On 4 October 1999, defendant J.H. Batten, Inc. (Batten) entered into a contract (the construction contract) with plaintiff Jonesboro United Methodist Church (JUMC) whereby Batten agreed to act as general contractor for the construction of a Fellowship Hall addition on real property owned by JUMC in Sanford, North Carolina. According to allegations in JUMC’s complaint, JUMC had concerns about Batten’s workmanship throughout the construction project. Instances of Batten’s allegedly poor workmanship included problems relating to the alignment and ventilation of the roof, the puckering of roof shingles, defects in the mortar joints and masonry work, mislocated purlins, missing insulation, and other matters. During and after construction, disputes arose between JUMC and Batten concerning both parties’ respective performances under the contract. The disputes centered around the balance owed for work performed, the completion of punch list items, and whether Batten was required to perform additional work under the terms of the contract or in satisfaction of warranties. The parties entered mediation in an effort to resolve these disputes.
On 6 August 2001, representatives of JUMC sent Batten a letter by facsimile transmission confirming a prior telephone agreement in which JUMC agreed to pay $101,000.00 to “satisfy the construction relationship” between JUMC and Batten. The letter thanked Batten for its “willingness to help us settle this todаy” and invited Batten to indicate its approval of the settlement agreement by signing and returning the letter by facsimile transmission. That same day, Batten’s managing agent, Harold Batten, signed the letter and returned it as requested to JUMC. At the bottom of the page, Batten wrote, “I agree that this is a
On 14 August 2001, JUMC sent Batten another letter by facsimile transmission. The second letter stated that upon further review, JUMC “disagree[d] on the amount of payment outstanding.” On this basis, the letter purported to “rescind[]” the 6 August 2001 settlement offer.
After JUMC refused to pay the amount specified in the 6 August 2001 letter, Batten filed suit in Forsyth County Superior Court on 16 August 2001, seeking $101,000.00 in damages in satisfaction of the settlement agreement. In the event the trial court determined there was not a binding settlement agreement, Batten sought a declaratory judgment “to declare the relative rights and obligations between the parties pursuant to the Contract.” In its answer, JUMC denied that a binding settlement existed and moved to dismiss, to change venue, and to stay the proceeding pending arbitration. JUMC further asserted numerous affirmative defenses, including unclean hands, anticipatory breach, and estoppel based on Batten’s alleged failure to perform under the contract. JUMC did not file any counterclaims in the action. After some discovery, Batten filed a motion for summary judgment, which the trial court allowed on 6 February 2002.
JUMC appealed, and the Court of Appeals affirmed in an unpublished opinion filed 17 June 2003. The Court of Apрeals concluded that the parties had entered a binding settlement contract and that no genuine issues of material fact remained to be litigated. JUMC filed a
petition for discretionary review, which this Court denied on 21 August 2003.
J.H. Batten, Inc. v. Jonesboro United Methodist Church,
On 23 April 2002, less than three months after the trial court entered summary judgment in Batten’s favor in the Forsyth County litigation, JUMC filed a complaint in Lee County. The cоmplaint stated three claims against Batten: breach of contract, breach of express and implied warranty, and “Negligence/Malpractice.” Batten filed its answer on 7 June 2002. On 3 July 2002 and 30 July 2002, Batten filed motions for judgment on the pleadings, which asked the trial court to dismiss JUMC’s claims against Batten because those claims “ar[o]se from the same transaction or occurrence that was the subject of litigation between the parties in Forsyth County.” The trial court denied the motions on 30 August 2002, and Batten appealed. The Court of Appeals affirmed in an unpublished opinion. We reverse.
Rule 13(a) of the North Carolina Rules of Civil Procedure designates certain claims as “compulsory counterclaims” that must be raisеd in responsive pleadings. Specifically, Rule 13(a) provides that
[a] pleading shall state as a counterclaim any claim which at the time of serving the pleading the pleader has against any opposing party, if it arises out of the transaction or occurrence that is the subject matter of the opposing party’s claim and does not require for its adjudication the presence of third parties of whom the court cannot acquire jurisdiction.
N.C.G.S. § 1A-1, N.C. R. Civ. P. 13(a) (2003). A claim is not a compulsory counterclaim, however, if
(1) At the time the action was commenced the claim was the subject of another pending action, or
(2) The opposing party brought suit upon his claim by attachment or other proсess by which the court did not acquire jurisdiction to render a personal judgment on that claim, and the pleader is not stating any counterclaim under this rule.
Id.; see also N.C. R. Civ. P. 13(a) cmt.
As we have previously noted, the ultimate effect of a pleader’s failure to assert a compulsory counterclaim is not set forth in the rule itself.
