costs of response incurred by any other person consistent with the national contingency plan.
42 U.S.C. § 9607(a)(2)(B) (emphasis added).
. The bankruptcy court opinion states: "In the context of this case, it is possible to view Juniper as a direct creditor of Hemingway and as an entity jointly liable with the Debtor.”
In re Hemingway Transp.,
. The bankruptcy court based its section 502(e)(1)(B) disallowance on the ground that Juniper had denominated its claim a derivative claim for "contribution,” thereby conceding its co-liability with the Hemingway-Bristol estate for future response costs. In our view, this ruling exalts form over substance, and ignores both the liberality with which pleadings must be construed and the right to plead alternative or seemingly "inconsistent” claims.
See
Fed.R.Bankr.P. 7008(a) (incorporating Fed.R.Civ.P. 8(e), providing that “[a] party may set forth two or more statements of a claim or defense
alternatively
or hypothetically ...
regardless of
consistency-”) (emphasis added);
cf. also Schott Motorcycle Supply, Inc. v. American Honda Motor Co.,
.The parties do not challenge the bankruptcy court ruling that the Hemingway-Bristol estate is “liable” for the "passive” disposal at the facility
(i.e.,
the leaking of previously generated or deposited containers of hazardous waste), even absent evidence that the chapter 7 estate contributed to the generation or the deposit of the hazard
*933
ous substances in the first instance. Furthermore, the chapter 7 estate could not establish an "innocent owner” defense: the 1982 DEQE notice afforded the debtors
actual
knowledge that drums of contaminants were located at the facility. On the other hand, the bankruptcy court found that "none of the interested parties, including the Trustee, Juniper and the two courts that approved the sale, were apprised of the presence of hazardous wastes on the property, despite the DEQE action.”
In re Hemingway Transp.,
. The EPA informed Juniper in May 1987 that its alleged contribution to the passive disposal was undetermined because the extent of the рost-1983 "contaminant plume” at the facility had yet to be ascertained.
. Because of its earlier section 502(e) disallowance, the bankruptcy court refused to permit Juniper to introduce evidence of anticipated future cleanup costs. Although we need not decide the issue at this juncture, we note that the EPA's npnbinding preliminary allocation of responsibility may be inadmissible evidence as to the value of Juniper’s claim for future response costs, see 42 U.S.C. § 9622(e)(3)(C) ("The nonbinding preliminary allocation of responsibility shall not be admissible as evidence in any proceeding ... [nor] constitute an apportionment or other statement on the divisibility of harm or causation.”), and, on remand, that it may be incumbent on Juniper to present other evidence of the extent of its "injury.”
. The determination of Juniper’s CERCLA "liability” by the bankruptcy court is required solely for purposes of the allowance or disallowance of Juniper’s proof of claim, a core proceeding in bankruptcy, and the court cannot ignore the possibility that the EPA might yet maintain a successful enforcement action against Juniper. But unlike the holder of a
prepetition
claim for contribution, which normally must await final distribution under Bankruptcy Code § 726, Juniper would enjoy a distinct distributional advantage should it succeed in establishing its entitlement to the "innocent landowner” defense under section 9607(b)(3). The court properly cоuld provide for the
immediate,
pre-distribution payment of Juniper's "claim”
in trust, see, e.g., In re Allegheny Int'l, Inc.,
. Prior to admitting Jumper's attorney fee billing in evidence, the bankruptcy judge stated: ‘‘[A]ssuming only for the moment that legal services are a compensable item of damage [under CERCLA], then aren’t all reasonable fees incurred by the plaintiff resulting from the alleged harm, aren’t they all compensable? ... [D]idn’t [Juniper’s attorneys] perform services as a result of the acts of the defendant if I find the defendant liable?” Thus, the court plainly signaled its intention to treat Juniper’s entire attorney fee request as either compensable or noncompensa-ble.
. Even assuming the issue was preserved, the record on appeal does not enable reliable appellate review. It is impossible to determine with reasonable confidence whether the attorney fees incurred by Juniper were reasonably "necessary” to facilitate its compliance with the EPA administrative order, or to discover the existence or whereabouts of other PRPs who might be amenable to suit by Juniper in an action for contribution.
