49 Mo. App. 90 | Mo. Ct. App. | 1892
Plaintiff corporation, a lumber company, sold and delivered a bill of lumber amounting to $70.95, to the defendants, Schuler & Muench, contractors, with the other defendants, the Hellers, for the erection of a certain building for the latter. The plaintiff, in accordance with the statute, filed its mechanics’ lien against the lot and the building, in the erection of which said lumber was used by Schuler & Muench, under the contract with the owners, the Hellers. Afterwards the plaintiff brought its suit for the enforcement of said hen before a justice of the peace. The defendants, the Hellers, were duly served with process, but no service was had on Schuler & Muench. The justice thereupon entered an order on his docket requiring the plaintiff to give notice to Schuler & Muench as required by section 6163, Revised Statutes.
On the day set for the hearing of the cause the following entry appears on the docket of the justice: “And now, on this first day of December, 1890, it appearing to the satisfaction of the court, that Newton Hall, constable of Washington township, did, more than twenty days before the time of the trial in this case, post up, at four public places in the county, four'
From the judgment overruling the motion, defendants, the Hellers, have appealed.
The justice, under the provisions of article 4, chapter 94, was invested with jurisdiction over the subject-matter of the action. The appealing defendants, the Hellers, who were the owners of the property subject to the hen of plaintiff, were served with summons according to law so that the jurisdiction, not only over the subject-matter but of the person as to the appealing defendants, was complete. But the appealing defendants
The statute, section 6713, requires that, in all suits for the enforcement of mechanics’ liens, the parties to the contract shall be made a party. It further provides in section 6725, that in all cases where a lien shall be filed by any person other than the contractor, that it shall be the duty of the contractor to defend any action brought thereupon, etc. In Horstkotte v. Menier, 50 Mo. 158, it was declared that when the owner of property contracts with a responsible party to furnish all materials and erect for him a building under the above section, he has the right to look to such contractor for protection against all liens by materialmen and subcontractors. If the original party was not made a party he would not be bound by the judgment; whereas, if he was, he would be estopped to dispute the amount of the recovery between himself and the owner. The original contractor ought to be brought before the court as a co defendant for the purpose of protecting his rights and those of the owner. The statute in relation to the enforcement of mechanics’ liens before justices of the peace requires that, if the finding be for the plaintiff and sustaining the lien, the judgment shall be that he recover the amount of the indebtedness found to be due, with costs, with the addition that, if sufficient property of the debtor cannot be found to satisfy such judgment and costs, the same or the residue thereof shall be levied of the property charged with the lien, etc. The case under the statute is as if a creditor proceeding by attachment and garnishment should dismiss his suit against the defendant and afterwards take steps.
In all cases except in that provided in section 6164 the statute by its very terms requires that there must be a personal judgment against the contractor; otherwise there would be no judgment which the owner’s property could be condemned to satisfy. It is' well settled by the cases just cited that no recovery can be had charging the premises with a lien except as incident to a personal judgment against some one with whom the contract for the work or materials was made, and who, himself, is. either the owner or standing with the owner, or some contractor under him, in a contractual relation, and then only where the work or material actually entered into the construction of the building or improvement. The judgment of the circuit court was rendered as if the contractors had been notified as required by section 6163, which, as we have seen, was not the case.'
It is contended by the plaintiff that, although the appealing defendants had the right to have the contractors, Schuler & Muench, made codefendants and served with process, yet, as that was not done, and as they took no steps before judgment to have it done, that they thereby waived their right. It has been oftentimes decided under our practice act that unless the objection of defect of parties to the record is made, either by demurrer or answer, it will be deemed waived. Gimbel v. Pignero, 62 Mo. 240; Butter v. Lawson, 72 Mo. 227. And this rule has been held to apply in actions brought upon mechanics’ liens in courts of
The judgment of the circuit court is.reversed, and cause remanded with directions to sustain the motion of the appealing defendants.