Jones v. . JuddJones v. . Judd
- Reporters:
- ,
- Before:
- Gardiner
As the plaintiffs were prevented, by the authority of the state, from completing their contract, they are entitled to recover for the work performed, at the contract price. The ten per cent was a part of the price stipulated. It was reserved to secure the fulfilment of the contract, and to be paid upon afinal estimate. The performance of the required condition became impossible by the act of the law, and of course the plaintiffs were entitled to recover without showing a compliance with the agreement in this particular. (Comyn on Cont. 50; 10John. 36.)
Upon the question of damages; I think the offered evidence was properly rejected. If the contract had been performed by the plaintiff, he might have recovered upon the special agreement, or
Again; the plaintiffs assumed the risk of all accidents which might enhance the expense of the work, while the contract was subsisting; (Boyle v. Canal Co. 22 Pick. 384; Sherman v.Mayor of New- York, 1 Comst. 321;) and is entitled, consequently, to the advantages, if any, resulting from them. The suspension of the work, by state authority, was an accident unexpected by either party. It was one which, under the offer, we are bound to assume, was of benefit to the plaintiffs. But the defendant can not require an abatement from the agreed
JEWETT, HURLBUT and PRATT, Js. concurred.
BRONSON, Ch. J., RUGGLES, HARRIS and TAYLOR, Js. were for reversal, on the ground that the evidence offered upon the question of damages was improperly excluded.
Judgment affirmed.