This is a review of a decision of the court of appeals affirming a judgment of the circuit court for Milwaukee county, HON. PATRICK J. MADDEN, presiding. The judgment dismissed the claim of the plaintiff-appellant-petitioner, Joseph P. Jansen Company, Inc., (Jansen) and awarded $17,910.75 to the defendant-respondent, Milwaukee Area District Board of Vocational, Technical and Adult Education (MATC) on its counterclaim. This case involves the application of a written construction contract to a dispute over credits and extras for work done and materials used in filling an excavation (hole) in a building site. Jansen, a building contractor, claimed it was entitled to additional compensation for alleged “extra work” performed under the written construction contract in filling the excavation, and MATC, the owner, claims it is entitled to a credit on its payments to Jansen because of Jansen’s substitution of materials used as fill. The trial court construed the contract as a matter of law and granted MATC’s renewed motion for directed verdict after a jury verdict was rendered in favor of Jansen.
Under Sec. 2210, Stoehr was required to strip all topsoil from the land on which the building was to be erected.
1
Performance of this requirement left a depressed area known as a swale at the building area of the MATC South Campus known as the TI South Wing. Before the building could be constructed, this swale had to be filled with material of sufficient stability to bear the weight of the building. Jansen raised the question of responsibility for filling the swale at a meeting held on
After being informed by MATC’s architect that it was responsible to fill the swale area, and before proceeding with construction, Jansen requested permission to substitute “site fill” for “engineered fill” as specified in the contract. A substantial amount of fill was required to bring the swale area to the required elevation. Site fill was considerably less expensive than engineered fill and met relevant contract specifications. MATC agreed to the substitution of fills but there is conflicting evidence as to whether an agreement was reached to credit MATC with the cost savings resulting therefrom. However, a conference memorandum prepared by MATC’s architect indicates that at the meeting held on June 9, 1975, Jansen conceded that there was a value difference between the site fill and select fills and agreed to submit the question to arbitration to determine the amount of credit due the owner, if an agreement could not be reached with the architect.
Jansen and MATC failed to resolve their dispute over the responsibility for excavating and filling the swale area; and, in November of 1977, two years after completion of the building project, Jansen brought this action seeking a reimbursement of $14,625 for the alleged “extra work” it performed. MATC counterclaimed for a
The case was tried to a jury on April 16th through 18th, 1977. At the close of plaintiff’s case, MATC moved for dismissal, arguing that liability was determinable solely from the contract. Before submission to the jury, MATC also moved for a directed verdict on the same grounds. The court reserved ruling on each of these motions and submitted the case to the jury. On April 19, 1979, the jury returned a verdict in favor of Jansen. On October 24, 1979, more than 180 days after the jury rendered its verdict, the trial court granted MATC’s motion for a directed verdict and set aside the jury verdict. Judgment was entered on November 29, 1979, awarding MATC the sum of $17,910.75 on their counterclaim.
Jansen appealed this decision, arguing that MATC’s motion for directed verdict should be denied because the trial court did not enter its order granting the motion within the time period specified in sec. 805.16, Stats. (90 days) and, further, that there was credible evidence to support the jury verdict. The court of appeals affirmed the trial court’s judgment, holding that the failure of the trial court to render a timely decision on MATC’s motion was not prejudicial and that the terms of the contract were not ambiguous and thus they required Jansen to excavate and fill the swale.
Issues:
1. Did the trial court commit prejudicial error in failing to act on MATC’s motion for a directed verdict within 90 days of the verdict?
2. Did the court of appeals err in holding that the construction of the construction contract was solely a question of law reviewable ab initio by that court?
Sec. 805.16, Stats., expressly requires that an order granting or denying a motion challenging the sufficiency of the evidence, or for a new trial, must be entered within 90 days of the verdict or the motion shall be deemed denied.
2
Pursuant to the provisions of sec. 805.14, motions to dismiss made at the close of plaintiff’s case and motions for directed verdict are motions challenging the sufficiency of evidence as that term is used in ch. 805, Stats.
3
In this case, more than five months
On review of this case, the court of appeals acknowledged the error but held “that the defendant was not prejudiced.” 4 Jansen argues that this holding was erroneous as it disregarded established case law applying the time limitation for deciding motions after verdict.
