12 N.Y.S. 630 | N.Y. Sup. Ct. | 1890
This action was brought to recover certain moneys claimed to be due by defendant to plaintiff. The plaintiff was a manufacturer working a steam rolling-mill, and the defendant was a vendor of steel. In 1879 the defendant made an agreement with the father of the plaintiff by which he agreed to furnish crude steel to the father of the plaintiff; the latter to manufacture it for him at a fixed rate of compensation. The agreement was continued during the mutual pleasure of the parties, and to terminate only after two months’ notice of such discontinuance, and the completion of all contracts then entered into. In December, 1881, the father of the plaintiff died; and subsequent thereto the defendant entered into an agreement' with the plaintiff, who had succeeded to his father’s interest in the mill, which had in the mean time been removed to Pennsylvania. This agreement was a continuation of the agreement theretofore made between the defendant and plaintiff’s father, and provided that the defendant should supply raw material, and the plaintiff was to work it up, and defendant was to pay plaintiff at the prices fixed in the agreement, and that the agreement was to terminate on two months’ notice. Under this agreement the parties continued business over two and a half years, until the 16th of July, 1884, when notice was given terminating the same two months thereafter. At this time there was $331.56 due under this second agreement, and the plaintiff stopped working thereunder. On the 31st of July, 1884, the parties entered into a third agreement, which provided for its continuance for 5 years, during which the defendant was- to have the exclusive sale of the entire product of the plaintiff’s mill, with a credit of 60 days from the date of each monthly account within which to pay the amount thereof. It further provided that, in ease the defendant should fail to make payment as provided in the agreement, the
■ The claim of the defendant is that the plaintiff cannot recover the moneys sued for, because he failed to perform the contract under which these moneys were earned, and that the breach of the contract caused the defendant certain damages, as alleged in the counter-claim. It seems to us, in view of the negotiations between these parties which resulted in the making of the third agreement, that whatever defaults may have taken place under the second agreement were waived, and that the plaintiff would have a right of action against the defendant for the amount due under that second agreement at the time at which the third agreement was entered into. The ease in respect to the claim made under the third agreement, however, is entirely different. By the terms of the third agreement, the plaintiff was to have the right to terminate the same, in case the defendant should fail to make payment as therein provided, upon 10 days’ personal notice. And the plaintiff expressly states, in the course of his cross-examination, that the object of requiring the 10-days notice was to enable the defendant to hold on to the agreement for these 10 days. It appears from the uncontradicted evidence in the case that instead of waiting till the 10 days to stop work, at which time the agreement became null and void by its terms, the plaintiff stopped work instantly, and refused to go on during the period of these 10 days, and thus broke the agreement upon his part. The terms of the agreement did not provide that the agreement should become null and void in case the defendant failed to make payment in accordance with its terms; but it gave the plaintiff the option, in ease of such failure, to terminate the agreement by giving 10 days’ notice; such termination evidently to take place after the expiration of the 10 days for which the notice had been given. Therefore the position of the plaintiff is a breach upon his part of the terms of the agreement under which he claims judgment against the defendant. In order that the plaintiff should recover these various sums of money which he claims, it was necessary for him to show that he had performed the contract on his part, and until he established that proposition no right of action in his favor existed. The plaintiff not only did not establish this proposition, but it was proven that he broke the agreement himself by failure to comply with its terms. This being the condition of the proof, we do not see how the plaintiff can recover for the work done prior to the breach.
It is urged that by the provisions of the agreement the plaintiff was to have a lien upon the termination of the agreement upon all the material which was sent to him by the defendant in case of a breach. But that lien did not exist until the expiration of the 10 days after the giving of the notice, and after the agreement had become null and void. The provision is as follows: “It is further agreed that, in case the party of the second part shall fail to make payments as above provided, this agreement shall, upon 10 days’ personal notice, be null and void; and any sum or sums which may at.such time be due the party of the first part shall be a lien upon any stock or material belonging to the party of the second part which may then be in the mill.” The words “at such time” evidently refer to the time when the agreement shall become null and void, namely, 10 days after notice. “The material belonging to the party of the second part which may then be in the mill.” The