28 Mass. App. Ct. 77 | Mass. App. Ct. | 1989
Donald Jones and Anthony Tokowicz were hurt when a steel beam on which they were sitting gave way during construction of a film processing plant for the Polaroid
During the course of the trial, Vappi moved for summary judgment on the ground that it was the beneficiary of an indemnity obligation which it had imposed on General Iron in their subcontract. Vappi, as it construed the scope of the indemnity clause, would not be bound to pay damages to the plaintiffs in any event. The trial judge decided that question in favor of Vappi. Against the possibility that he might be mistaken on the indemnity issue, the judge astutely refrained from entering a judgment and kept Vappi in the case so that, should the indemnity point come out differently on appeal, the case would not have to be retried.
Before the case went to the jury, General Iron settled with all the plaintiffs
We turn now to the disputed language, which appears in Article III (10) of the subcontract between Vappi and General Iron. So far as pertinent, General Iron agreed:
*79 “To indemnify and save the Contractor [Vappi] . . . harmless from and against any and all costs, loss, expense, liability, damages, or claims for damages arising or resulting from any work of the Subcontractor [General Iron], including attorney’s fees, expenses and costs of defending any action on account of any injury or damage to property or persons, or on account of any other action against the Contractor . . . for any liability . . . arising out of any work performed by or required from the Subcontractor and on account of any injury (including death) to any persons or property arising or resulting from the Work provided for or performed by the Subcontractor . . . .”
1. Scope of the indemnity clause. General Iron attempts to elude the reach of the indemnity provision by arguing, first, that the indemnity clause does not apply because inadequate safety measures caused the accident and, under the contract, supervision and safety were not included in General Iron’s work. It is an unpersuasive argument in light of the opinions in Shea v Bay State Gas Co., 383 Mass. 218 (1981); Whittle v Pagani Bros. Constr. Co., 383 Mass. 796, 798-799 (1981); Aho v. Blanchette, 18 Mass. App. Ct. 149, 151-152 (1984); and Speers v. H.P. Hood, Inc., 22 Mass. App. Ct. 598 (1986). Those cases emphasize that indemnity provisions are not to be read grudgingly against the indemnitee but “like any ordinary contract, with attention to language, background and purpose.” Id. at 600.
As to language, so far from excluding supervision, the definition of the scope of the work in Article I of the subcontract expressly calls upon the subcontractor to furnish “all things necessary to complete all work . . . including . . . supervision . . . ,” and Article 111(7) requires General Iron to comply with safety requirements in the general contract documents and to require similar compliance of its agents,
Against the background of a moderately large construction project, it is unremarkable for a general contractor to shift to a subcontractor responsibility for claims connected to. that subcontractor’s work. See Speers v. H.P. Hood, Inc., 22 Mass. App. Ct. at 601. The risk so allocated becomes the subject of insurance which the subcontractor, under Article VI of the subcontract, is required to carry. Compare id. At bottom, the purpose of the indemnity clause is to distribute among the subcontractors and suppliers insurance burdens covering their respective areas of responsibility. Recognition of that purpose reinforces reading the language of the contract for what it says, rather than for what it omits. Contrast Bendetson v. Coolidge, 7 Mass. App. Ct. 798, 801 (1979).
In a variation on its theme of limiting the scope of the indemnity clause, General Iron argues that the failure of the clause to state expressly that the subcontractor must indemnify Vappi even when it, as general contractor, is concurrently negligent
2. Application of G. L. c. 149, § 29C. There is not even surface merit to the argument that the indemnity clause is invalid by reason of G. L. c. 149, § 29C. In its first form, § 29C was inserted by St. 1984, c. 484, § 43. The subcontract between Vappi and General Iron was executed December 19, 1978, five years before the legislation was passed.
