249 Pa. 423 | Pa. | 1915
Opinion by
Plaintiff sued in assumpsit for damages resulting from a breach of contract. In the statement of claim the entire contract between the parties, including drawings, specifications, correspondence, requirements, uses, terms and conditions, was fully set forth. What constituted the breach was also averred and the damage resulting as a necessary consequence of that breach was set out in an itemized statement made part of the declaration. The defendants demurred on the following grounds: (1) That the statement of claim did not show a valid cause of action in that the contract relied on to sustain a recovery did not contain a warranty that the defective elbows would stand a pressure of 300 pounds per square inch; (2) that under the contract defendants were not liable for the consequential damages caused by the bursting of the pipe-bends after the same had been accepted and installed by the plaintiff; (3) that under the fact» averred in the declaration defendants are not indebted to the plaintiff in any sum whatever.
The demurrer admitted the facts properly pleaded, and hence we must accept as established, all the rele-' vant facts averred in the statement. The pipe-bends, known as elbows, were a component and necessary part of the entire pumping equipment manufactured and installed by the defendants for a specified use, and this was the basis of the contractual relation of the parties. It is argued for appellants that the express guaranty of the. discharging pipe did not apply to the elbows, which were
The second ground of demurrer states as a fact that which does not appear in the record. It may be conceded that there was no express agreement to pay damages caused by the bursting of the pipe-bends, but no such damages are claimed in this action. In the declaration plaintiff simply seeks to recover the actual expense of taking out the defective elbows and installing the new ones which appellants furnished to take their place. In the facts averred it does not appear that the defective elbows “had been accepted and installed by plaintiff,” or that anything had been done to indicate that the elbows had been tested and finally accepted. Indeed it is expressly averred in the declaration that the bursting of the discharge piping and elbows, “was due entirely to defendants’ failure to supply elbows and annular discharge piping in accordance with the terms of said order and contract, and which defendants undertook to supply to withstand a pressure of 300 pounds to the square inch, as to said elbows, and 250 pounds pressure per square inch as to said annular discharge piping.” There is
We entirely agree with learned counsel for áppéllee that the right to recover damages in this case does not depend upon an express agreement to pay damages. The general rule is that a contracting party is liable for the damages, which are the natural consequences of the breach, where the vendor undertakes to furnish an article for a certain specified use. Our own cases as well as those from other jurisdictions furnish ample authority to support this rule as a measure of damages where the facts warrant its application. See Wade v. Haycock, 25 Pa. 382; Port Carbon Iron Co. v. Groves, 68 Pa. 149; Erie City Iron Works v. Barber, 102 Pa. 156; Smith v. Citizens Gas & Gaseous Fuel Co., 5 W. N. C. 97; Philadelphia & Reading Coal & Iron Co. v. Hoffman, 1 Sadler, 405; Haines v. Young, 13 Pa. Superior Ct. 303; Boston Woven Hose & Rubber Co. v. Kendall, 178 Mass. 232; 35 Cyc. 234.
In the case at bar the expense of taking out the defective elbows and installing the new ones furnished by appellants to take their place was the direct and natural consequence of the breach of the contract. We cannot conceive of any more direct and natural consequence of the breach than the expense incurred in taking out the defective elbows and installing the new ones for the very purpose of completing the pumping equipment according to contract.
The learned court below gave this case , such careful
The first, third, fourth, fifth and sixth assignments of error are not in proper form and need be given no further consideration. All of these assignments are in the language of the pleader, and do not contain the judgment, or decree, or order, or finding, or conclusion of law, about which complaint is made. We have had occasion in several recent cases to call this matter to the attention of counsel so that more care may be exercised in assigning errors for the consideration of this court.
Judgment affirmed.