Friеl Golf Management Company, Inc. (Friel), protests that a consent judgment between its rival, Johnson Turf and Golf Management, Inc. (Johnson), and the city of Beverly,
This, in outline, is the factual context and procedural setting of the dispute. In the fall of 1996, the city published a requеst for proposals (RFP) to qualified bidders to operate the Beverly Golf and Tennis Club (club) for a five-year period, with a five-year option to renew to be held by the city. As a result of procedural glitches not here relevant, on September 17, 1997, the city published a seсond RFP, and Johnson and Friel submitted the only two qualified bids. Johnson outbid Friel by $550,000. Even so, the city awarded the contract to Friel, concluding that Johnson had no “recent experience” operating a clay tennis court and lacked sufficient equipment to maintain the golf coursе in the manner contemplated by the RFP. Some members of the Beverly Golf and Tennis Commission downgraded Johnson’s qualifications, citing “negative references” from other Johnson clients.
Aggrieved by the city’s award of the contract to Friel, Johnson, on December 19, 1997, filed the instant aсtion claiming violations of G. L. c. 30B, breach of an implied contract, violation of the public trust, and conspiracy. It sought money damages and injunctive relief to restrain the city’s award of the contract to Friel. After a hearing on the plaintiff’s motion for a preliminary injunction, a Superior Court judge, recognizing that, without an injunction, Johnson’s remedy would be limited to bid preparation costs unless there was proof of bad faith, see Peabody Constr. Co. v. Boston,
Friel, who had managed the club prior to the first bidding process, maintained the status quo under the order. On February 5, 1998, Friel moved, with the assent of the parties, to intervene in the instant case; that mоtion was allowed on the same day. By July, 1998, after the city had rebid the contract as suggested by the motion judge, Friel, for the third time, was the recipient of the award. On August 19, 1998, a status conference was held in the Superior Court on the underlying case. The parties agreed that Johnson would amend its complaint limiting its claims to money damages. Johnson, for reasons that do not appear in the record, agreed to drop its pursuit of the management contract. Friel was voluntarily dismissed as an intervener because Johnson limited its claims to money damagеs. This arrangement was memorialized in a “Proposed Agreement and Procedural Order” approved by another Superior Court judge on September 4, 1998.
Trial of Johnson’s damage claims was bifurcated by order of the judge. Pursuant to Mass.R.Civ.P. 53(b)(2), as amended,
At this juncture, the case took an unpredictable course. About thirty days prior to the scheduled trial, the city reversed itself and entered into a “Settlement Agreement” with Johnson which, among other things, awarded Jоhnson the contract for the operation of the club. It appears that Friel, which was no longer a party to the action, had no notice or opportunity to be heard. In August, 2001, a judgment entered incorporating by reference all of the terms of the agreеment. Approximately three weeks later, Friel filed a “Motion to Re-intervene and to Set Aside [the] Judgment.” Another judge, after a hearing, denied Friel’s motion. Friel has appealed from that order.
Analysis. A judge should allow intervention as of right when (1) the applicant claims an interеst in the subject of the action, (2) he is situated so that his ability to protect his interest may be impaired as a practical matter by the disposition of the action, and (3) his interest is not adequately represented by the existing parties. Mass.R.Civ.P. 24(a)(2),
With respect to the threshold question of timeliness, it has been observed that “postjudgment motions to intervene, whether as of right or pеrmissive, are seldom timely.” Bolden v. O’Connor Café of Worcester, Inc.
It remains to ask, however, whether Friel has established a “significantly protectable” interest in the litigation. See Bolden v. O’Connor Café of Worcester, Inc.,
Nor is Friel’s interest remote or contingent. See and compare Restor-A-Dent Dental Labs., Inc. v. Certified Alloy Prods., Inc.,
The motion judge saw Friel’s asserted interest somewhat differently. He concluded that the master’s decision in July,
We have examined the transcript of the motion hearing and can find no support for these rulings. To the contrary, at sеveral points during the hearing, the motion judge questioned why Friel was not allowed to defend its interest prior to the August, 2001, settlement agreement awarding the contract to Johnson. Indeed, when the judge pressed Johnson’s counsel for an explanation for its argument that Friel was derеlict for not reintervening after the master’s decision, counsel could not muster anything. The motion judge then commented that he did not think Friel had any reason to intervene at that stage. There followed an oblique reference to a mediation session conducted by a Superior Court judge after the master had filed his decision where the idea of awarding the contract to Johnson was initially discussed. The record is devoid of information regarding what happened at that time beyond what we have noted from the hearing transcript. There is no doubt, however, that the motion judge was apprised that Friel, through no fault of its own, was not present to state its perspective. Construing the analogous Fed.R.Civ.P. 24(a) in Fiandaca v. Cunningham,
In exercising his discretion, the motion judge commented that Friel’s postjudgment bid to reintervene “would cause significant prejudice and delay to the parties to this litigation.” He minimized any corresponding prejudice to Friel by concluding that Friel could pursue “its remedy for perceived wrongs in a separate action.” That theme was echoed by Johnson’s appellate counsel during oral argument of this appeal. He suggestеd that any contract or G. L. c. 30B claims Friel may have arising out of the settlement agreement could be litigated in a separate proceeding. When pressed by the panel, counsel indicated that, in fact, Friel had filed such an action which was presently pending in the Superior Court. However, as one member of the panel surmised, the city had raised several affirmative defenses to Friel’s new action, including issue preclusion, pending of a prior action, and waiver.
We are not obliged to consider the question whether issue prеclusion would apply in these circumstances, because the pertinent question is not whether Friel’s interest could be protected in another action, but whether there “may” be a practical negative impact on the protection of that interest if intervention is not allowed. See Cosby v. Department of Social Servs.,
In these circumstances, it seems clear to us that the motion judge mistakenly denied Friel’s application for postjudgment re-intervention in the instant case. There remain significant factual
For these reasons, we reverse the order denying Friel’s mоtion to reintervene and remand the case to the Superior Court for further proceedings consistent with this opinion.
So ordered.
Notes
For ease of reference we refer to the defendants as the city.
General Laws c. 30B, known as the Uniform Procurement Act, provides that certain municipal contracts be awarded by advertised competitive bidding.
The motion judge wrote that he would treat Friel’s motion to intervene under Mass.R.Civ.P. 24(b),
Nothing in the special master’s findings suggests аn award of the contract to Johnson as a proper remedy for the city’s violation of G. L. c. 30B. Thus, there was no rational basis for Friel to conclude that its interest was in jeopardy at that juncture of the proceedings.
The Reporters’ Notes to Mass.R.Civ.P. 24 state that rulе 24(a) is identical to Fed.R.Civ.P. 24(a). Reporters’ Notes to Mass.R.Civ.P. 24(a), Mass. Ann. Laws Court Rules, Rules of Civil Procedure, at 483 (LexisNexis 2003). Therefore, “the adjudged construction . . . given to the Federal rule[] is to be given to our rule[], absent compelling reasons to the contrary or significant differences in content." Rollins Envtl. Servs., Inc. v. Superior Ct.,
