78 Ct. Cl. 423 | Ct. Cl. | 1933
When applied to the facts in this case :the written contract between the plaintiff and the Govern:ment precludes the entry of judgment by the court in plaintiff’s favor on any of the items making up its claim, and the • question whether plaintiff should be compensated for all or .any portion of the extra expense arising from the conditions disclosed by the findings, by reason of the delay in progress of the work caused by the Government and the extra work ■ which plaintiff was required by the Government’s authorized representative to perform, is for the Congress to decide. The facts hereinbefore set forth, with this memorandum, will therefore be certified to Congress in accordance with section 151 of the Judicial Code, which provides with refer- - ence to a case of this character that the court “ * * * shall proceed with the same in accordance with such rules as it may adopt and report to such House the facts in the ■case and the amount, where the same can be liquidated, * * * together with such conclusions as shall be suffi- • cient to inform Congress of the nature and character of the demand, either as a claim, legal or equitable, or as a gratuity .against the United States * *
The facts established by the evidence, and set forth herein, 'together with this memorandum and our conclusions with respect to the various items, will be certified to the Senate in accordance with Senate Besolution 326 referring to this court Senate bill 2588 for the refief of plaintiff in the premises.
Before discussing the merits of the various items making up the claim from the standpoint whether the plaintiff, in '..the circumstances, ought to be compensated ■ therefor in
Plaintiff performed a-11 the work required by it under the-contract strictly in accordance with the terms .thereof except that the work was not completed within ninety days after-notice of acceptance of the bond furnished by plaintiff under-the contract, and to the satisfaction of the Government, but: the delay in completing the work within the time specified as ■ a matter of fact was caused almost entirely by the Government in slowing down the progress of the work by occupancy of the building before it was completed, in ordering-changes and extra work and requiring and compelling plaintiff to execute the same without a written order and without. compensation, in failing to furnish articles of equipment and supplies called for by the contract when they were needed,, and in requiring plaintiff in some cases to furnish equipment and material at its own expense which the contract required the Government to supply, all of which resulted in additional expense for materials, labor, and overhead, and caused the work to extend beyond the date when there was-ah increase in cost of labor and when it could and would, have otherwise been completed.
Had the Government given plaintiff written directions to perform the various items of work involved in plaintiff’s claim it would have been entitled under the contract and specifications to compensation for the additional cost and expenses with respect to a number of the items involved, and the Department under the contract would have been authorized to make payment therefor. And it seems to us under the facts disclosed that at least a number of the items involved constituted extra work under the contract and that, as a matter of justice to plaintiff, written directions should have been given as requested by plaintiff at the time. In some instances not involved in this claim written direc
The conditions affecting plaintiff’s capital were such that if the payments provided in the contract to be made as the work progressed were not received it would be unable to proceed with completion of the work called for by the contract. This fact was known to the Government’s representative and he used it as a means of compelling plaintiff to carry out the demands for extra work and the performance of work requiring additional costs, due to errors of the Government and in the plans supplied by it. In some instances when the extra work involved in making up plaintiff’s claim was required by the Government, plaintiff was advised and led to believe that the matter would be adjusted and compensation made therefor later. This, however, was not done. At the completion of work in 1921, when plaintiff made its claim for extra compensation and requested the Government not to impose upon it any penalty for delay in completing the work within the time specified because such delays had been due to causes over which plaintiff had no control and had been caused chiefly by the Government, the Government acceded to plaintiff’s claim with respect to the penalty and none was imposed. All claims for reimbursement of its losses, however, were denied, and in connection with the whole matter it was stated to the Surgeon General by the Government’s authorized officer who had at all times been in charge of the work that “ On the other hand, the Government was particularly fortunate in obtaining a contract at all, and it is confidentially stated that the trans
The evidence establishes to our satisfaction that, based upon the amount which was paid by the Government under the contract and the value of the work actually performed by plaintiff, including the items involved in this claim, this statement made at the conclusion of the work by the official of the Government who was present at all times during the progress of the work and who had supervision thereof, as the representative of the Surgeon General, was substantially correct.
