Joseph A. Fortin Construction, Inc. v. Massachusetts Housing Finance AgencyJoseph A. Fortin Construction, Inc. v. Massachusetts Housing Finance Agency
A judge of the Superior Court allowed the defendant’s motion for summary judgment against the plaintiffs, on the basis that the action was barred by the statute of limitations, G. L. c. 260, § 2A. The plaintiffs appealed and the Appeals Court reversed the judgment.
Joseph A. Fortin Constr. Co.
v.
Massachusetts Pious. Fin. Agency,
17 Mass.
The facts were established by uncontroverted affidavits. The MHFA made a construction loan in August, 1974, to Beverly Homes, Inc. (Beverly), to develop a housing project. Beverly hired the plaintiffs as general contractors for the project. On November 22,1976, before the project was completed, Beverly terminated the plaintiffs’ contract for an alleged default. The resulting dispute was submitted to arbitration. The arbitrator found for the plaintiffs. The plaintiffs then sought enforcement of the arbitrator’s award in the Superior Court and obtained a judgment against Beverly in 1980 for amounts due them under the contract. In May, 1980, the plaintiffs’ writ of execution of the judgment was returned unsatisfied. The plaintiffs filed the present action against the MHFA in October, 1980, seeking to recover from the MHFA the value of the unsatisfied judgment they hold against Beverly. The plaintiffs’ theory apparently is that the MHFA had a duty, under St. 1966, c. 708, as amended through St. 1971, c. 1030, to require Beverly to provide security from which the plaintiffs could have secured payment of their judgment, that MHFA negligently failed to perform its duty, and that this negligence caused injury to the plaintiffs. We suggest nothing concerning the merits of the plaintiffs’ claims. Before us is a more narrow question: assuming such a cause of action exists, when does the statute of limitations begin to run?
2
Both parties agree that the plaintiffs’ action is in
General Laws c. 260, § 2A, provides that actions of tort shall be commenced “only within three years next after the cause of action accrues.” While the point at which negligence actions accrue is not provided in the statute, it is a well-settled rule that causes of action in tort generally accrue under G. L. c. 260, § 2A, at the time the plaintiff is injured.
Cannon
v.
Sears, Roebuck & Co.,
The plaintiffs contend that they incurred injury when the writ of execution on their judgment was returned unsatisfied. Under this analysis, the statute began to run in May, 1980. The plaintiffs’ action filed in October, 1980, would, therefore, be well within the three-year period allowed by G. L. c. 260, § 2A. In contrast, MHFA claims that, if the plaintiffs suffered any injury at all from MHFA’s alleged failure to act, they did so at the time (November, 1976) that Beverly wrongfully terminated the plaintiffs’ employment contract. Thus MHFA contends that the plaintiffs’ proposed action accrued, if at all, in November, 1976. It then argues that the proposed action is barred by the limitation in G. L. c. 260, § 2A, because the plaintiffs filed their complaint against MHFA in October, 1980, more than three years after the accrual of the action. We agree with the plaintiffs.
Before an action based in negligence may be maintained, there is a requirement that both negligence and harm be shown, with a causal connection between the two elements. Cannon v. Sears, Roebuck & Co., supra. Looking to the negligence and injury alleged, and to the facts of this case, we conclude that the MHFA’s purported negligence could not have caused the plaintiffs’ injury until the plaintiffs received back unsatisfied the writ of execution on their judgment against Beverly.
The injury caused by a defendant required to maintain a negligence action is the same as that required for the cause of action to accrue.
Dinsky
v.
Framingham, supra
at 803. “To rule otherwise would be intrinsically unfair. . . . [T]he plaintiff might be barred from bringing an action even before the facts arose on which he could assert a claim for relief.”
Cannon
v.
Sears, Roebuck & Co., supra
at 742. We have concluded in other situations that a cause of action accrues on the happening of an event likely to put the plaintiff on notice. The plaintiffs here obtained, and received back unsatisfied, a writ of execution on their judgment against Beverly for wrongful termination of the contract within two months of obtaining the judgment. We think in the circumstances of this case the return of the writ
We conclude that the judge improperly entered summary judgment against the plaintiffs on the ground that the claim was barred by the statute of limitations. The judgment for the defendant is reversed. The case is remanded to the Superior Court for further proceedings consistent with this opinion.
So ordered.
Notes
The MHFA contends as a threshold matter that the plaintiffs’ appeal is not properly before us because the judge did not make the necessary findings under Mass. R. Civ. P. 54 (b),