See Gardner v. Gardner,
At the outset, we acknowledge that the compulsory counterclaim rule applies only to claims that are mature at the time the responsive pleading is filed.
See
N.C. R. Civ. P. 13(a) (stating that the rule applies to claims a party “has” against an opposing party “at the time of serving the [responsive] pleading”);
see also Country Club of Johnston Cty., Inc. v. United States Fid. & Guar. Co.,
In its аnswer to Batten’s Forsyth County complaint, JUMC admitted Batten’s factual allegation that “[cjertain disputes [had] ar[isen] between Batten and JUMC. regarding Batten’s and JUMC’s performance of the [construction] [c]ontract.” In addition, JUMC set forth three affirmative defenses that expressly relied upon Batten’s alleged noncompliance with the terms of that contract. Specifically, JUMC alleged that Batten (1) had “unclean hands with regard to its performance under [the construction contract],” (2) was “estopped from seeking damages ... as [Batten] ha[d] not fully performed under its subcontract with [JUMC],” and (3) was “not entitled to recovery of any amounts owed by [JUMC]” due to “[Batten’s] anticipatory breach of the contract.” Similarly, in its Briеf in Opposition to Plaintiff’s Motion for Summary Judgment in the Forsyth County action, JUMC alleged that in addition to the dispute over the balance owed on the construction contract, “there were unresolved issues such as additional items of work to be performed under the [construction] contract, warranty work, and punch lists.” Thus, JUMC’s pleadings in the Forsyth County action demonstrate that JUMC was aware of the factual basis for its Lee County claims at the time it filed its responsive pleadings during the Forsyth County litigation.
Moreover, in its Lee County complaint, JUMC alleged that as early as 5 December 2000, more than
eight months prior
to the initiation of the Forsyth County action, it provided the architect supervising the construction project with “a copy of a prеliminary independent report identifying many
We next turn to the question of whether JUMC’s claims against Batten in the Lee County litigation “arise[] out of the transaction or occurrence that is the subject matter of’ Batten’s claims against JUMC in the Forsyth County litigation. There is no simple test to determine when a claim “arise [s] out of the transaction or occurrence that is the subject matter of the opposing party’s claim” for purposes of Rule 13(a). 1 G. Gray Wilson,
North Carolina Civil Procedure
§ 13-3, at 259 (2d ed. 1995). As the United States Supreme Court stated in interpreting a predecessor to the modem federal compulsory counterclaim rule, “
‘[transaction’
is a word of flexible meaning. It mаy comprehend a series of many occurrences, depending not so much upon the immediateness of their connection as upon their
logical relationship.” Moore v. N.Y. Cotton Exchange,
North Carolina’s compulsory counterclaim mle is identical to its federal counterpart.
Compare
Fed. R. Civ. P. 13(a) (2005)
with
N.C. R. Civ. P. 13(a). Not surprisingly, therefore, our Court of Appeals has looked to the federal courts for guidance in applying Rule 13(a). In
Curlings v. Macemore,
the Court of Appeals adopted the three-pronged analytical framework employed by the United States Court of Appeals for the Fourth Circuit and other federal courts.
Applying the Curlings factors, Batten’s claims in the Forsyth County litigation and JUMC’s claims in the Lee County litigation all raised legal issues arising out of the common factual background of the construction contract and the construction project. Moreover, both sets of claims depended in large part on evidence of the parties’ respective conduct throughout the construction relationship. Finally, the claims are “logically related” in that they all concern the parties’ respective performances under the construction contract and their corresponding liabilities under the construction and settlement contracts.
JUMC argues, however, that its claims against Batten cannot be compulsory counterclaims with respect to either of the clаims asserted in Batten’s Forsyth County complaint. First, JUMC contends that Batten’s claim seeking enforcement of the settlement agreement
and JUMC’s claims for damages based on breach of the construction contract, breach of warranties, and negligent construction “involve consideration of different facts and different legal principles.” While there is some truth to this contention, Rule 13(a) “does not require that the legal claims be identical. It is sufficient that the nature of the actions and the remedies sought are logically related in fact and law.”
Brooks,
Second, JUMC argues that its claims against Batten cannot bе compulsory counterclaims with respect to Batten’s declaratory judgment action because the trial court never reached final judgment on the latter claim. To be sure, a claim cannot be barred by
res judicata
or collateral estoppel unless it was litigated to final judgment in a prior action.
Thomas M. McInnis & Assocs. v. Hall,
In conclusion, the construction contract and the parties’ performance under that contract constitute a single “transaction or occurrence” that formed the factual basis for the parties’ respective claims for relief in both the Forsyth County and Lee County
The decision of the Court of Appeals is reversed, and the case is remanded to that court for further remand to the Lee County Superior Court for further proceedings consistent with this opinion.
REVERSED AND REMANDED.