General Iron wishes to invoke G. L. c. 149, § 29C, because, in its 1984 form, § 29C declared indemnity clauses in construction contracts which absolved indemnitees from their own negligence to be “against the public policy and . . . void and unenforceable.” A substantial revision of § 29C was made soon thereafter by St. 1985, c. 228, § 3. Section 4 of the 1985 act made the amendment retroactively effective as of April 7, 1985, the effective date of the 1984 act. The later version of § 29C was, therefore, a total substitution for the original. It is less sweeping and declares void indemnity provisions in construction contracts only when the
3. The indemnitee’s counsel fees. As part of its indemnity claim, Vappi was entitled to recovery of reasonable counsel fees and legal costs incurred in defending the claim. Amoco Oil Co. v. Buckley Heating, Inc., 22 Mass. App. Ct. 973 (1986), and cases cited. It was open to Vappi to pursue those legal expenses as, part of a separate indemnity action brought after completion of the negligence action. See, e.g., New England Merchants Natl. Bank v. Latshaw, 12 Mass. App. Ct. 150, 152-153 (1981); Wolverine Ins. Co. v. Tower Iron Works, Inc., 370 F.2d 700, 703 (1st Cir. 1966). As an alternative, Vappi could assert its claim to indemnification as a cross claim within the negligence action. See Mass.R.Civ.P. 13(g), 365 Mass. 759 (1974); Lusk v. Pennzoil United, Inc., 56 F.R.D. 645, 647-648 (N.D. Miss. 1972). That is the course Vappi chose.
Through the close of the evidence, however, Vappi offered no evidence and, indeed, made no mention of the legal fees component of its cross claim in a pretrial memorandum. There were some understandable reasons for keeping the legal expenses issue on the back burner. At the beginning of the trial, considerable expense had yet to be run up and an estimate might have been seriously inaccurate. After the trial judge had decided the indemnity question on Vappi’s motion for summary judgment, he ordered counsel not to refer to the indemnity issue in front of the jury, and that acted as a further inhibition to touching on the subject.
On June 17, 1986, there occurred a lobby conference at which counsel for the plaintiffs and for General Iron described the general terms of a settlement hammered out by them the previous evening, namely the $1,000,000 settlement previously adverted to. There ensued a discussion among the judge and counsel for all parties in the case at which they considered: (1) the terms of the $1,000,000 settlement; (2)
On June 18, 1986, the next day, Vappi and Polaroid, which were represented by the same counsel, moved for leave to present to the judge, jury-waived, evidence of fees and costs attendant upon their defense. Their motion was denied.
Whether to admit additional evidence after a party has rested lies within the sound discretion of the trial judge. Kerr v. Palmieri, 325 Mass. 554, 557 (1950). Duchesneau v. Jaskoviak, 360 Mass. 730, 734 (1972). Dominick v. Dominick, 18 Mass. App. Ct. 85, 90 (1984). The judge, in a memorandum he filed about posttrial matters, recognized that the discretion to admit additional evidence after the evidence has formally closed may be indulgently exercised to remedy an oversight discovered shortly thereafter, before parties have changed position and before the case has gone to a next phase. In his memorandum the judge observed that between the end of the lobby conference and the presentation of the Vappi-Polaroid motion there had occurred “a major restructuring of the positions of several parties.” General Iron, for example, may have chosen not to settle for $1,000,000 had it been placed on notice that further exposure loomed.
Judgments affirmed.
The $1,000,000 settlement was allocated one-half to Jones and his wife and one-half to Tokowicz. Ganteaume & McMullen, Inc., which provided architectural and engineering services for the job, placed an additional $230,000 in the settlement pot. That amount was similarly apportioned.
V&V did not defend and a default judgment was entered against it conformably with Mass.R.Civ.P. 55(a) & (b)(1), 365 Mass. 822 (1974).
As might be expected, the general conditions for construction contracts on the Polaroid job require the contractor to “take all necessary precautions for the safety of employees.” Par. 25(b).
Although the jury found that General Iron had not acted negligently, General Iron could not — and did not — disclaim liability to Vappi for the negligence of V & V, to which General Iron had subcontracted work it was contractually bound to perform for Vappi.
The accident occurred February 20, 1979.
Only Vappi filed a cross appeal from the judgment. Polaroid had the benefit of an indemnity provision running from Vappi.