Lead Opinion
Appellant Shari Judkins seeks review of an order granting summary judgment to Appellee, Walton County, on Judkins’ inverse condemnation claim based on Jud-kins’ failure to comply with the four year statute of limitations contained in seсtion 95.11(3)(p), Florida Statutes. Judkins argues that the stabilization doctrine set forth in United States v. Dickinson held the statute of limitations on her claim in abeyance until Walton County abandoned its efforts to remediate the flooding of Judkins’ property; she also argues that the trial court abused its discretion in failing to grant her leave to amend her complaint. We affirm the denial of leave to amend without comment, but write to explain why we affirm the trial court’s ruling that the stabilization doctrine does not apply to this case.
Judkins acquired unimproved residential property in Destín in 2001, and became the sole owner of the parcel in 2006. -In 2002 and 2003, Walton County performed road improvement activity on Holiday Road, which fronts the property. That activity involved alteration to the existing drainage pattern. After the work was complete in 2002, Appellee noticed that the property floоded nearly every time it rained, such that it was impossible to improve the property. While there is some evidence that later projects may have contributed some flood water to the property, Judkins has consistently asserted that the property has
After Judkins complained to the county, she asserts she received numerous assurances that the flooding problem would be repaired. According to Judkins, the county represented that contemplated road work in nearby neighborhoods would alleviate flooding on her property. Walton County undеrtook several projects, but the problem was never successfully resolved; there is no evidence that these projects were undertaken for the purpose of remedying flooding on the Judkins propеrty. In fact, a 2004 letter from the county engineer to Judkins advised that the flooding was not caused by the 2002 road improvements and that Walton County assumed no responsibility for repairing it. One such project concluded in 2007 but did not ameliorate the flooding.
In 2009, Judkins filed a Complaint for Inverse Condemnation based on the flooding of the parcel, alleging that the drainage system associated with the road improvement project caused water to continuously and permanently stand on the property, rendering it unusable. Walton County raised several affirmative defenses, including that the claim was barred by the statute of limitations, which the county asserted bеgan to run in 2002 when the water first continuously invaded the property. On this basis, the trial court granted summary judgment to Walton County.
Judkins contends that the logic of United States v. Dickinson compels reversal in this case.
This Court applied Dickinson’s rationale to inverse condemnation claims in Millender v. State Department of Transportation,
Only one other Florida court has applied the Dickinson stabilization doctrine. In Hillsborough County Aviation Authority v. Benitez,
Judkins relies on Applegate v. United States,
No court has applied the stabilizаtion doctrine in a situation where the extent of the injury is known and the cause of action has accrued. Judkins suggests that we apply the doctrine based solely on a subsequent promise to build a distinct project which may have some remedial effect on the initial intrusion, for which a cause of action has accrued. We decline to do so.
Turning to the instant case, application of this rule is simple. When the flooding allegedly caused by Walton County’s improvements to Holiday Road invaded Jud-kins’ property in 2002, the property was no longer improvable and thus had been taken, regardless of whether the county promised to repаir the problem. The statute of limitations began to run at that time, and had elapsed well before suit was filed in 2009.
This is not to say that Walton County’s actions in promising to remedy the flooding and then, after the limitations period expired, abandoning the remediation effort insulated it from liability. Indeed, Judkins may very well have been able to avoid the statute of limitations by pleading and proving equitable estoppel. Avoidance of affirmative defenses, however, must be specifically pled in a Reply. Fla. R. Civ. P. 1.110(d). At no point in this proceeding did Judkins raise collateral estoppel, and therefore the issue was waived.
Because the Dickinson stabilization doctrine does not apply in this case, the summary judgment entered below is AFFIRMED.
Concurrence Opinion
Concurring.
I too conclude that the circuit court’s decision should be affirmed because Jud-kins’ claim did not comply with the statute of limitations.
■ But, with all respect for my colleaguеs’ views, I think that the Dickinson stabilization doctrine does apply to forestall the
Applegate is most often cited. It involved a government promise to construct a sand transfer plant that would remedy government-caused erosion on coastal property. After decades of promises, the plant never got built. When landowners sued, and the government asserted a statute of limitations defense, the Federal Circuit applied Dickinson and permitted the suit to go forward. It said:
With plans for a sand transfer plant pending, the landowners had no way to determine the extent, if any, of the permanent physical occupation.... [Uncertainty has stayed accrual of the claim. The Government’s promise to restore the littoral flow destroyed any predictability of the extent of damage to the land.
Applegate,
Likewise, here, I think that Walton County’s promises to Judkins allowed her lawsuit to be postponed, for a while anyway. It does not matter for purposes of the Dickinson stabilization doctrine that Judkins knew in 2002 that the County had flooded her property. Though the flooding was evident, the County promised to fix it and its ongoing work adjacеnt to her property kept the situation from immediately stabilizing or reaching permanency. See Dickinson,
Nevertheless, I still think that Judkins filed her case too late. Even applying Dickinson, her situation became permanent in 2004. What stabilized things at that point is that Judkins wrote the County a letter asking point-blank about “what [it] intended to do about resolving the problem [of water running onto her] formerly dry, accessible, and useable property?” The County responded in May 2004, by asserting that it did not cause Judkins’ flooded property situation; by disputing Judkins’ contention that her property had been dry, accessible, and useable; and by extending no promise to fix her flooded property. The lеtter declared instead that Judkins’ property had “always” been wetlands. And it was framed as the County’s “last correspondence on the matter.”
While the County’s various assertions in the letter about the cause and naturе of the flooding remained hotly disputed, no genuine issue of material fact remained after the County’s letter as to Dickinson’s applicability. The letter ended Dickinson’s applicability because Judkins’ flooding situation effectively became permanent — her рroperty remained flooded and the County expressed no intention of fixing it. Judkins produced no evidence in response to Walton County’s summary judgment motion to show that she reasonably could continue relying on whatever old promises the County had made prior to May 2004. So the situation stabilized and the four-year statute of limitations commenced. Because Judkins did not file her
