184 Pa. 146 | Pa. | 1898
Opinion by
When this case was here before, 173 Pa. 129. it was upon the sufficiency of an affidavit of defense to prevent judgment. The statement of cause of action claimed judgment for the amount of the purchase money stipulated in the agreement for the sale of the land, and the affidavit of defense claimed that the stipulation of the agreement which provided for a title clear of all incumbrances had been violated, and that the plaintiffs were unable to convey such a title. The incumbrance alleged in the affidavit was that which was created by the survey and location of a branch railroad of the Pittsburg & Connellsville Railroad over the land in question, at a time anterior to the execution of the contract of sale. All the particulars of the survey and location were set forth in the affidavit, including a formal adoption of the location by the resolution of the directors of the railroad company of April 4, A. D. 1892. The affidavit also set forth a notice from the counsel of the railroad company by letter dated May 19, 1893, to the effect that the company had surveyed and located the said branch railroad, sometime before, over the property, and that if the defendant purchased the property he would have to take it subject to the right of the railroad company to appropriate the right of way for the road over the land. The plaintiffs having entered a rule for judgment notwithstanding the,, affidavit, the court below discharged the rule, whereupon the
In view of the testimony taken on the trial, and of the decisions of this Court as to what constitutes a good location, we cannot consider these contentions as at all tenable. We have so recently defined what is a good location of the route of a railroad that a brief citation from our latest decision on the subject, will be sufficient. In the case of Williamsport R. Co. v. Phila., etc., Railroad Co., 141 Pa. 407, our Brother Williams, delivering the opinion said: “ The successive steps contemplated by the act of 1849 and subsequent legislation, as necessary to vest a title to the roadway in the corporation, are these:
“1. A preliminary entry on the lands of private owners for the purpose of exploration. This is made by engineers and surveyors who run and mark out one or more experimental lines, and who report their work with such maps and profiles as may be necessary to present it properly to the company that employs them.
“3. Payment to the owner for what is taken and the consequences of the taking, or security that it shall he made when the amount due him is legally ascertained.
“ The title of the owner is not divested until the last of these steps has been taken, (citing authorities). As against him the corporation can acquire only a conditional title hy its act of location, which ripens into an absolute one upon making compensation. As to third persons and rival corporations, however, the action of the company adopting a definite location is enough to give title. . . . The act of location is at the same time the act of appropriation. The space covered by the line as located is thereby seized and appropriated to the purposes of the construction and operation of the railroad, by virtue of the power of eminent domain, and nothing remains to he done except to compensate the owner. After the act of location by the company, the owner or the company may proceed at once to secure an ascertainment of damages.”
It will be observed now, that the selection and adoption of a line by the directors “ fastens a servitude upon the property affected thereby, and so takes from the owner and appropriates to the use of the corporation.” All of this was repeated and reaffirmed in the opinion of Mr. Chief Justice Sterrett, in Johnston v. Callery (this same case), 173 Pa. 129.
Let us now see what was the action of the company as to the adoption and location of the route in this case. Mr. J. B. Washington, the secretary and treasurer of the company, was examined on the trial, and was asked, “ Q. Have you in your possession any plan of that company showing the location of a branch railroad from a point at or near the crossing at Glen wood down in the direction of Marion station? A. I have. Q. Will you produce that plan please ? (Plan produced by the witness.) Q. By whom was this plan prepared? A. By the chief engineer of the company. Q. Now where does that line of railroad cross
It will thus be seen that the resolution of April 4, 1892, recites that a survey of the route had been previously made, and that a map or plan thereof was then before the board, and further that, “a map or plan showing accurately a survey of the line ” should be filed in the office of the secretary of state.
The witness was asked on cross-examination, “ At the time the resolution of the board of directors was passed that jmu have just read, there had been no map or plot showing accurately the survey of the line of the branch road made ? A. There was a map presented to that meeting and adopted, a copy of which was filed in the office of the secretary of the common wealth. Q. Now was that this map? A. Yes, sir.”
While it is true that the surveyors or engineers who actually ran the line on the ground were not produced, the result of their work, to wit: the plan showing the survey, was produced, and was acted upon, and the line thus surveyed was adopted as the line of the road. We do not understand that anything more than this is required. When the engineers have returned to the office of the company, the protracted surveys of the line or lines run, and the survey thus made has been formally adopted and declared to be the location of the road, that constitutes and completes the fact of location. It certainly cannot be necessary for the company to keep the original engineers who did the work on the ground always in sight, so as to produce them in court years after the work was done, in order to testify to their work whenever the fact of the location may be questioned. The plan or map of the survey is the best evidence of what was done, and affords the strongest implication that the work was done. Moreover, the question whether the actual location had been made, was a question of fact, and was submitted to the jury, and was found in the affirmative, and there was not a particle of testimony in the case to impeach the fact of the survey, or the correctness of the finding of the jury.
The contention that because the damages had not been adjusted and paid or secured, at the time of the contract, therefore no title had yet been acquired by the company is of no importance. If the inchoate right of the company was complete it “ fastened a servitude ” upon the property, and therefore became an incumbrance upon the title. The owners were still entitled to prosecute their claim for damages, and to receive the dam
As the case was submitted to the jury on the facts set forth in the affidavit of defense of which we have previously approved as being sufficient, if true, to make out a good defense, and the jury has found those facts, there seems to be nothing on the record that demands further consideration. It was shown on the trial that the property was bought for the Second Avenue Traction Co. to erect a power house thereon, and for that purpose it was very desirable to have the building on the bank of the river. The location of the railroad cut off such use of the ground and rendered the land undesirable. As there was no doubt of the railroad company’s right to proceed to the ascertainment of damages under its location, and to erect the road on the route adopted, it is difficult to understand how, or in what sense, the adoption of the survey and the location of the road on that line was not an incumbrance on the title. With this servitude fastened upon it, and holding it for the benefit of the railroad company, the purchaser could not get the title he contracted for, and therefore his contract rights as a purchaser were seriously affected by the superior rights of the company. On this subject our Brother, the Chief Justice, said in this very case, 178 Pa. 129, quoting from the Williamsport case, “ The act of location is at the same time the act of appropriation. The space covered by the line as located is thereby seized and appropriated to the purposes of the construction and operation of the railroad by virtue of the power of eminent domain, and nothing
The judgment is affirmed.