Jones v. GordonJones v. Gordon
The National Marine Fisheries Service (the Service)
I
In March 1983, Sea World, an operator of aquatic zoological parks, applied to the Service for a permit to capture killer whales (Orcinus orea) for purposes of scientific research and public display. The Marine Mammal Protection Act of 1972 (the MMPA),
In its permit application, Sea World requested permission to collect up to 100 killer whales over a five-year period from Alaska and California coastal waters. Up to ten killer whales would be maintained permanently in captivity for research and display, and up to 90 would be held temporarily (no more than three weeks) for research. The numerous scientific tests proposed included liver biopsies, gastric lavages, hearing and respiratory tests, tooth extractions, and blood tests. Sea World also proposed to tag, mark, and attach radio transmitters to killer whales held temporarily.
Pursuant to MMPA § 104(d)(2),
On November 1, 1983, the Service issued a permit to Sea World authorizing the permanent removal of up to 10 killer whales and the temporary capture of up to 90. The. permit imposed several conditions not present in Sea World’s original application. For example, Sea World was required to conduct a study of local killer whale population in Alaska areas and to submit a report to the Service. No captures could be conducted without further authorization by the Service, and the length of temporary captures was restricted. No more than 2% of a local population could be permanently removed over a two-year period, and no more than two animals could be removed from a distinct social group (pod). Killer whales temporarily captured could be recaptured no more than twice. Many of the planned tests also required further authorization by the Service.
On May 1, 1984, Jones sought declaratory and injunctive relief against the Service in federal district court, alleging that the Service’s issuance of the permit without preparation of an environmental impact statement violated the National Environmental Policy Act of 1969 (NEPA),
The Service and Sea World first challenge the district court’s exercise of jurisdiction. They base their challenge on section 104(d)(6) of the MMPA, which provides:
Any applicant for a permit, or any party opposed to such permit, may obtain judicial review of the terms and conditions of any permit issued by the Secretary under this section or of his refusal to issue such a permit. Such review, which shall be pursuant to chapter 7 of Title 5, may be initiated by filing a petition for review in the United States district court for the district wherein the applicant for a permit resides, or has his principal place of business, or in the United States District Court for the District of Columbia, within sixty days after the date on which such permit is issued or denied.
The district court rejected this jurisdictional challenge. The district judge ruled that section 104(d)(6) did not apply to Jones’s action since Jones, rather than disputing the “terms and conditions” of the permit, alleged that the Service had failed to comply with the procedural requirements of NEPA. The district judge further ruled that NEPA itself provided an independent source of jurisdiction for Jones’s action. We review de novo the district court’s determination of subject matter jurisdiction. Clayton v. Republic Airlines, Inc.,
We agree with the district court that section 104(d)(6) does not apply to Jones’s action. Section 104(d)(6) does not purport to govern all challenges to section 104 permits. Rather, as to permits issued, it governs “judicial review of the terms and conditions ” of such permits. MMPA § 104(d)(6),
Jones’s action does not seek review of the terms and conditions of the Service’s permit to Sea World. Jones has instead alleged that the Service, by not preparing an environmental impact statement, has violated the procedural requirements of NEPA. We recognize, of course, that this procedural claim may indirectly implicate some of the terms and conditions of the permit. Nevertheless, we have no difficulty concluding that Jones’s challenge is essentially procedural in character. Because Jones does not seek review of the terms and conditions of the permit, we hold that section 104(d)(6) and its 60-day statute of limitations do not operate to bar Jones’s action.
Because section 104(d)(6) does not provide jurisdiction in this case, we now must determine whether the district court had a different source of jurisdiction to entertain Jones’s action. The district judge found that NEPA itself provided an independent jurisdictional basis. We need not reach that issue because jurisdiction over Jones’s action arose from the combined operation of
Ill
In an argument not joined by the Service, Sea World contends that the requirement of an environmental impact statement under NEPA conflicts irreconcilably with the mandatory time limits for agency action under section 104(d) of the MMPA. Sea World argues that under Flint Ridge Development Co. v. Scenic Rivers Association,
In Flint Ridge, the Supreme Court found a “clear and fundamental conflict of statutory duty” between the Interstate Land Sales Full Disclosure Act (Disclosure Act),
Sea World argues that section 104(d) of the MMPA is in irreconcilable conflict with the environmental impact statement requirement of NEPA. Section 104(d) sets forth certain time limitations for processing of section 104 permit applications. Once the Service publishes notice of a permit application, interested parties have 30 days in which to submit written data or views, MMPA § 104(d)(2),
Reading these provisions together, Sea World argues that section 104(d) requires that the Service grant or deny a permit, at the latest, within 90 days after publication of notice plus the length of any hearing. We assume, for purposes of this appeal, that this reading is correct. Sea World further asserts that the Service requires approximately 360 days to prepare an environmental impact statement. For purposes of this appeal, we also accept this assertion. Sea World concludes that under Flint Ridge the Service is exempt from NEPA when issuing a section 104 permit, since it cannot prepare an environmental impact statement within the period in which it must issue or deny the permit under section 104(d) of the MMPA.
The issue is not without doubt and Sea World’s argument is plausible. Nevertheless, we agree with the district court that the apparent conflict between section 104(d) and NEPA is reconcilable.
The purpose of the new language is to make it clear that each agency of the Federal Government shall comply with the directives set out in ... [Section 102(2) ] unless the existing law applicable to such agency’s operations expressly prohibits or makes full compliance with one of the directives impossible ____ Thus, it is the intent of the conferees that the provision “to the fullest extent possible” shall not be used by any Federal agency as a means of avoiding compliance with the directives set out in section 102____ [N]o agency shall utilize an excessively narrow construction of its existing statutory authorizations to avoid compliance.