The effect of an order entered after the expiration of the 90-day time limit set out in sec. 805.16, Stats., is a question of first impression. Several decisions of this court, however, have discussed the effect of an order entered after the passing of the 60-day time limit contained in the predecessor statute to sec. 805.16. 5
“The verdict was returned by the jury on March 22, 1962, so that the sixty-day period within which the circuit court might have entered an order for a new trial, absent any order extending time, expired on May 21, 1962. The circuit court’s memorandum opinion was not rendered until June 8, 1962, and the order for new trial was not entered until July 17, 1962. Thus the circuit court’s order for a new trial is void for lack of jurisdiction because not entered within the statutory period. Alberts v. Rzepiejewski (1962), 18 Wis. (2d) 252, 256, 257, 118 N.W. (2d) 172 ,119 N.W. (2d) 441 ; Volland v. McGee (1941),236 Wis. 358 , 363,294 N.W. 497 ; Urban v. Anderson (1940),234 Wis. 280 , 283, 284,291 N.W. 520 ; and Bankers Finance Corp. v. Christensen (1923),181 Wis. 398 ,195 N.W. 319 .” Hurst v. Hungerford,19 Wis. 2d 537 , 539,120 N.W.2d 727 (1963).
The purpose of this court’s strict application of the time limit for deciding motions after verdict has been summarized as seen below:
“. . . If its purposes are to be accomplished, its unambiguous terms must be complied with. Starting with sec. 2878, Stats. 1898, and giving consideration to the several amendments thereto, it is clear that the legislature and this court, in the exercise of its rule-making powers, intended that litigation be expedited and that unreasonable delays in deciding motions after verdict be prevented.” Beck v. Wallmow,226 Wis. 652 , 657,277 N.W. 705 (1938).
This purpose is equally applicable to the time limits established in sec. 805.16, Stats. The Judicial Council stated its intent in proposing sec. 805.16 was “to prevent unnecessary protraction of litigation.”
6
This is the same
In ruling- the error of the trial court was not prejudicial to the defendant, the court of appeals addressed the wrong question. An order that is adverse to a party and is made after the court has lost the capacity to exercise its jurisdiction is, without a doubt, prejudicial to the party aggrieved. However, cases decided under sec. 270.49(1), Stats. 1973, make it eminently clear that when a trial court tardily attempts to decide a motion over which it has lost competency to exercise jurisdiction, an appellate court is not foreclosed from invoking its power under secs. 751.06 and 752.35, formerly sec. 251.09, Stats. 1975, in the interest of justice to accomplish the same result that the trial court attempted to accomplish but was unable to because of its loss of the capacity to exercise jurisdiction.
“In a situation such as this, where the trial court has determined that a new trial should be had in the interestof justice but the court’s decision or order for a new trial is ineffective because of failure to comply with the requirements of sec. 270.49, Stats., this court deems it its duty to review the record to determine whether it should exercise its discretion under sec. 251.09 to order a new trial in the interest of justice.” Graf v. Gerber, 26 Wis. 2d 72 , 76,131 N.W.2d 863 (1965). See also: Dupler v. Seubert,69 Wis. 2d 373 , 381,230 N.W.2d 626 (1975).
In
Graf v. Gerber, supra,
we applied the procedure described in the quotation above and ordered a new trial to prevent a miscarriage of justice in the case where the trial court was without competency to exercise its jurisdiction to enter such an order because the statutory time limit for ordering a new trial had expired. We exercised our discretionary powers in a similar manner in
Looman v. Milwaukee Mutual Ins. Co.,
We deem it appropriate to adopt a similar procedure where an order of the trial court is ineffective for failure to comply with the 90-day time limit of sec. 805.16, Stats. Unlike former sec. 270.49, Stats. 1973, sec. 805.16 applies to motions challenging the sufficiency of the evidence in addition to motions for a new trial. The time limit which formerly restricted the power of the trial court to deal with motions for a new trial now restricts the power of the trial court to deal with all post verdict motions challenging the sufficiency of the evidence as well as those seeking a new trial on other grounds. Because of this difference in the scope of the revised statute, it is appropriate for this court to review the record under sec. 751.06 to determine whether it is proper to direct a judgment in the case where the void trial court order granted a motion challenging the sufficiency of the evidence.
