45 S.E. 827 | N.C. | 1903
The features of this case are very much those of Shawv. Etheridge,
If the plaintiffs were entitled to recover for permanent damages they could recover for any act of damage committed prior to 3 October, 1900 (date of summons), and any consequences flowing from such prior act down to the trial, but not for any injuries inflicted subsequent to that date. 2 Sutherland Damages (2 Ed.), sec. 1038. But that is not this case. The locusin quo where the logs were rolled into the canal and the obstruction was caused was not on the plaintiffs' land, and they announced *355 in open court that they did not claim for alleged injuries to the canal as distinguished from the land and crops, and further that they did not claim that there was any injury to the crop of 1900. The only damage shown, therefore, upon the plaintiffs' evidence is ponding water back, sobbing their land, and thereby injuring their land and crops in 1901 and 1902. This ponding back and injury were subsequent to the bringing of the writ, and damages for such injury cannot be recovered in this action. Woods Mayne on Damages, sec. 109. It is true, the plaintiffs claim that the canal was obstructed and made shallower by the defendants' acts prior to the summons, but they admit no damages to them accrued therefrom prior to the writ. Such an obstruction did not necessarily cause the ponding back and water-sobbing the plaintiffs' land and injury to their crops in 1901 and 1902, for the obstruction might have been removed and the canal repaired before any ponding back and injury in 1901. It was the failure to do this, and the consequent ponding back and injury in 1901 and 1902, which is the ground of action. It is (448) immaterial when the obstruction to the canal was made, since the plaintiffs say they do not sue for that. There is no permanent damage to the plaintiffs' land either alleged or shown, for the water-sobbing can be relieved by removing the obstruction and cleaning out the canal so that it can drain the plaintiffs' land as before the obstruction was made.
The amended complaint avers that by reason of the obstruction to the canal complained of, "the waters which would have naturally flowed through the same from the land of the plaintiffs were obstructed and dammed and backed upon the land of the plaintiffs, greatly damaging said land of the plaintiffs, causing said land to be less productive and prevented theproper drainage of the same." This lessened production is admitted not to have occurred in 1900. The obstructed drainage which caused it is an abatable nuisance, as in Shaw v. Etheridge, supra, and the measure of the damage accruing therefrom in 1901 and 1902 is the lessened production — the loss in the crops for these years. Adams v. R. R.,
(449) Aside from this error as to the measure of damages, the court should have further directed a verdict against the plaintiffs because the action was prematurely brought.
Error.
Cited: Lumber Co. v. Lumber Co.,