59 Ind. App. 472 | Ind. Ct. App. | 1915
The substance of appellees’ complaint is as follows: In 1906, appellant city of Rushville by regular proceedings contracted with appellees, to furnish the-material and perform the work in the improvement of Arthur Street in said city from Third Street north to the corporation line. The work consisted of grading the roadway and surfacing it with broken stone, and constructing cement gutters and stone curbing along the line of the roadway on each side. The cost of the work was to be assessed against the abutting owners as provided by statute. Appellees after the work had commenced were regularly granted extensions of time, within which to complete it, the extended periods expiring September 1, 1908. On July 1, 1907, appellees were prosecuting the work,, and at that time had completed most of the curbing and guttering, and had graded and surfaced a large part of the roadway. On April 23, 1907, appellant city, by regular proceedings, contracted with appellant company for the construction of a sewer system in said city, including a sanitary sewer the entire length of Arthur Street. Commencing about July 1,1907, appellant company, as a part of the work of constructing the sewer .on Arthur Street, made an excavation the entire length of that street north of Third Street, eighteen feet .deep and four feet wide, the west edge of which was within four feet of the east edge of the curb and gutter theretofore constructed by appellees, and placed therein a row of eighteen-inch sewer pipe as required by the contract, and thereupon, using loose dirt, filled the excavation not more than half full, and thereafter did nothing further at the work until April, 1908, all of which was done before appellees had completed • their
The fact that no instruction on the subject of appellees’ contributory fault was given by the court tends to magnify the effect of the omission of that element from instruction No. 9. Instructions Nos. 10 and 11 do not supplement No. 9 in the matter under consideration. In fact, the same infirmity, perhaps to a less marked degree, exists also in those instructions. In other respects, however, instruction No. 11 tends rather to aggravate the error in No. 9, in that the natural effect of the former in the minds of the jurors would necessarily be to minimize the force that should be assigned to the fact of faulty construction by appellees.
From the foregoing facts it appears that the arrangement between the city and the construction company was to the effect that the latter in consideration of the equivalent of a lump sum to be paid, obligated itself to furnish all the material and labor necessary, and thereby to construct an entire improvement according to designated plans and specifications, free from the control of the city respecting how the work should be accomplished. It was the right of the city to require that a certain work be done, but except as outlined in the specifications, and as above indicated, it reserved no right to dictate how the result should be accomplished. The construction company must, therefore, be regarded as an independent contractor, rather than as an agent or servant of the city. Prest-O-Lite Co. v. Skeel (1914), 182 Ind. 593, 106 N. E. 365; Wabash, etc., R. Co. v. Farver (1887), 111 Ind. 195, 12 N. E. 296, 60 Am. Rep. 696; Vincennes Water Co. v. White (1890), 124 Ind. 376, 24 N. E. 747; City of Richmond v. Sitterding (1903), 101 Va. 354, 43 S. E. 562, 99 Am. St. 879, 65 L. R. A. 445, note. This is true, notwithstanding the provisions of the contract, by which as indicated the city reserved the right of general supervision. Prest-O-Lite Co. v. Skeel, supra; Uppington v. City of New York (1901), 165 N. Y. 222, 59 N. E. 91, 53 L. R. A. 550; Salmon v. Kansas City (1912), 241 Mo. 14, 145 S. W. 16, 39 L. R. A. (N. S.) 328; Casement & Co. v. Brown (1893), 148 U. S. 615, 13 Sup. Ct. 672, 37 L. Ed. 582; Foster v. City of Chicago (1902), 197 Ill. 264, 64 N. E. 322.
It is evident that both instructions Nos. 8 and 9, as applied to the facts in this case are erroneous. Por the giving of these instructions there must be a reversal in behalf of the city, and a reversal in behalf of appellant construction company for -error in instruction No. 9. We do not base our decision on the insufficiency of the evidence. Other questions presented are not determined as they may not arise on a retrial. The cause is reversed with instructions to sustain the motion of each appellant for a new trial.
Note. — Reported in 109 N. E. 797. Proximate and remote causes of injury from negligence, see 36 Am. St. 807. Liability of municipal corporation for acts or negligence of independent contractor in repairing or improving street or highway, see 16 Ann. Cas. 433. See, also, under (1) 2 Cyc. 1042; (2) 3 C. J. 1356; (3) 29 Cyc. 651, 652; (4) 29 Cyc. 652; (5) 28 Cyc. 1280, 1282; (6) 28 Cyc. 178; (7, 8) 28 Cyc. 1280; (9) 28 Cyc. 1436, 1463; (10) 28 Cyc. 1266; (11) 28 Cyc. 1283.