The first item in plaintiff’s claim concerns the matter of reimbursement for its additional expense for a delay of eleven working days caused by the Government due to its failure to give plaintiff possession of the building upon delivery of the notice of acceptance of the bond on March 1, 1920, which caused the work under the contract to extend beyond May 10, 1920, when there was a general increase in labor costs, causing plaintiff additional expense, including overhead for this period, of $524. Although the contract provided that the Government would not be responsible for any damages arising out of any delay caused by it, this was an actual expense of plaintiff for which it has not been compensated (finding II).
The second item in the claim (finding III) relates to additional expense for labor, loss of time, and unnecessary repairs and overhead expense in the amount of $7,092.22 resulting from lack of elevator facilities which plaintiff contemplated, at the time it made its bid, would be available.
The hospital building, which plaintiff contracted to remodel, was vacated by the Government when the work commenced. There was an elevator in this building which had been operated with electric current supplied by the Government ; there was also an emergency connection with the current supplied by the Edison Company. The only work to be performed by plaintiff on this elevator was to change the control from mechanical to electrical control. When the Government vacated the building there was no current with Avhich to operate the elevator and when plaintiff sought to connect the elevator motor with the current of the Edison
In addition to the foregoing, plaintiff could have minimized its expense of $7,092.22 because of lack of elevator facilities by doing the necessary work to make the elevator-usable at a cost of only $350.
The next item in the claim relates to extra expense to plaintiff as the result of interference with progress of the
The merit of the claim for $1,616 grows out of a great many circumstances. Employees and equipment were moved into the building and a considerable portion of it was occupied by the Government about July 1, 1920. Other employees and equipment were moved in from time to time. At that time the contract period of 90 days for completion of the work had expired, but failure of plaintiff to have the work completed had resulted from other acts of the Government which had brought about delay in the completion of the work, for which delay the Government under the contract was not responsible for damages. Plaintiff incurred the additional expense claimed because of the interference with and slowing down of the work on account of the occupancy of the building before the work of remodeling was completed, and it is simply a matter with Congress as to whether plaintiff should be reimbursed for this expense which was brought about by a delay for which it was not liable under the contract. There is merit in this item of the claim. The Government had the use of the building at plaintiff’s expense.
The next item (finding V) relates to extra expense of $647 for installation of urinals, together with overhead expense of $122.93, on which a reasonable profit was.$76.99, making a total of $846.92, and concerns the delay of the Government in supplying certain urinals and in furnishing erroneous measurements and dimensions with the result that the work preparatory to connection of these articles had to be torn out and reinstalled. We think there is merit in this claim. The extra expense resulted from erroneous information supplied by the Government upon which plaintiff proceeded to rely. A written order for the extra work mentioned should have been given and payment made therefor. The plaintiff was without fault.
The next item (finding YI) relates to the failure of the Government to furnish, in accordance with the contract, all pipes and fittings, including nickel-plated pipes and fittings, to be installed by plaintiff, for a period of nearly eleven
The next item is somewhat similar (finding VII). The Government agreed under the contract to furnish all hospital equipment, including 13 sterilizers and pipes and fittings therefor, which plaintiff was to install. The plaintiff was ready and prepared to do all work necessary for the installation and to install the sterilizers April 15, 1920, and so notified the Government and requested that such sterilizers be furnished for installation. The Government was unable to do so and plaintiff was supplied by the Government with measurements of the sterilizers so that it could proceed with the performance of the roughing work necessary for their installation so that they could be connected promptly when they arrived. When the pipes and connections for the sterilizers had been installed and all tiling laid and walls painted, it was found when the sterilizers arrived and were delivered by the Government in November 1920, that the measurements supplied by the Government were erroneous and that all of the work which had been done had to be torn out and done over at an additional cost to plaintiff for this particular work, including overhead and reasonable profit, in the total amount of $1,288.05.