Although the decision of the trial court granting the motion for directed verdict is void, prior decisions of this
“. . . However, this court should not exercise its independent discretion to direct a new trial in every instance where we would be compelled to find no abuse of discretion on the part of the trial court in attempting to direct a new trial in the interest of justice, but in which the order is found to be defective for noncompliance with sec. 270.49(2). Our discretionary power in this respect should be sparingly employed, and ought not to be invoked except in a situation where we are convinced that there has been a probable miscarriage of justice if the jury’s verdict were permitted to stand. . . .” Id. at 270-71.
This principle is equally applicable where, as here, the court reviews the record to determine whether to direct a judgment where the trial court has lost competency to exercise its jurisdiction to rule on motions challenging the sufficiency of the evidence. With these rules in mind, we review the record to determine whether there will be a probable miscarriage of justice if the construe
The court of appeals held that the contract language in unambiguous terms required Jansen to excavate and fill the swale. If correct, this holding would require that the contrary jury verdict be set aside and that judgment be granted to MATC on its counterclaim, because a judgment entered on the verdict otherwise would create a miscarriage of justice.
Construction of the Contract
It is well established that absent ambiguity requiring resort to extrinsic evidence, the construction of a written contract presents a question of law solely for the court’s determination.
Pleasure Time, Inc. v. Kuss,
“We suppose there can be no doubt that it was the duty of the county court to construe this written agreement, instead of leaving the question as to its proper construction to the jury.” Id. at 300.
Similarly, we held in
Douglas v. Johnson,
“As we view the record in this case, we are satisfied that the question should have been resolved by the court as a matter of law, primarily upon the terms and language of the contract as incorporated therein. It is difficult to see that a jury’s determination would be helpful in the resolution of this question.” Id. at 537.
We agree with the holding of the appellate court that the terms of the contract are unambiguous and thus Jan
In addition to these express provisions, the Instructions to Bidders, which are part of the contract, required Jansen to examine all drawings to determine the work covered in his contract as he would be required to do all the work “shown on the drawings, specified in the contract or reasonably implied as necessary.”
12
The instructions also required the bidder to visit the site to compare specifications with work in place and Jansen complied with the instruction and visited the site to compare the work completed as of that date with the contract
When MATC allowed Jansen to substitute the materials used as fill in the building area, they became entitled to a reduction in the contract sum under the General Conditions of the Contract for Construction, Article 13.3.1. Jansen’s bid was required to, and did, set out unit prices for these different materials to be used in calculating the credit due MATC on the contract price. The amount of $17,910.75 is the correct amount of the credit due MATC based upon the bid figures.
Our holding that the contractual provisions involved in this case are unambiguous compels the conclusion that the matter should not have been submitted to the jury under the circumstances although it was appropriate for the trial judge to have heard testimony with respect to the meaning of the terms used in the contract.
We hold that under the unambiguous terms of the contract, Jansen was obligated to excavate and fill the swale
By the Court. — The decision of the court of appeals is reversed, the judgment and order of the circuit court are reversed and cause remanded for entry of judgment in accordance with this opinion.
Notes
Sec. 2210(6) (A) states in part as follows:
“A. Prior to any grading operations, this Contractor shall strip topsoil, if any, to its entire depth or max. of 18" for all areas except building area. At building area and for distance of 5-0" beyond strip topsoil to its entire depth. . . .”
Sec. 805.16, Stats., provides in part as follows:
“Time for motions after verdict. Upon rendition of verdict, the judge shall in open court set dates for serving and filing motions and briefs and for arguing motions. No notice of motion need be served for motions after verdict. The dates for hearing arguments on motions shall be not less than 10 nor more than 60 days after verdict. If an order granting or denying a motion challenging the sufficiency of evidence or for a new trial is not entered within 90 days after verdict, the motion shall be deemed denied. . . .”
It should be noted that sec. 801.15(2) (b), Stats., allows this •time period to be extended for good cause if the order extending the time period is made prior to the expiration of the initial decision period. In this ease, the court did not enter such an order extending the time period.
See. 805.14, Stats., provides in part as follows:
“Motions challenging sufficiency of evidence; motions after verdict.
“(3) Motion at close op plaintiff’s evidence. At the close of plaintiff’s evidence in trials to the jury, any defendant may move for dismissal on the ground of insufficiency of evidence. If the court determines that the defendant is entitled to dismissal, the court shall state with particularity on the record or in its order of dismissal the grounds upon which the dismissal was granted and shall render judgment against the plaintiff.
