The judgment should be reversed and a new trial granted, with costs to appellant to abide event.
The action was for negligence. The plaintiff was a conductor on a worktrain, in the general employ of the defendant. At the time of the accident the train was engaged in hauling materials excavated in construction work to a dumping place. The plaintiff as conductor .had charge of the train, and it was moved under his direction. He was standing upon .the platform of a dumping car, and the train was backing up at about eight miles an hour. The engineer, without any signal or direction from the conductor, suddenly stopped the train, threw plaintiff off and one of the wheels of the car passed over his arm. This was claimed as negligence on the ‘part of the engineer and a recovery was had therefor-under the provisions of the Employers" Liability Act (Laws of 1902, chap. 600) and the Barnes Act (Laws of 1906, chap. 657, adding to Railroad Law [Laws of 1890, chap. 565], § 42a). Among other things the defendant claimed these men, the engineer and conductor, were not at the time of the accident the employees of the defendant. The construction work was being done by contractors, and by the terms of the agreement it was provided that the contractors should furnish the cars for handling the materials excavated, and the defendant should furnish the locomotive and train crew to haul the same; that such train crew while in spch service should be considered as the contractors’ employees, and, therefore, the defendant could not be held liable under the Employers’ Liability Act and Barnes Act for the alleged negligence of the engineer.
The court, among other things, submitted to the jury the question as one of fact whether these men were the employees of the
It is claimed by the defendant that under the terms of the agreement the engine and crew of the train in question were in effect hired out by the defendant to the contractors, and in the special employment of hauling and dumping the excavated materials and returning with the empty train these men were under the special direction and control of the contractors. I do not think this can be said as a matter of law. I think the question was very properly submitted to the jury as matter of fact for their determination. There is little evidence tending to support defendant’s contention aside from the clause in the contract that while in the contractors’ service the train crew should be considered as their employees.
It is not claimed the plaintiff had any knowledge of this provision in the contract, and his relations to the defendant could hardly, be affected by a secret provision in a contract between his general employer and a third party. The train was not under the absolute control of the contractors under the various provisions of the contract even; control thereof was largely retained by the defendant. It. was not used to take the cars of materials from the place of excavation to the dumping place. Another train was used to take the cars to the end of the switch next the main track, and the train in question then took the loaded cars to the dumping place and returned the empty ears to the switch again. The manner of protecting and operating this train and the main tracks was under the control of the defendant by the terms of the contract and the verbal directions of the defendant and the actual operation of the train. On this occasion the conductor was told to go and do this
I have carefully examined the late cases decided by the Court of Appeals .cited by the respective counsel. In all of these the facts were distinguishable from those in this case, and I think none of them are controlling in the determination of this case. In the latest one (Sexton v. N. Y. C. & H. R. R. R. Co., 114 App, Div. 678; 189 N. Y. 518) all the cases are considered. I need not discuss them in detail here.
I think the trial court in regarding the question as one of fact for the jury was quite as favorable to the defendant as it should have been. The verdict of the jury upon this question should not have been disregarded and a nonsuit- granted.
The judgment based upon such order must, therefore, be reversed, but under the circumstances we think we should not restore the verdict and direct a judgment thereon in favor of plaintiff, especially as the trial justice did not pass upon the weight of evidence upon the other questions in the case.
All concurred.
Judgment reversed and new trial ordered, with costs to appellant to abide event.