The Muscatine County Board of Supervisors and the Muscatine City Council created the Veterans’ Plaza Authority (VPA) to acquire a new jail site for the county. See Iowa Code § 346.27 (1991). The VPA notified the plaintiff, Gregory A. Johnston, that it proposed to condemn his land for this purpose. A compensation commission appraised the property. On September 1, 1992, the sheriff mailed to the VPA and Johnston a notice of appraisement of damages and advised them of their right of appeal. See Iowa Code § 472.18 (1991). 1
Dissatisfied with the appraisal, Johnston filed a notice of appeal in the clerk’s office and delivered a notice of appeal to the sheriff with directions for service. The sheriff did not actually serve the notice until October 14, 1992, nearly two weeks after the thirty-day deadline for appeal under section 472.18. The VPA moved to dismiss Johnston’s petition for lack of subject matter jurisdiction based on the late notice. The court sustained the motion, and we affirm.
Iowa Code section 472.18 requires that a party appealing from an appraisement do so within thirty days of the sheriffs mailing of the notice of appraisement and at the same time to give written notice to any adverse parties. We have held that service of notice at the time of the appeal is mandatory and
*132
jurisdictional.
See Wade Farms, Inc. v. City of Weldon,
The notice provisions of section 472.19(2) state:
In any condemnation proceeding instituted under this chapter by the state department of transportation in any court of the state wherein the property owner has delivered proper notice of appeal to the sheriff of the proper county with the intent that it be served immediately ... the delivery of the notice of appeal shall be deemed a commencement of the appeal proceedings.
(Emphasis added.)
Johnston argues that sections 472.18 and 472.19(2) impermissibly create two classes: DOT condemnees, who merely need to deliver notice of the appeal to the sheriff within thirty days, and all other condemnees, who must actually serve the notice within thirty days. 2 Johnston contends that his appeal would have been timely if the DOT was the condemner. He raises both equal protection and due process arguments based on this distinction.
We presume that statutes are constitutional.
Krull v. Thermogas Co.,
At the threshold of any equal protection or due process analysis, of course, is the determination of the type of scrutiny to be applied.
Glowacki v. State Bd. of Medical Examiners,
We need not decide whether strict scrutiny is the proper test. While Johnston raised an argument for strict scrutiny in his reply brief, this was too late.
See Young v. Gregg,
The VPA suggests that the reason for this distinction might have been a practical one— the difficulty in locating and serving the proper recipients for service on DOT con-demnees, due to their broader geographic dispersion in many cases. Johnston does not rebut this possible basis for the distinction, nor does he attempt to negate any other rational basis for the distinction. Because the burden is on him to rebut the presumption of constitutionality, his constitutional argument must fail. We therefore affirm the dismissal.
AFFIRMED.
Notes
. Chapter 472 is now renumbered as chapter 6B.
. Johnston first raised the specific grounds of his constitutional argument in a motion to enlarge the court's order under rule of civil procedure 179(b), and the question is raised whether the argument was therefore waived. We do not address the procedural question, however, because we reject the argument on its merits.