115 Cong.Rec. 39703 (1969), quoted in Calvert Cliffs’ Coordinating Committee, Inc. v. United States Atomic Energy Commission,
Such a possible interpretation, argued by Jones, begins with the accurate observation that section 104(d) does not require that notice be published within any particular period. Instead, the Service has the broad authority to “prescribe such procedures as are necessary to carry out this section.” MMPA § 104(d)(1),
Sea World contends, however, that this reading is itself inconsistent with Flint Ridge. In Flint Ridge, the Court encountered the suggestion that the Disclosure Act and NEPA could be reconciled “if the Secretary ordered the developer not to file its statement of record until HUD completed an environmental impact statement.”
We acknowledge that a fine line exists between an interpretation that enables NEPA to be applied “to the fullest extent possible” and a reading that renders the limitation provision in another statute “little more than a nullity.” Id. at 791. The interpretation suggested by Jones, however, neither circumvents the language of the MMPA nor violates its purpose; rather it promotes the predominant congressional
IV
The Service and Sea World next argue that issuance of the Sea World permit by the Service did not require preparation of an environmental impact statement. The district court ruled that an environmental impact statement was required. Federal courts must uphold an agency decision not to prepare an environmental impact statement unless that decision is unreasonable. Foundation for North American Wild Sheep v. United States Department of Agriculture,
To address the argument made by the Service and Sea World, we must first sketch the statutory and regulatory framework that governed the Service’s action. NEPA requires that federal agencies prepare an environmental impact statement for “major Federal actions significantly affecting the quality of the human environment.”
Pursuant to these CEQ regulations, the Administration — the parent agency of the Service — issued Revised Administration Directive 02-10, 45 Fed.Reg. 49312 (1980).
(a) Are likely to result in significant environmental impacts as defined in [40 C.F.R.] Sec. 1508.27, or
(b) Involve a geographic area with unique characteristics, are the subject of public controversy based on potential environmental consequences, have uncertain environmental impacts or unique or unknown risks, establish a precedent or a decision in principle about future proposals, may result in cumulatively significant impacts, or may have any adverse effects upon endangered or threatened species or their habitats.
Id. § 6.c.(7), 45 Fed.Reg. 49316.
The Service and Sea World argue that the issuance of the Sea World permit by
While mindful that we may not substitute our judgment for an agency judgment that is fully informed and well-considered, see Friends of Endangered Species, Inc. v. Jantzen,
Issuance of the permit is not a major Federal action significantly affecting the quality of the human environment; therefore, it has been determined that an Environmental Impact Statement is not necessary in this case. The permit authorizes the removal of ten animals from the wild and the conduct of field research on up to 90 additional animals. Regulations establishing public display and scientific research permit procedures under the MMPA have been in effect since 1974, and over 400 permits involving a take of 586,000 marine mammals have been issued. None have required an EIS and none have been prepared.
The Service did not address the applicability of the Administration directive. In particular, it did not discuss whether an exception to the categorical exclusion for issuance of MMPA permits for scientific research and public display applied.
“An ‘agency cannot ... avoid its statutory responsibilities under NEPA merely by asserting that an activity it wishes to pursue will have an insignificant effect on the environment.’ ” Steamboaters v. FERC,
The Service’s explanation is deficient in that it fails to explain why issuance of the permit does not fall within an exception to the categorical exclusions under section 6.c.(7) of the Administration directive. The elements of section 6.c.(7)(b) are stated in the disjunctive: if any of the elements is present, the Service must prepare an environmental assessment or an environmental. impact statement.
Similarly, the Service’s final report reveals the arguable existence of "uncertain environmental impacts or unique or unknown risks.” The Service report acknowledged the uncertain life expectancy of captive killer whales. It further recognized that the impact of removing killer whales was uncertain since so little is known concerning the size, composition, structure, and productivity of the killer whale populations at issue. It also stated that even temporary removals might affect the reproductive potential of killer whale groups.
The Service argues that the conditions contained in the permit issued to Sea World substantially mitigated any uncertain environmental effects. We agree that conditions mitigating the environmental consequences of an action may justify an agency’s decision not to prepare an environmental impact statement. See id. at 1394. The conditions contained in this permit, however, rather than mitigating environmental consequences, generally operate simply to defer important agency decisions until more information has been obtained. At most, they “provide only general guidelines. Their effectiveness depends on how they are applied and enforced.” Id. Moreover, the Service, in issuing the permit, provided no reasoned explanation — indeed, no explanation at all — of how these conditions would prevent application of an exception to the categorical exclusions.
We conclude, therefore, that the district court did not err in deciding that the Service has unreasonably decided not to prepare an environmental impact statement. We emphasize, however, that we disagree with the district court’s conclusion that the Service must prepare such a statement for the Sea World permit. Rather, the Service must consider the requirements of NEPA and regulations thereunder, and must provide a reasoned explanation of whatever course it elects to pursue.
AFFIRMED IN PART AND REVERSED IN PART.
Notes
. The Service itself is not technically a party to this action. For sake of simplicity, we refer to the Service rather than to its assistant administrator of fisheries, Gordon, who has been sued in his official capacity. The administrator of the National Oceanic and Atmospheric Administration, the Secretary of Commerce, and the Department of Commerce are also defendant-appellants.
. This directive was in effect during the entire period that the Service acted on Sea World’s permit application, but has since been revised.
See Revised Administration Directive Implementing the National Environmental Policy Act, 49 Fed.Reg. 29644 (1984).
. Because the elements of section 6.c.(7)(b) are stated in the disjunctive, we cannot agree with the district court that this action merely restates the CEQ regulation in