The delay in furnishing the sterilizers and the necessity of having to do over the work that had already been done resulted in an extra expense to plaintiff of $232.05 because of an increase in wages which occurred in the meantime. Plaintiff was without fault and this item of the claim has merit.
The next item (finding VIII) relates to the extra expense to plaintiff because of delay by the Government in furnishing six prophylactic sinks and tanks, which plaintiff was to
The next three items of claims (findings IX, X, and XI) relate to the inability of plaintiff to obtain hydrated lime, tile plinth block, and 2" x 6" wall tile.
As soon as plaintiff found out that these materials were unobtainable it promptly requested of the Government permission to substitute and use rock lime, marble plinth block, and 3" x 6" wall tile. After some delay the Government granted these requests but not until after May 10, 1920, when there was a general increase in labor costs. Plaintiff actually incurred the increased labor costs claimed in respect of these three items, but it seems to us that the items are of such a character that plaintiff has no meritorious claim against the Government for compensation for this increased expense. Plaintiff agreed to furnish materials of the kind specified apparently without knowing, or investigating to find out, whether they were obtainable. The Government did not know that the articles called for could not be obtained on the market and it granted plaintiff’s request to substitute twenty-three days after it was first made. It does not appear that this delay in granting the request was unreasonable. The Government doubtless wished to satisfy itself before granting the request to make substitutions that the materials were in fact unobtainable.
The next item (finding XII) has reference to an extra expense of $51.11 due to a delay of six months caused by the
The next items, which will be considered together (findings XIII, XIY, and XV) relate to extra expenses to plaintiff in connection with moving certain soil and vent pipes, floor drains, and marble wainscoting because of erroneous information shown on the plans furnished plaintiff upon the basis of which it made its bid for the work called for. The total wages and overhead expense resulting from these causes was $1,781.24 and the reasonable profit for this extra work which was not contemplated by the contract or by the plaintiff in making its bid was $178.11. Plaintiff’s claim on account of these items is meritorious. The contract did not contemplate this work and plaintiff had no way of knowing that it would be required. It relied upon information furnished by the Government which was erroneous.
The next item, finding XVI, relates to the extra work in connection with the solarium. Compliance with the terms •of the contract and specifications did not produce the result desired by the Government, and plaintiff was required to perform this extra work at the expense stated in the finding mentioned. A written order therefor was refused. We think a written order should have been given. This item amounts to $400.55. In our opinion it should be allowed.
Although the contract required the Government to furnish all pipes and fittings for the kitchen equipment (finding XVII (b)), it failed to do so and plaintiff was compelled by the Government to purchase the same, in order to avoid having payments due under the contract withheld, at an additional expense plus a reasonable profit of $411.24.
The same was true with reference to the nickel-plated pipes and fittings for the showers, toilet stalls, etc., which the Government was required to furnish (finding XVII (c)). Plaintiff was required by the Government, without any written order, to purchase this equipment at its own expense. It did so at an extra expense plus a reasonable profit of $884.18.
The plans and specifications showed that floors in rooms C-6 and C-ll were only to be repaired (finding XVII (d)). Plaintiff desired to make such repairs as contemplated by thq contract but the Government required it instead to give the whole floor a new coat of cement. Although warned that such coating of the floor would not hold, that it would crack and have to be removed, plaintiff was required by the Government to proceed as directed. It did so and laid the floor under the supervision of the Government’s authorized representative. It cracked and the Government required that it be torn up and a new floor laid under penalty that if this was not done further payments under the contract would be withheld. Plaintiff did this extra work at extra expense plus a reasonable profit, totalling $401.21.
