137 Wis. 107 | Wis. | 1908
Tbe trial court beld, in effect, tbat tbe written, contract in question was uncertain and indefinite in its terms, so that it could not be determined therefrom whether it required the defendants to ship a carload of malt every week to the plaintiff at Milwaukee without further ■orders, or whether it required the plaintiff to order each carload by separate order before the defendants were required to ship it. So construing the contract, the court, against objection, permitted the introduction of a large amount of parol testimony relating to the situation of the parties and their-negotiations resulting in the making of the contract, as well as testimony relating to the .acts and correspondence of the parties after the contract in the way of practical construction thereof, and submitted to the, jury the question of the proper construction of the contract in the light of this evidence.
These rulings were all challenged by the plaintiff on the ground that the contract is definite and certain in its terms, and required the defendants to deliver one carload per week at Milwaukee without further orders. This contention is based upon the written clauses of the written contract which follow the words “Price,” “E. O. B.,” and “When to be shipped” of the printed blank. These clauses provide, in substance, that the price shall be fifty-nine cents per bushel delivered free on board cars at Chestnut Street Station, Milwaukee, to be shipped one car per week beginning in the last week of November. If these clauses stood alone there would seem to be very good ground for the plaintiff’s contention, but
The sole remaining question which we deem it necessary to consider is whether there was a waiver by the defendants of the plaintiff’s breach of the contract. The contract, as properly construed by the jury, required the plaintiff to order one carload per week beginning with the last week in November. A carload contained from 1,900 to 2,000 bushels, •and, had a carload been ordered each week, the performance of the contract would have been completed during the first week in February. The plaintiff ordered one carload in November and one-in December. On January 8th the defendants wrote, calling attention to the default, and in effect demanding that the plaintiff live up to the contract in the future. The plaintiff then ordered another carload, which upon delivery was claimed to be not up to contract requirements. A serious dispute arose on this question, which was finally settled by the defendants consenting to a slight reduction of price on February 4th. From this time until March 25th there was complete silence between the parties. The . plaintiff gave no orders and the defendants made no demand for orders. On the 25th of March the plaintiff ordered a carload to be delivered, and on the following day the defendants declined to deliver any more and declared the contract canceled. Were they entitled to take this action at this time ?
There may be a breach of an executory contract by deliberate refusal to perform stipulations upon which''the obligation of the other party depends, and, when such breach takes place, the other party has a right to treat the contract as
Under many circumstances the failure to send orders for two months might be a very insignificant matter, but certainly that cannot be said here, where prompt ordering of a product, subject to great and rapid changes in market value, was evidently a very material part of the arrangement. In view of the nature of the contract, the evident intention that there was to be rapid delivery, the dissatisfaction with the January shipment, and the repeated declaration of the plaintiff that it would insist upon the delivery of a better quality of malt in the future, in the face of defendants’ claim that the quality was unexceptionable, we think that there was ample ground for the defendants to conclude that the plaintiff’s failure to order any more cars, or make any sign for a period of nearly two months after delivery should have been completed, under the terms of the contract, was a deliberate repudiation of the contract by the plaintiff upon which they were entitled to stand. As they neither did nor said anything thereafter indicating that they expected 'or demanded performance of the contract, it cannot be said that they treated the contract as still existing, or waived their right to treat the repudiation as a breach.
By the Court. — Judgment affirmed.