Lead Opinion
We granted John Thurmond & Assоciates, Inc.’s (JTA) petition for writ of certiorari to the Court of Appeals to determine whether a plaintiff in a breach of contract and negligent construction case must prove fair market value of the property as a prerequisite to any recovery. See Kennedy v. John Thurmond & Assoc.,
David Kennedy is a homeowner whose home was substantially damaged by fire. JTA is a residential restoration/construction company hired by Kennedy to make repairs to his home for an agreed upon contract price of $311,156. Kennedy subsequently discovered problems with the construction and initiated an action against JTA for breach of contract, breach of warranty, negligent construction, and negligence. At trial Kennedy presented evidence of the cost of repairing the allegedly faulty construction estimated at $751,632.
1. We begin our analysis of the proper meаsure of damages in this case by acknowledging that damages are intended to place an injured party, as nearly as possible, in the same position they would have been if the injury had never occurred. See BDO Seidman v. Mindis Acquisition Corp.,
As a general rule, damages for defective construction, whether those damages are the result of a breach of contract or negligence of the contractor, are determined by measuring the cost of repairing or restoring the damage, unless the cost of repair is disproportionate to the property’s probable loss of value. Hall v. Chastain,
proof of the cost of repair because of the defective construction is illustrative of the difference in value claimed as damages, and is more likely to represent the true damage suffered from the failure of a contractor to complete his contract than would the opinion of an expert as to the difference in values.
(Punctuation omitted.) Williams Tile &c. Co. v. Ra-Lin & Assoc.,
These principles are repeated in the Restatement (Second) of Contracts, which states:
(2) If a breach results in defective or unfinished construction and the loss in value to the injured party is not proved with sufficient certainty, he may recover damages based on
(a) the diminution in the market price of the property caused by the breach, or
(b) the reasonable cost of completing performance or of remedying the dеfects if that cost is not clearly disproportionate to the probable loss in value to him.
Restatement (Second) of Contracts: Alternatives to Loss in Value of
Thus, under Georgia law, cost of repair and diminution in value are alternative, although oftentimes interchangeable, measures of damages in negligent construction and breach of contract cases.
2. Against this background, and relying on several Court of Appeals cases, JTA argues that evidence of fair market value is necessary regardless of the measure of damages applied because recoverable damages in construction defect cases can never exceed the fair market value of the рroperty at the time of the breach or tort. While Georgia courts may not always have been clear in their application of the rules of damages in construction defect cases, we find no authority in the cases JTA relies upon to support bis contention that courts have created an inflexible rule limiting the amount of recoverable damages.
In Small v. Lee & Bros., supra,
and one which would not be unjust in its application to either party, would be the difference between the value of the house as finished and the house as it ought to have been finished. To require that the house should be rebuilt, and that the contractor should pay the cost of rebuilding, or that the estimated cost of making the house conform to the contract should be allowed as damage, would be to give an unconscionable advantage to the owner, and would deprive the contractor of adequate compensation for his work and materials.
Id. at 398. Thus, the court in Small correctly recognized that in some cases defects cannot be remedied without great expense and/or substantial damage to the rest of the structure and determined that in such casеs, where the cost of remedying the defect would far exceed the value of the improvement and provide a windfall to the injured party, an alternative measure of damages should be applied. See also Mercer, supra,
In Ryland Group v. Daley, supra,
Despite JTA’s arguments, we are not persuaded that either this lаnguage or the similar language in Song was intended by the Court of Appeals to create an immutable rule that damages may never exceed the fair market value of the property. To construe this language to mechanically limit damages would be contrary to the charge that the method of calculating damages should be flexible so as to reasonably compensate the injured party, and at the same time, be fair to all litigants.
3. Here, the record shows that Kennedy elected to prove his damages by presenting evidence, including expert testimony, of the cost to repair the alleged damage to his home caused by JTA’s defective workmanship. Because there is no indication in the record that the court determined cost of repair to be an inaрpropriate measure of damages in this case and because Kennedy presented some evidence of the cost to repair, we agree with the Court of Appeals that the trial court erred in directing a verdict against Kennedy. See Teklewold v. Taylor,
Judgment affirmed.
Notes
Kennedy presented evidence demonstrating that, inter alia, siding and roof materials had been improperly installed and floors on the home’s main level were substantially uneven, causing wall cracks throughout the home and requiring the tear out and removal of all floor joists beneath the home in order to repair the defects.
Although unusual, it may sometimes he appropriate, in order to make the injured party whole, to award a combination of both measures of damages. In such cases, notwithstanding remedial measures undertaken by the injured party, there remains а diminution in value of the property, and an award of only the costs of remedying the defects will not fully compensate the injured party. See, e.g., Ray v. Strawsma, supra,
Whether the facts in a particular controversy justify the application of the rule of damages permitting recovery for the amount of the reasonable cost of repairing the defects, or whether the facts are such as to require application of the diminution in value rule, is a question ordinarily determinеd by the trial court based on the varying facts and circumstances of each case. See Ray v. Strawsma, supra,
The proportionality rule similarly does not require an injured party to prove fair market value. When assessing proportionality, the trial court need only determine whether the cost to remedy the defect is disproportionate to the loss. See Empire Mills, supra,
That is not to say there is no limitation on the amount of damages to be awаrded in construction defect cases. As with all damages, “ ‘the cost of repair must be reasonable and bear some proportion to the injury sustained.’ [Cit.]” Empire Mills, supra,
Dissenting Opinion
dissenting.
