111 Cal. 286 | Cal. | 1896
Action to foreclose subcontractors’ liens. Pending the litigation the claim of Joost Brothers was
Eugene Sullivan was the owner, and his wife, Kate Sullivan, was made a party, the complaint alleging that she claimed some interest in the property. Eugene Sullivan died before the trial, and Kate Sullivan, having been duly appointed administratrix of his estate, was substituted, as such administratrix, in his stead; and as such, and as an individual, has taken this appeal.
A contract was made by Eugene Sullivan with one Westcott to raise, make alterations, additions, and repairs to a two-story frame building upon a lot situate at No. 625 Natoma street, city of San Francisco. Plaintiffs alleged that neither said contract nor any memorandum thereof was ever filed in the recorder’s office; “that said building was completed on or about the fourteenth day of October, 1891, and further alleged the filing of their respective liens before the expiration of thirty days from and after the completion of the building.”
The answer denied each of these allegations, and alleged that the building was completed on October 10, 3891. Bayreuther’s notice of lien was filed November 11,1891, and Byron’s on November 12th; and, therefore, if the building was completed on October 10th, both claims were filed too late.
The court found that neither the contract nor any memorandum thereof was filed, and that the building was completed bn October 14th, and appellant contends that these findings are not justified by the evidence.
Byron’s subcontract was for the brickwork, for which he was to receive two hundred and thirty-five dollars, and his work was finished September 24, 1891. He testified that he was at the house (the building in question) on October 14th; that it was then completed; that he did not know how long before that it had been completed; that he could not say when, prior to October 14bh, was,
Mr. Bayreuther testified that he furnished the material for four closets, two bathtubs, the kitchen sinks, etc., that he furnished the materials and completed the work which included all the plumbing in the building according to the specifications, and did some extra work which consisted of tinning in gutters and one extra gas-fitting in the two lower flats, and that he completed his work on October 3d; that he saw the building on October lltli and 14th; that the contractor took his tools away on the 14th; that he was called there on Sunday morning, October 11th, by Miss Sullivan because one of the closets in the building made a rattling noise, and he sent a man there on the 12th to repair it; that he went the next day to see if everything was all right, and saw the contractor moving his tools away; that “ the building was completed that day. The alterations consisted of raising an old house, making three flats of it—two upper and one lower flat. The defendants were living at that time in the upper flat.” He further testified that when he called there Sunday -morning, October 11th, there was a doorknob not on in the upper flat, and a rim to a bath on the lower flat had not been put on, and did not "observe anything else unfinished; that putting on the doorknob and rim of the bathtub was not his work; that the closet was not broken, but made a noise; that he had an agreement that in case anything was wrong with the closets lie would repair them- and make them in good order, and that he formed the conclusion that the building was completed on the 14th from what others told him, and from seeing the contractor moving his tools away. Mr. Westcott, the contractor, was not subpoenaed by the plaintiffs, and was not at the trial.
M. J. Welch, the architect in charge "of the work, was called by plaintiff and testified as to other matters, but was not examined as to the date of the completion of the work, and plaintiffs thereupon rested.
Miss Ella Sullivan testified that she was living with her parents in the house when she sent for Mr. Bayreuther on October 11th; that Westcott was there when Bayreuther called; that the house was then completed and the men had all gone away except Westcott; that they were then living on the upper floor; that the locks mentioned rvere on the old work and not on the new; and that Westcott did not take his tools away until the 14th because he was waiting for someone to lend him a horse and wagon for that purpose.
Mrs. Kate Sullivan, one of the defendants, testified that the house was completed before Bayreuther was called to fix the closet, and she was then occupjdng the upper floor, and the ground floor was also rented and occupied. Upon cross-examination she testified that it was completed a week before Bayreuther called, but .afterward changed the time to a week, or maybe more, before she paid the third payment, which was on October 15th. The foregoing is. the substance of all the evidence relating to the date at which the building was completed.
The finding that the date of completion was October
Hot only so, but the building was actually occupied by the owner and by a tenant before the 11th, and this was evidence of the completion of the work under Westcott’s contract, and its acceptance by the owner, which is conclusive upon the plaintiffs, when not explained, and would also, under the like condition, have been conclusive upon the owner if necessary to sustain the plaintiffs’ liens filed upon the strength of such occupancy. (Giant Powder Co. v. San Diego Flume Co., 78 Cal. 196.) If it be conceded that the contract between the owner and Westcoit were void because not recorded, it would, nevertheless, furnish a test of completion. (Barker v. Doherty, 97 Cal. 10, 12.) If, however, it had been shown that notwithstanding the trivial character of the uncompleted work described by Bayreuther, that work actually continued thereon and was completed on the 14th, the finding would have been sustained.
Appellants also contend that the third finding to the-effect that neither the contract between the owner and
A memorandum of the contract was filed, and the only question is as to its sufficiency. The memorandum having been put in evidence, the finding should have set it out, leaving its sufficiency to be found as a conclusion of law.
It is contended by respondents that it is insufficient in that it was not signed; that neither plans nor specifications, nor their equivalent, were filed, and that it does not show the general character of the work.