“(4) Motion at close op all evidence. In trials to the jury, at the close of all evidence, any party may challenge the sufficiency of the evidence as a matter of law by moving for directedverdict or dismissal or by moving the court to find as a matter of law upon any claim or defense or upon any element or ground thereof.
“(5)
‘ (d) Motion for directed verdict. A party who has made a motion for directed verdict or dismissal on which the court has not ruled pending return of the verdict may renew the motion after verdict. In the event the motion is granted, the court may enter judgment in accordance with the motion.”
Jos. P. Jansen Company, Inc. v. Milwaukee Area District Board of Vocational, Technical and Adult Education, Unpublished Opinion (Ct. App.) December 19, 1980, Slip Op. at 3.
Sec. 270.49(1), Stats. 1973, reads as follows:
“Motion for new trial. (1) A party may move to set aside a verdict and for a new trial because of errors in the trial or because the verdict is contrary to law or to the evidence, or for excessive or inadequate damages or in the interest of justice; but such motion must be made and heard within 2 months after the verdict is rendered, unless the court by order made before its expiration extends such time for cause. Such motion, if not decided within the time allowed therefor, shall be deemed overruled.In case judgment is entered without deciding a pending motion for a new trial, the supreme court may direct the trial court to determine such motion within 2 months after filing the remittitur in the trial court.
Judicial Council Committee’s Note to sec. 805.16, Stats.
The use of the phrase “lost competency to exercise Jurisdiction” is more grammatically correct than the former use of the phrase “lost jurisdiction” as under the provisions of sec. 801.04, Stats., it is now clear that “nothing in chs. 801 to 849 affects the subject matter jurisdiction of any court. . . .” Thus, the 90-day time limit of sec. 805.16 more accurately deprives the court of the competency to exercise its discretion.
Section 2200(4) (B) reads as follows:
“Balance of required excavation shall be done under this Section.”
Section 2200(3) (A) reads as follows:
“Clearing and stripping of topsoil within grading limit line was done under Section 2210. Clearing and stripping of topsoil as specified in 2C above shall be done under this Contract.”
Section 2210(6) (A) reads as follows:
“Prior to any grading operations, this Contractor shall strip topsoil, if any, to its entire depth or max. of 18" for all areas except building area. At building area and for distance of 5'-0" beyond strip topsoil to its entire depth. Stockpile topsoil where directed and protect from instrusion of foreign matter. Maintain topsoil relatively free of weeds. Use weed killer as required.”
Sections 2200(8) (B) & (C) and 9(A) & (B) read as follows:
“(B) All topsoil has been removed and building excavated to 1-0" below floor slab under Section 2210. Compaction to within 5'-0" of building was done under Section 2210.
“(C) Compaction required where fill of 2'-0" or more is required within building for distance 5'-0" outside of building lines and for compacted areas at building disturbed by construction. Fill required shall be gravel as specified herein.
“(A) Do all filling and backfilling and grading to area outside of building to required subgrade. Grades indicated on drawings are finished grades. Allow 5" for topsoil and one inch for lawns to be placed under Lawns Contract. See drawings for other sub-grades. Provide extra material for backfill if required.
“(B) The placing and compaction of fill under slabs after foundation walls are in place shall be coordinated with the back-filling against the outside of the walls. Place backfill around walls in horizontal layer max. of I'-O" deep and compact as required to prevent after settlement.
“1. Deposit Select Fill on each side of piers, walls and free standing structure simultaneously to approx, same elevation. Make proper provisions to prevent wedging action against structure. Deposit so that walls filled on both sides will not have differential greater than 1 — 0" between levels on each side.”
Section 2154(2) (A) reads as follows:
“Each bidder shall read Instructions to Bidders, Conditions of Contract, General Requirements, and Specifications, all of which are part of the Project Manual and contain provisions applicable to successful bidder. He shall also examine all drawings, as successful bidder will be required to do all work belonging to his Contract, which is either shown on drawings, mentioned in his specifications, or reasonably implied as necessary to complete his contract.”
Section 2154(2) (C) reads as follows:
“Unless otherwise specifically mentioned in various Sections of the Specifications, base bids upon assumption that work will be performed during regular working hours. Owner requests firm lump sum Base Bid for work contemplated and as covered by these specifications and accompanying drawings.”