We granted certiorari to determine whether proof of the property’s market value is a prerequisite to a recovery for breach of a construction contract or for negligent construction. The majority answers that question in the negative. I disagree and, therefore, rеspectfully dissent.
“There are three measures of damages applicable to injury to improved realty.” Link & Hertz, Ga. Law of Damages, § 27.2, p. 473 (2007). The general rule permits the plaintiff to recover the cost of restoration; when that cost is unreasonable considering the property’s pre-injury market value, recovery of the diminution in the
However, the complaint in this case did not allege that John Thurmond & Associates, Inc. (JTA) damaged Mr. Kennedy’s house. That structure had already sustained substantial damage in a fire, and JTA was hired to make repairs for a contract price of $311,156. Mr. Kennedy contends that JTA breached the contract and performed the repairs negligently. Thus, recovery is sought for failing to improve the property in accordance with the contract, not for damaging existing improvements to the realty.
Obviously, fair market value of the property as it should have been improved must be shown, since that is what Mr. Kennedy claims that he lost as the result of JTA’s breach or negligence.
As a general rule, the measure of damages in such a case is
“the difference between the value of the work as actually done and the value which it would have had if it had been done properly under the contract.... (T)his difference in value can be shown by evidence of the reasonable cost of correcting the defect.” [Cit.]
City of Atlanta v. Conner,
“[T]his difference in value can be shown by evidence of the reasonable cost of correcting the defect. Proof of the cost of repair because of the defective construction is illustrative of the difference in value claimed as damages, and is more likely to represent the true damage suffered from the fаilure of a contractor to complete his contract than would the opinion of an expert as to the difference in values, though such proof would also have been permissible.” [Cit.]
Magnus Homes v. DeRosa,
As is true in cases involving damage to improved property, there is an alternate measure of damages in cases involving the breach and
cannоt be reasonably repaired, the measure of damages is “the property’s value as diminished by irremediable defects ... deducted from the value of the house as it should have been completed according to the contract.... If the damage cannot be repaired, it seems pointless error to insist the value be determined by cost of repair.” [Cit.]
City of Atlanta v. Conner, supra. Thus, this alternate measure of damages for irremediable defects also requires proof оf the difference in market values, but since recovery is sought for irreparable defects, that difference cannot be shown by evidence of the cost of repairs.
Recognition of the general and alternate measure of damages in construction cases “is not a new rule, nor is it necessarily limited to breach of contract cases. [Cit.]” Ray v. Strawsma,
Regardless of the measure of damages, however, the fair market value of the property must be proven, and, although exact figures are not necessary, the trier of fact must be able to “reasonably estimate (the fair market value) without resort to guesswork.” [Cits.]
City of Atlanta v. Conner, supra. Proof of fair market value at the time of the breach is necessary in all cases because that is what was allegedly lost and “the plаintiff is entitled only to the benefit of the bargain or to be made whole and not to recover a windfall.” Ryland Group v. Daley,
The determinative factor as to which measure of damages applies is that “ ‘[t]he cost of restoration may not be disproportionate to the diminution in the property’s value. Rather, “ ‘the cost of repair must be reasonable and bear some proportion to the injury sustained.’ (Cit.)” [Cit.]’ [Cits.]” (Emphasis omitted.) Wise v. Tidal Constr. Co.,
Ideal Pool Corp. v. Hipp,
Here, Mr. Kennedy claimed some $751,631 in repairs to a residence that JTA contracted to rebuild for $311,156. Obviously, $751,631 to “repair” a house that was rebuilt for $311,156 is unreasonable, just as a sum between $12,000 and $15,000 to “repair” a $14,500 swimming pool in Ideal Pool Corp. was unconscionable. Thus, Mr. Kennedy was not entitled to rely on the cost of repairs as his measure of damages, but was required to show the diminishment in the fair market value of the house as a result of the defects. The residence
has some value, if only for scrap ([cit.]), and that value may obviously be whatever it is worth as a result of the irremediable defects. The owner should not have the benefit of that value, however low, by recovering [more than double] the entire contract price; the property’s vаlue as diminished by irremediable defects should be deducted from the value*478 of the house as it should have been completed according to the contract.
Ray v. Strawsma, supra at 623-624 (1). Because Mr. Kennedy failed to prove his recoverable damages, but relied instead on the evidence of the cost of “repairs,” the trial court correctly granted JTA’s motion for directed verdict and the Court of Appeals incorrectly reversed the trial court. Therefore, I dissent to the majority’s affirmance of what I believe to be an erroneous judgment of the Court of Appeals.