So much of the memorandum as is material to the objections made is as follows: “Know all men by these presents: That a contract has been entered into for raising, making alterations, additions, and repairs to the two-story frame-house building to be used for tenements, situate, etc. [describing the lot]. That the names of all parties to said contract are as follows: Eugene Sullivan and 0. W. Westcott. That the following is a statement of the general character of the work to be done under said contract, to wit, raising, making alterations, additions, and repairs to a two-story frame building to be used for two tenements, situated as above stated, and prosecuted under the direction of M. J. Welch, architect.” Then follows a perfect statement of the total amount to be paid, the amount of each of the partial payments, and when they are to be made, and attached thereto was a bond executed by two sureties that Westcott would perform his contract.
That part of section 1183, necessary to be considered, is as follows: “All such contracts shall be in writing Avhen the amount agreed to be paid thereunder exceeds one thousand dollars, and shall be subscribed by the parties thereto, and the said contract, or a memorandum thereof, setting forth the names of all the parties to the contract, a description of the property to be affected thereby, together with a statement of the general character of the work to be done, the total amount to be paid thereunder, and the amounts of all partial pay-
It is not necessary that the memorandum should have been signed or subscribed by the parties. The statute requires that the contract “shall be subscribed by the parties thereto,” but only requires that the memorandum shall “set forth the names of all the parties to the contract.” The names of the parties are stated, and it further stated that they are all the parties to the contract. This follows the statute and is sufficient in that respect.
It is said, however, that neither plans nor specifications were filed. The memorandum does not disclose that there were any, and therefore this case is distinguishable from the cases where the memorandum was held insufficient because plans and specifications were referred to as part of the statement of the general character of the work to be done, and yet were not filed with the memorandum in which the reference was made. This was the case in Willamette etc. Co. v. Los Angeles College Co., 94 Cal. 235, 236, and in Butterworth v. Levy, 104 Cal. 509, and in Wood v. Oakland etc. Transit Co., 107 Cal. 503. The question, therefore, is whether the memorandum states “ the general character of the work to be done.”
If the statute had omitted the words last above quoted, and had simply said that the contract, or a memorandum of it, should be filed, it would have been understood that the word “memorandum” ex vi termini implied that it need not contain a full and particular statement of the contract. Webster defines it thus: “(Law.) A brief note in writing of some transaction, or an outline of some intended instrument; an instrument drawn up in brief and compendious form.”
Before the amendment of 1887 the statute imperatively required that the “contract he filed”; and as the plans and specifications—-whenever referred to, at
The words “ general character ” do not mean a special, particular, minute, or detailed description of the work to be done. The adjective “ general,” as defined in Webster’s Dictionary, means: “1. Relating to a genus or kind; pertaining to a whole class or order; belonging to a whole rather than to a part; .... 3. Hot restrained or limited to a precise or detailed import; not specific; lax in signification”; and of the noun “ character ” he gives, as applicable here, “ 9. Account; description.”
The definition given of the word “ general” in Black’s Law Dictionary, so far as pertinent, is: “ Universal, not particularized; as opposed to special.” The same author defines the word “ character ” only as applied to individuals, but it is nevertheless pertinent here. "The aggregate of the moral qualities which belong to and distinguish an individual person; the general result of one’s distinguishing attributes.”
Other cases are cited by respondent where the memorandum was held insufficient because it did not state for what purpose the building was intended; or did not state the kind of building, as “ frame ” or “ brick ” or “ stone.”
Here the size of the lot, twenty-five by seventy-five feet, is given, that a frame building already thereon is to be raised, repaired, and additions made thereto, and converted into flats for the purpose of being used as tenements. This is quite sufficient as a statement of the general character of the work to be done.” It is not claimed that the memorandum was fraudulently
The statute, imposing as it does a liability upon the owner beyond the price he contracted to pay, in favor of a subcontractor with whom he has no contract relations, is penal as well as remedial, and, therefore, whilst it must have such construction as will reasonably effectuate its remedial purposes, must be strictly confined to such purpose. No merely technical construction can be indulged for the purpose of visiting a penalty upon the owner, unless there has been a substantial failure to comply with the law; such as, if continued, would defeat the remedial purposes of the statute; but if there be a reasonable doubt as to the construction of the statute, or as to whether the defendants complied with it, they should have the benefit of it. (Sutherland on Statutory Construction, 444; Chase v. New York Cent. Ry., 26 N. Y. .523, 525; Shanklin v. Gray, ante, p. 88. The memorandum in this case was a substantial and sufficient compliance with the statute.
As the case must be remanded one or two other questions should be noticed. Appellant claims that there was no evidence of the reasonable value of the work done by the plaintiffs. As the memorandum of the contract between Westcott and the owner is sufficient, the contracts between the contractor and the subcontractors are conclusive, both" as to their principal contracts and as to contracts for extra work, so far as they fixed the value. Where the value was not fixed by contract other proof of value must be made. To prevent misapprehension it may be added that, if the memorandum filed was not in compliance with the statute, the contract price agreed by the contractor to be paid to the subcontractors is evidence of value, but such evidence may be rebutted. (See Booth v. Pendola,
No other questions discussed by counsel need be noticed.
The judgment and order appealed from should be reversed and the cause remanded for a new trial.
Vanclief, C., and Britt, C., concurred.
For the reasons given in the foregoing opinion, the judgment and order appealed from are reversed and a new trial granted.
Temple, J., Henshaw, J., McFarland, J.