The contract and specifications contained no provision requiring plaintiff to paint certain portions of the garage where no work was to be done (finding XVII (f)), but the Government, after asking for bids on painting the second floor and the hallway, where no work was to be performed, refused to accept such bids and required plaintiff to paint the second floor and the hallway of the garage, as well as to supply certain additional materials. Plaintiff was required to do this work without written directions. It did so at an extra expense plus a reasonable profit for the work, totaling $829.90.
These items total $4,816.21; they are meritorious and, in our opinion, should be allowed. They are clearly extras under the contract. They could have, and we think should have, been ordered in writing and paid for under the contract.
The next item (finding XVIII) relates to two toilet bowls in the hospital building which froze and burst while it was unoccupied and before plaintiff was authorized to commence work under the contract. Plaintiff was in no wise responsible for this; however, the Government required it without
The next item (finding XVIII (a)) relates to the extra ■work performed in connection with the door to the shower bath in the garage. The Government requested plaintiff to install a larger door to the shower which plaintiff agreed to do without extra charge. After this work had been performed and the door hung in accordance with the Government’s direction, the Government decided that the door was too large and required plaintiff to remove it. This necessitated extra work and expense of cutting the plaster, moving the door jamb, and repainting. Plaintiff requested that the expense of making the change be allowed as an extra, but the Government refused and threatened to withhold payments with the result that plaintiff performed this extra work at an additional cost plus a reasonable profit therefor of $117.81. Plaintiff was right, and we think this item should be allowed.
The next two items of claims presented amount to $3,841.59 and $3,995.70 (findings XIX and XX).
The first results from increased cost to plaintiff in doing the -work due to delays, extra work, and unreasonable requirements of the Government which caused a portion of the work to be carried beyond July 10, 1920, when there was an increase in the cost of materials, labor, and supplies, whereas, had it not been for these delays, the extra work and other requirements of the Government, the work called for by the contract could and would have been completed on or before July 10, 1920. This extra expense was in addition to the various items hereinbefore specifically mentioned.
The second item is made up of extra expense for wages of plumbers, tile setters, and marble workers after July 1, 1920, brought about by the decrease in efficiency of labor on account of conditions inherent in union labor at that time arising from an investigation being conducted by the State of New York. This item of expense was also in addition to all others herein mentioned.
The basis of this claim is that had plaintiff not been delayed by the Government the work called for by the con
The last two items of the claim, finding XXI, amounting to $8,207, are made up of additional overhead expense not directly chargeable to any of the items hereinbefore discussed and additional wages paid to the superintendent, foreman, timekeeper, watchman, etc., and for increased telephone and other charges. These expenses were actually incurred by plaintiff in performing the work required of it under the contract, but the evidence fails to establish that these expenses arose from causes for which the Government was responsible and for which it should, in equity, be charged. The record does not establish with any definiteness just what brought about this additional expense but it seems clear to us that the expense was not brought about by any direct act of the Government. On the contrary the record as a whole justifies the conclusion that this expense was brought about by delays arising from disturbed labor conditions in plaintiff’s plant, as well as in the industries generally from which material required in the performance of this contract was obtained.
The evidence establishes beyond question that the actual cost to plaintiff of performing the work required by the Government in the remodeling of the hospital in question, exclusive of the cost of extras ordered in writing and paid for, and exclusive of profit, was $34,765.54 in excess of the contract price of $124,950 paid, and the evidence further establishes to our satisfaction that the actual value to the Government of the work performed by plaintiff in remodeling the hospital, as required by the Government and of which the Government received the benefit, was $19,032.78 in excess of the amount allowed and paid under the contract. This amount includes the reasonable profit of $844.64 on fourteen certain items of extra services and for materials purchased and supplied by plaintiff outside the contract provisions for which the Government, we think, erroneously refused to give written orders. The amount of $19,032.78
The foregoing findings and this memorandum of our conclusions with respect to the various items of the claim presented by plaintiff will be certified to the Senate in accordance with Senate Resolution 326.