191 A.D. 205 | N.Y. App. Div. | 1920
The plaintiffs, contractors, have recovered a judgment for $5,345.22 against the city of New York for damages caused by the suspension of their work in constructing a sewer. The city, appealing, claims that by the express terms of the contract such damages are at the charge of the contractors. The contract, which was made on September 19, 1912, was for the construction of a section of a sewer in Staten Island. Work was begun soon thereafter and continued until March 6, 1913, when the engineer in charge notified plaintiffs to cease work on account of the failure of the board of estimate and apportionment to appropriate sufficient funds to pay for the engineering and inspection necessary to complete the sewer. Work was accordingly suspended until May 17, 1913, when, the requisite appropriation of funds having been made, it was, on the direction of the defendant, resumed and completed. It is for the damages caused by the suspension of the work that the judgment under consideration was rendered.
The contract contains the following clause: “ The President [of the borough] may suspend the whole or any part of the work herein contracted to be done if he shall deem it for the interest of' The City so to do, without compensation to the Contractor for such suspension other than extending the time for completing the work as much as it may be, in the opinion of the President, delayed by such suspension.” As I understand it, the claim of the appellant that it is not liable rests primarily upon this clause in the contract.
Was it the intent of the parties that this power to suspend work, entailing as it did great expense on the contractors, could be exercised because the city had failed in the performance of its obligation? I think not. It cannot be assumed that a clause in the contract was intended to authorize one of the parties to impose the result of its own default upon the other. A court should not so interpret a contract unless required so to do by the most explicit terms. There is room enough for the proper operation of the clause without giving it an interpretation so unreasonable. The city was bound to furnish inspectors and engineers. Without them the work could not proceed. The city suspended work on the contract because it had no appropriation for such engineering and inspection. Therefore, the city suspended the work because it had failed in its obligation. The quoted clause cannot be construed to authorize such an unreasonable and unjust result. It cannot in its true meaning be said to authorize the suspension of the work in the interest of the city, when used to relieve the city from the result of a violation of its duty under the contract. It is the interest of the city in performance and not in breach which justifies a suspension of the work.
As no other point was made by the brief of the appellant, it is unnecessary to consider other points discussed by the respondents.
The judgment and order should be affirmed, with costs.
Present—Jenks, P. J., Mills, Putnam, Blackmar and Kelly, JJ.
Judgment and order unanimously affirmed, with costs.